| = LCGT Commissioning plan = | = iKAGRA Commissioning = == Commissioners at the site == * Feb 24 (Wed): Miyakawa, Kokeyama, Aso(PR2 install) * Feb 25 (Thu): Miyakawa, Kokeyama, Aso(PR2 install) * Feb 26 (Fri): Miyakawa, Kokeyama * Feb 27 (Sat): Kokeyama, Akutsu * Feb 28 (Sun): * Feb 29 (Mon): Miyakawa, Kokeyama, Michimura, Enomoto, Kataoka, Aso * IMC stabilization (Kawamura,Enomoto) * finish IMMT1T QPD setup (Akutsu,Michimura) * prepare for IXC+IXA vent (Kimura) * prepare for IXA clean booth cleaning (Michimura,Kataoka) * Mar 01 (Tue): Miyakawa, Kokeyama, Michimura, Enomoto, Kataoka, Aso * IMC stabilization (Kawamura,Enomoto) * IXC+IXA vent (Kimura) * IXA clean booth clean up (Michimura,Kataoka) * Mar 02 (Wed): Miyakawa, Kokeyama, Michimura, Enomoto, Akutsu, Aso * IMC stabilization (Kawamura,Enomoto) * Mar 03 (Thu): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Akutsu, Aso * Mar 04 (Fri): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Aso * Mar 05 (Sat): Kokeyama, Kataoka * Mar 06 (Sun): Kataoka * Mar 07 (Mon): Miyakawa, Kokeyama, Michimura, Ushiba, Kuwahara, Kataoka, Akutsu, Aso * Mar 08 (Tue): Miyakawa, Kokeyama, Michimura, Ushiba, Kuwahara, Kataoka, Akutsu, Aso * Mar 09 (Wed): Miyakawa, Kokeyama, Michimura, Ushiba, Kuwahara, Akutsu, Aso * Mar 10 (Thu): Miyakawa, Kokeyama, Michimura, Akutsu, Aso * Mar 11 (Fri): Miyakawa, Kokeyama, Michimura, Akutsu?, Aso * Mar 12 (Sat): Kokeyama * Mar 13 (Sun): * Mar 14 (Mon): Miyakawa, Kokeyama, Aso * Mar 15 (Tue): Miyakawa, Michimura, Aso == What we do == * confirm mirror actuators (picomotors, coils, OSEMs) work from digital system * prepare oplevs and cameras * prepare RT models and MEDM screens for mirrors and LSC * prepare feet, pedestals for large beam profiler and DC PDs * REFL optics * stable operation of IMC * initial alignment: [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/DocDB/ShowDocument?docid=4823|JGW-T1604823]] * lock 3km Michelson ---- = LCGT Commissioning plan (As of Aug 2012) = == Schedule == * List up issues to be addressed for installation procedure (September) * Detailed installation plan (October) * General Commissioning Strategy (how to deploy man power etc) (by the end of November) |
iKAGRA Commissioning
Commissioners at the site
- Feb 24 (Wed): Miyakawa, Kokeyama, Aso(PR2 install)
- Feb 25 (Thu): Miyakawa, Kokeyama, Aso(PR2 install)
- Feb 26 (Fri): Miyakawa, Kokeyama
- Feb 27 (Sat): Kokeyama, Akutsu
- Feb 28 (Sun):
- Feb 29 (Mon): Miyakawa, Kokeyama, Michimura, Enomoto, Kataoka, Aso
- IMC stabilization (Kawamura,Enomoto)
- finish IMMT1T QPD setup (Akutsu,Michimura)
- prepare for IXC+IXA vent (Kimura)
- prepare for IXA clean booth cleaning (Michimura,Kataoka)
- Mar 01 (Tue): Miyakawa, Kokeyama, Michimura, Enomoto, Kataoka, Aso
- IMC stabilization (Kawamura,Enomoto)
- IXC+IXA vent (Kimura)
- IXA clean booth clean up (Michimura,Kataoka)
- Mar 02 (Wed): Miyakawa, Kokeyama, Michimura, Enomoto, Akutsu, Aso
- IMC stabilization (Kawamura,Enomoto)
- Mar 03 (Thu): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Akutsu, Aso
- Mar 04 (Fri): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Aso
- Mar 05 (Sat): Kokeyama, Kataoka
- Mar 06 (Sun): Kataoka
- Mar 07 (Mon): Miyakawa, Kokeyama, Michimura, Ushiba, Kuwahara, Kataoka, Akutsu, Aso
- Mar 08 (Tue): Miyakawa, Kokeyama, Michimura, Ushiba, Kuwahara, Kataoka, Akutsu, Aso
- Mar 09 (Wed): Miyakawa, Kokeyama, Michimura, Ushiba, Kuwahara, Akutsu, Aso
- Mar 10 (Thu): Miyakawa, Kokeyama, Michimura, Akutsu, Aso
- Mar 11 (Fri): Miyakawa, Kokeyama, Michimura, Akutsu?, Aso
- Mar 12 (Sat): Kokeyama
- Mar 13 (Sun):
- Mar 14 (Mon): Miyakawa, Kokeyama, Aso
- Mar 15 (Tue): Miyakawa, Michimura, Aso
What we do
- confirm mirror actuators (picomotors, coils, OSEMs) work from digital system
- prepare oplevs and cameras
- prepare RT models and MEDM screens for mirrors and LSC
- prepare feet, pedestals for large beam profiler and DC PDs
- REFL optics
- stable operation of IMC
initial alignment: JGW-T1604823
- lock 3km Michelson
LCGT Commissioning plan (As of Aug 2012)
Schedule
- List up issues to be addressed for installation procedure (September)
- Detailed installation plan (October)
- General Commissioning Strategy (how to deploy man power etc) (by the end of November)
List of items necessary for commissioning
The List is Here.