Differences between revisions 7 and 9 (spanning 2 versions)
Revision 7 as of 2014-06-29 18:44:31
Size: 1013
Comment:
Revision 9 as of 2016-03-10 03:15:12
Size: 1283
Editor: YuKataoka
Comment:
Deletions are marked like this. Additions are marked like this.
Line 2: Line 2:
= Parameter =
 * Weight : 18.1kg
 * Size : L=647.7mm, W=177.8mm, H=133.2mm
[[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3538|IFI Drawing]]
= Current Status =
 * IFI was purchased from UF
 * IFI was completed to Assemble on the PSL table in 2015/11
 * Installation was completed in 2015/11
 * Alignment was completed in 2016/02
 * IFI will not be suspended but directly put on the IFI table
 * A pair of unsuspended steering mirrors (STM) have been used for the beam centering
Line 3: Line 14:
 * IFI will be purchased from UF
 * Assembly on the PSL table is scheduled in 2014/11
 * Installation will be in 2015/3
 * IFI will not be suspended but directly put on the IFI table
 * A pair of unsuspended steering mirrors (STM) will be used for the beam centering
=== Related documents ===

Input Faraday Isolator

Parameter

  • Weight : 18.1kg
  • Size : L=647.7mm, W=177.8mm, H=133.2mm

IFI Drawing

Current Status

  • IFI was purchased from UF
  • IFI was completed to Assemble on the PSL table in 2015/11
  • Installation was completed in 2015/11
  • Alignment was completed in 2016/02
  • IFI will not be suspended but directly put on the IFI table
  • A pair of unsuspended steering mirrors (STM) have been used for the beam centering

KAGRA/Subgroups/IOO/IFI (last edited 2016-03-22 22:37:39 by YuKataoka)