Regular Meeting 0806
Participants
kokeyama, Ge, Fujii, Fujikawa, Uehara, 佐藤、大河、鈴木、菅井, Nakano, Nagano
Announcement
Registration for the F2F meeting in August at Toyama U is open (link, 3 IOO slots)
Schedule for Phase-2
Chart https://docs.google.com/spreadsheets/d/19xC6L0TJmjMtuSEoGe7Z7SVVK78MD4S52m0Hm0C5IKw/edit
Punchlist https://docs.google.com/spreadsheets/d/1hHhXEqC5DwITUqYFjVgB-ZnAb53V1C4OlaeYNqjblCI/edit#gid=0
Report from the Last 2 weeks
- IMC - MC REFL dust shield installation started.
- MZM - Fixed the optical setup. Servo was broken and repaired.
- RAM - Fixed the optical setup. Cablings are on going.
- HPL - HPL delivered to PSL from Hongo. Several troubles happened. HPL and FI, output collimator lens are now installed. Linear polarization is coming from the laser. Mode matched to PMC, and PMC was locked. Mode matching should be modified.
- PEM - Accelerometers were installed on the periscopes. 5 accs are installed in the PSL now.
Plans for the coming 2 weeks
- IMC - finish the mount swapping. Power adjustment system on REFL. Coil drivers swap. Dust shield after F2F meeting. Remote control for the PZT mirrors.
- RAM - Cabling, construct the digital model. Take the beat btw 80MHz modulated beam.
- MZM - Lock the MZI. Start the measurement by taking the beat between 80MHz modulated beam.
- PEM - check the correlations with PSL.
- HPL - Prof. Mio will visit on Tue. Prep for 10W? Assemble the enclosure.
- IMMT2 - fix the folded oplev for IMMT2 and measure the TF.
- Miyoki-san is planning to test the water cooler beam dump. Cable rack will be installed below the PSL-IMC beam tube. (ALS installation will start this week in the PSL/googles needed)
Visitors
- GE, guiguo from WIPM
- Uehara-san
- (PEM) Fujikawa-kun, Mori-san, Kaihotsu-kun
- (Laser) Tue: Prof. Mio, Tahara-kun, Sakakibara-kun
- Anna from Sep 5th
Absence
- Yamakoh in Norikura on Mon and Tue
Next meeting
- Aug 20th