Line 3: Line 3:
[[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=2104|Report by Kentaro]] (2014/1)  * IFI will be purchased from UF
 * Assembly on the PSL table is scheduled in 2014/11
 * Installation will be in 2015/3
 * IFI will not be suspended but directly put on the IFI table
 * A pair of unsuspended steering mirrors (STM) will be used for the beam centering
Line 5: Line 9:
[[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=2486|IFI Layout]] (2014/6)  * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=2104|First Report by Somiya in 2014/1]]
 * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=2192|Magnetic noise estimation by Somiya]]
 * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=2227|Scatter-light noise estimation by Somiya]]
 * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=2330|Apperture noise estimation by Somiya]]
 * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=2486|IFI Layout by Somiya]]
 * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=2474|STM noise by Nakano]]

Input Faraday Isolator