bKAGRA Phase 1 Initial Alignment
Commissioners at the site
- Type-Bp team: Shoda (absent in the week of 10/10), Miyo (absent from 10/19), Arai
- Type-B team: Mark (absent during 10/15-24), Fabian, Enzo
- Kokeyama (absent during 10/15-10/31), Enomoto (10/10-13, 10/16-20), Nakano (basically at the site), Izumi (absent on 10/4 and occasionally), Inoue (10/3-5?, 10/16?-), Yokozawa (10/9-20), Aso (10/16-), Michimura (10/3-4)
Schedule
- Oct 2 - 6: Initial alignment preparations (Kokeyama, Michimura)
- some dirty work in the SR2 area
- Oct 10 - 13: Initial alignment to PR3 (Kokeyama)
- Oct 16 - 20: Initial alignment to EX (Inoue, Izumi)
- Oct 23 - 27: Initial alignment to EY (Inoue, Izumi)
- Oct 30 - : Beam position measurements (Uchiyama)
iKAGRA Commissioning
Test run summary
Summary of iKAGRA Test Run March 2016 (JGW-T1605101)
Summary of iKAGRA Test Run March 2017 (JGW-T1605177)
TO DO after Apr test run but before iKAGRA ends
- oplev stability, noise measurements (with mirror fixed)
- scattering noise investigation
- PR3 height check
- measure PR3 suspension Q values
- save and note all the interferometer settings, configurations to write a paper
investigate 15 Hz resonance in ETM suspensions 1301
- calibration confirmation, actuator efficiency measurement(including BS)
- stop the clean booth filters and see if the noise changes
- take noise spectra using an analog FFT analyser up to very high frequency. Compare it with the spectrum taken by the digital system
- measure the accurate position of the mirrors (PR3 and BS) with respect to the markings on the floor
- remove REFL aluminum foil and see if the noise changes
- measure Schnupp asymmetry (how?)
Some issues to remember
unknown 550 Hz LPF in MICH OLTF klog #1645
why sensitivity improved over 2 kHz? after Apr 12 commissioning break? (klog #1531)
- why there are no 60 Hz line noise?
- RF PD issues: breaks easily with single power supply, Dsub 9pin connectors don't fix tight
Commissioners at the site
Mar 31 to Apr 11: http://densuke.biz/list?cd=RGpffPNuJw6xwBMF
Mar 7 to Mar 20: http://densuke.biz/list?cd=wgUxhq6KHdfsUnWW
April Commissioning Break (Apr 1-10)
- Apr 1 (Fri) GV opening day (Leader: Kokeyama)
k1boot backup (Miyakawa) 1326
time adjust k1fw0, k1fw1 (Miyakawa) 1328
- fix GE RFM on k1ex0 (Miyakawa)
reboot and update display driver for monitor PCs (Miyakawa) 1328
unreel power cables around racks (Kokeyama,Michimura) 1330
close IOO rack (Kokeyama,Michimura)
open GVs close to IXA,IYA (Saito) 1336
restore Michelson (Kokeyama,Michimura,Komori) 1336
- cable making for seismometer,thermometer,hygrometer,barometer(Hayama)
- Apr 2 (Sat) Spare day (Leader: Michimura)
Apr 3 (Sun) PSL&IMC day (Leader: Michimura)
collect broken EXA viewport (Akutsu, Michimura)
replace ETMX oplev collimator holders (Akutsu,Michimura) 1346
longer cable for IMC EOM (Nakano,Enomoto) DONE
re-alignment of PMC (Nakano,Enomoto) 1349
replace TTFSS to the modified one (Nakano,Enomoto) 1348
- investigate TTFSS Interface slow nob (Nakano,Enomoto) [later]
put the PMC control back to remote mode (Nakano,Enomoto) 1351
replace 100 kHz LPF for IMC lock from SR560 to RC circuit, modify connectors to screw cables (Enomoto,Nakano) 1350 1359
- make sure history of circuits are properly recorded on JGW Doc S numbers (Nakano,Enomoto)
put N terminators for RF distributor (Michimura) 1352
replace Dsub 9pin cable for IMC REFL RF PD connected in series with longer one (Komori,Miyamoto) 1352
protect IMC picomotor drivers and devices on the floor (Komori,Miyamoto) 1352
tighten SMA cable connectors with wrench (Nakano,Enomoto,Komori,Miyamoto) 1352
- measure ADC noise, PD dark noise (Komori,Michimura)
Apr 4 (Mon) PSL&IMC day (Leader: Michimura)
- connect PR2-BS bellows, VAC safety check (Saito, from PM)
BS coil balance, sign check (Komori,Uchiyama,Ohishi) 1354
update PMC guardian (Nakano) 1353
- check lens/mirror mounts, pedestals, forks are properly fixed tight (Nakano,Enomoto,Nagano)
put orange and yellow power cables between PR3 to IOO rack (Hasegawa)
fix IQ demodulator being too hot issue (Nakano,Enomoto,Nagano) 1401 [later]
- replace IMC coil differential cable with diff to single board (Nakano,Enomoto,Nagano) [later]
- cancel --- (ETMY PZT cabling (Ohishi,Miyoki,Miyo)
change ETMY oplev to folded configuration, redo calibration (Akutsu,Miyamoto) 1355, 1374
replace PR3 oplev collimator holder (Akutsu,Hasegawa) 1356
- fix conlog, install printer, install VNC (Sasaki)
make a state monitor on MEDM (Miyo) [LOCK_STATUS guardian]
- cable making for seismometer,thermometer,hygrometer,barometer(Hayama)
Apr 5 (Tue) PSL&IMC, PR3 day (Leader: Kawamura)
connect PR2-BS bellows, VAC safety check (Saito)
re-alignment of IMC and stabilize IMC lock (Nakano,Enomoto,Nagano) 1386,1499
RF PD for Michelson REFL (Hasegawa,Miyamoto,Nagano) 1377
- fix PR3 LVDT WD issue (Shoda,Fujii,Miyakawa) [later]
PR3 LVDT offload with fishing lod (Shoda,Fujii) 1382
- install the remote control system of the motors (Shoda,Fujii) [later]
check PR3 yaw picomotor (Shoda,Fujii) IT WORKS
change ETMX oplev to folded configuration, redo calibration (Akutsu,Miyamoto) 1406, 1436
safety check (Kawamura,Awai,Kimura,Tomaru) [partially done]
- add memories on k1fw0, k1fw1, k1dc0 for 64sec frame data (Miyakawa)
- install PEMs, GIF maintenance (Araya,Miyo,Hayama,Kataoka)
- Apr 6 (Wed) PR3, MICH day (Leader: Michimura)
- connect PR2-BS bellows, VAC safety check (Saito, until AM)
Simulink NoiseBudget for Michelson (Shimoda,Michimura,Kokeyama)
online calibration model, UGF servo (Aritomi,Michimura,Kokeyama) 1425, 1472
auto alignment (Miyo,Aso,Kokeyama) 1484 [for IMC]
- replace IMC, BS oplev collimator holders (Akutsu) [CANCEL]
water gage setting (Hayama, Kataoka) 1392
- realtime model for environmental sensors (Hayama, ?)
- Apr 7 (Thu) MICH day (Leader: Aso)
- feedback MICH also to BS (Aso) [CANCEL]
try to use REFL RF PD for MICH lock (Nakano) 1388
- cancel --- (feedback MICH also to ETMY PZT (Miyo,Aso))
- realtime model for environmental sensors (Hayama, ?)
- Apr 8 (Fri) MICH day (Leader: Kokeyama)
- make MICH_LOCK guardian script to check calibration filter settings (Miyo)
- Apr 9 (Sat) Spare day
- Apr 10 (Sun) Spare day
- Apr 11 (Mon) Start test run 2nd round
TO DO before Apr 11
- PSL, IMC related
- re-alignment of PMC
- put the PMC control back to remote mode [Apr 1-5]
- replace TTFSS to the modified one [Apr 1-5]
- Add a monitor of laser power right after the laser [Apr 1-5]
- re-alignment of IMC and stabilize IMC lock [Apr 6-8]
- replace 100 kHz LPF for IMC lock, from SR560 to RC circuit [Apr 6-8]
replace IMC REFL RF PD to the one which has DC output DONE
- close IOO rack (may need RF distributor modification) [Apr 1-5]
- fix IQ demodulator being too hot issue [Apr 1-5]
- Exchange holders for IMC oplev light sources (if required) [Apr 4-7]
- ISC related
- BS Oplev QPD diagonalization, coil balance [Apr 1-5, no laser hazard]
- EX, EY coil balance at higher frequency (~10Hz. Done for DC) [Apr 1-5]
- EY PZT [Apr 1-5]
IMC and MICH Noise budgeting using Simulink NoiseBudget [Apr 6-8]
- auto alignment for IMC and MICH (dithering? ASC?) [Apr 6-8]
- make online calibration model, UGF servo (auto gain adjuster using calibration lines) [Apr 6-8]
- feedback MICH also to BS to increase MICH feedback range [Apr 6-8]
- Exchange holders for BS/ETMs oplev light sources (if required) [Apr 4-7]
DetChar related
- lock loss investigation (use 3/25-3/11 data)
- AOS related
- replace EXA end viewport for EX2 camera [Apr 4-7]
- VAC related
- connect PR2-BS duct [Apr 4-5, no laser hazard]
- open the GVs (close to IXA,IYA) to reduce clipping [Apr 1]
- check anchors and bolts for vacuum tanks [Apr 4-5]
- PR3 related
- PR3 transfer function measurements, noise measurements [Apr 5-6]
- PR3 LVDT offload with fishing lod [Apr 5-6]
- fix PR3 LVDT WD issue [Apr 5-6]
- install the remote control system of the motors [Apr 5-6]
- check PR3 yaw picomotor [Apr 5-6]
- Exchange holder for PR3 oplev light source (if required) [Apr 4-7]
- DGS related
- k1boot backup [Apr 1, Miyakawa]
- Time adjust on k1fw0, k1fw1 [Apr 1, Miyakawa]
- Add memories on k1fw0, k1fw1, k1dc0 for 64sec frame data[Apr 5-8, Miyakawa]
- Fix camera noise [Kokeyama]
- Fix conlog [Apr 4-8, Sasaki]
- Fix GE RFM on k1ex0 [Apr 1, Miyakawa]
- Reboot and update display driver for monitor PCs [Apr 1, Miyakawa]
- Install printer of 2nd floor for k1ctr0-4 [Apr 4-8, Sasaki]
- Install VNC for monitor k1mon0-2 [Apr 4-8, Sasaki]
- Make a state monitor on MEDM [Apr 4-8, Miyo]
- General
Safety check (reported by Awai) [Apr 1-10]
Initial alignment work
first week
- Feb 24 (Wed): Miyakawa, Kokeyama, Aso
PR2 install (Aso et al) DONE
- PR3 install (Shoda et al)
- Feb 25 (Thu): Miyakawa, Kokeyama, Aso
- Feb 26 (Fri): Miyakawa, Kokeyama
- Feb 27 (Sat): Kokeyama, Akutsu
install Y end machines (Kokeyama) DONE
EY camera (Kokeyama) DONE
- Feb 28 (Sun):
- Feb 29 (Mon): Miyakawa, Kokeyama, Michimura, Enomoto, Kataoka, Akutsu, Aso
- IMC stabilization (Kawamura,Enomoto)
finish IMMT1T QPD setup (Akutsu,Michimura,Kataoka) DONE
- prepare for IXC+IXA vent (Kimura)
peel PR3 first contact (Shoda,Fujii) DONE
check PR2 picomotors (Aso,Miyo) DONE
EX camera (Kokeyama) DONE
install PR2 viewport for the camera, and the camera (Akutsu,Kokeyama) half done (no camera yet)
- Mar 01 (Tue): Miyakawa, Kokeyama, Michimura, Enomoto, Kataoka, Akutsu, Aso
turn on PR3 local damping (Shoda,Okutomi,Fujii) DONE
pedestals for PDs (Michimura,Tomaru) ARRIVED
- Mar 02 (Wed): Miyakawa, Kokeyama, Michimura, Enomoto, Akutsu, Aso, Furuhata, Kambara
put PRM-PR3 bellows (MIRAPRO 8:00-11:00) DONE
put BS-IXC bellows (MIRAPRO PM?) DONE
- IMC stabilization (Kawamura,Enomoto)
IXC+IXA vent (Kimura) DONE
finish IXA clean booth clean up, bring clean goods (Kimura,Tomaru) DONE
- peel ETMX first contact and set coils (Ohishi,Shoda,Aso) REMAINING ISSUE
install BS viewports for the oplev and the camera(Akutsu,Michimura,Kambara,Furuhata) half done (45deg issue, IPC issue)
install PR3 viewport for the camera, and the camera (Akutsu,Shoda,Okutomi,Fujii) half done (no camera yet)
k1cam0 and k1cam1 setup (Kokeyama) DONE
DAQ networks for EX and EY (Miyakawa,Kokeyama) DONE
calibrate PR3 oplev (Shoda,Okutomi,Fujii) DONE
- Mar 03 (Thu): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Akutsu, Aso, Furuhata, Kambara
high power IMC (Enomoto) DONE (~850 mW)
PR2 alignment, beam profiling at PR3 half done (beam profiling not yet)
check IMMT2 picomotor (Miyo,Doi) DONE
ETMX,ETMY,BS picomotor (Miyo) mostly DONE (ETMX to be confirmed)
setup PDs at EXA (Akutsu,Fujii) DONE
peel ETMY first contact and set coils (Ohishi,Takahashi) DONE
- PR2, PR3, BS, IMMT1T cameras (Kokeyama) PR2 DONE, BS and PR3 to be done
- ETMX first contact issue: WE DECIDED TO GO WITH REMAINING FIRST CONTACT
- Mar 04 (Fri): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Furuhata, Kambara
PR3 rough alignment into IXA (Michimura,Ushiba,Kuwahara,Okutomi,Kambara,Furuhata) DONE (beam profiling at IXA not yet)
DQ channels for EXA EYA PDs (Kokeyama) Done
fix IPC errors (Miyakawa, Kokeyama) Done
open BS-IXC GV (Saito,Uchiyama,Kimura) DONE
place ND filters to MC_REFL and PMC_TRANS cameras, and check ghost beams (Enomoto) DONE (decreased power to ~250 mW)
- Mar 05 (Sat): Kokeyama, Kataoka
- Mar 06 (Sun): Kataoka
- block PSL beam for VAC work (Uchiyama)
second week
- Mar 07 (Mon)
- beam clipping at BS check, BS rough alignment into Y, IXA beam check with respect to PR3 alignment, beam profiling at IXA?, sweep PR3 at night (Michimura,Ushiba,Kataoka,Kambara,Furuhata,Okutomi)
check ETMX actuation (Ohishi,Takahashi) DONE
calibrate ETMX oplev (Kuwahara) DONE
ETMX picomotor check (Miyo) DONE
install EXA end flange (Tomaru) DONE
calibrate ETMY oplev (Kokeyama,Kuwahara) DONE
PR3 oplev calibration result, check PR3 oplev channels (Kokeyama,Okutomi) DONE
- RFM test between center area and both ends (Kokeyama)
- Mar 08 (Tue)
install BS oplev and calibrate (Akutsu,Hasegawa,Kuwahara) DONE
fine adjustment of PR3 alignment to BS and IXA, Xarm viewport, PR3 sweep to EXA (Michimura,Shoda,Okutomi,Ushiba,Furuhata,Kagawa,Fujisawa) DONE
install EXA end viewport (Akutsu,Hasegawa,Kuwahara) DONE
check ETMY actuation (Ohishi,Takahashi,Kuwahara) DONE
install EYA end flange (Kimura,Tomaru) DONE
VIS guardian (Shoda,Okutomi,Kokeyama) DONE
- Mar 09 (Wed)
BS actuation check (Ushiba,Kuwahara,Furuhata) DONE
setup PD at EYA (Akutsu,Hasegawa,Kambara) DONE
install EYA end viewport (Akutsu,Hasegawa,Kambara) DONE
take PD from EXA, EXA beam check, ETMX rough alignment (Michimura,Fujii) DONE, DONE
setup PD at BS (Akutsu,Hasegawa,Kambara) DONE
EXA end, EYA end cameras (Kokeyama) DONE
RFM network between center and Yend (Kokeyama) DONE
- Mar 10 (Thu)
connect BS-IYC (MIRAPRO) DONE
start EXA evacuation (Kimura) DONE
block Y arm beam (Akutsu,Kambara,Hasegawa) investigated
LED from EYA to BS (Miyoki) failed -> try brighter LED
- Mar 11 (Fri)
connect PR2-PR3 duct (MIRAPRO) DONE
- sweep ETMX and wait for AS PD to get any signal (Miyo,Hasegawa)
- sweep BS and wait for ETMY PD to get any signal (Fujii,Furuhata)
- Mar 12 (Sat)
- partially connect PR2-BS duct (MIRAPRO)
- LED from EYA to BS (Tomaru,Uchiyama,Hasegawa,Miyo) failed
- Mar 13 (Sun)
BS PD to face X (Uchiyama) DONE
third week
EXA vent (Saito,Tomaru) DONE
ETMX alignment re-adjustment (Uchiyama) DONE
viewport for IXA (Michimura) DONE
BS alignment re-adjustment (Uchiyama?) DONE
ETMY oplev re-calibration DONE
IYA vent (Kimura?) DONE
get the beam back to IFI and then to REFL DONE
set up REFL optics and cabling DONE
beam to and from X and Y arms DONE
TO DO before Mar 26
insert PR2-BS duct Done
- evacuate IXA and IYA (we do not evacuate anything in March)
- IOO cabling check (?)
- get PMC back to remote control mode (To be done by Apr 11)
coil balancing for BS, ETMX, ETMY Done except BS
coil offload with picomotors for BS, ETMX, ETMY (and PR3 yaw) Done
oplev damping for BS, ETMX, ETMY, PR3 Done
more alignment to maximize contrast, clipping investigation Done, 75%MAX
measure power at REFL port from X and Y arms Done
install REFL camera (steal IMMT1T camera) Done
check LSC model Done
lock Michelson and measure openloop transfer function Done
MICH guardian Done
calibration model Done
get strain spectrum Done
What we do
- confirm mirror actuators (picomotors, coils, OSEMs) work from digital system
- prepare oplevs and cameras
- prepare RT models and MEDM screens for mirrors and LSC
- prepare feet for large beam profiler
- prepare pedestals for DC PDs
- REFL optics
- stable operation of IMC
initial alignment: JGW-T1604823
- lock 3km Michelson
LCGT Commissioning plan (As of Aug 2012)
Schedule
- List up issues to be addressed for installation procedure (September)
- Detailed installation plan (October)
- General Commissioning Strategy (how to deploy man power etc) (by the end of November)
List of items necessary for commissioning
The List is Here.