Differences between revisions 5 and 6
Revision 5 as of 2014-06-29 18:23:06
Size: 245
Comment:
Revision 6 as of 2014-06-29 18:35:59
Size: 623
Comment:
Deletions are marked like this. Additions are marked like this.
Line 2: Line 2:

 * IFI will be purchased from UF
 * Assembly on the PSL table is scheduled in 2014/11
 * Installation will be in 2015/3
 * IFI will not be suspended but directly put on the IFI table
 * A pair of unsuspended steering mirrors (STM) will be used for the beam centering
Line 6: Line 12:

[[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=2474|STM noise]] (2014/6)

Input Faraday Isolator

  • IFI will be purchased from UF
  • Assembly on the PSL table is scheduled in 2014/11
  • Installation will be in 2015/3
  • IFI will not be suspended but directly put on the IFI table
  • A pair of unsuspended steering mirrors (STM) will be used for the beam centering

Report by Kentaro (2014/1)

IFI Layout (2014/6)

STM noise (2014/6)

KAGRA/Subgroups/IOO/IFI (last edited 2016-03-22 22:37:39 by YuKataoka)