Line 2: Line 2:

 * IFI will be purchased from UF
 * Assembly on the PSL table is scheduled in 2014/11
 * Installation will be in 2015/3
= Parameter =
 * Weight : 18.1kg
 * Size : L=647.7mm, W=177.8mm, H=133.2mm
[[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3538|IFI Drawing]]
= Current Status =
 * IFI was purchased from UF
 * IFI was completed to Assemble on the PSL table in 2015/11
 * Installation was completed in 2015/11
 * Alignment was completed in 2016/02
Line 7: Line 12:
 * A pair of unsuspended steering mirrors (STM) will be used for the beam centering  * A pair of unsuspended steering mirrors (STM) have been used for the beam centering

Input Faraday Isolator

Parameter

  • Weight : 18.1kg
  • Size : L=647.7mm, W=177.8mm, H=133.2mm

IFI Drawing

Current Status

  • IFI was purchased from UF
  • IFI was completed to Assemble on the PSL table in 2015/11
  • Installation was completed in 2015/11
  • Alignment was completed in 2016/02
  • IFI will not be suspended but directly put on the IFI table
  • A pair of unsuspended steering mirrors (STM) have been used for the beam centering