= LCGT Commissioning plan = | = iKAGRA Commissioning = == Commissioners at the site == * Feb 24 (Wed): Miyakawa, Kokeyama, Aso * PR2 install (Aso et al) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=825|DONE]] * PR3 install (Shoda et al) * Feb 25 (Thu): Miyakawa, Kokeyama, Aso * PR3 install (Shoda et al) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=831|DONE]] * oplev and camera for ETMX (Akutsu,Kokeyama) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=834|DONE]] (not calibrated yet) * Feb 26 (Fri): Miyakawa, Kokeyama * PR3 install, check signals (Shoda et al) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=852|DONE]] * install X end machines (Kokeyama) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=853|DONE]] * oplev and camera for ETMY (Akutsu,Simon) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=854|DONE]] (not calibrated yet) * Feb 27 (Sat): Kokeyama, Akutsu * install Y end machines (Kokeyama) * EY camera (Kokeyama) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=856|DONE]] * Feb 28 (Sun): * Feb 29 (Mon): Miyakawa, Kokeyama, Michimura, Enomoto, Kataoka, Akutsu, Aso * IMC stabilization (Kawamura,Enomoto) * finish IMMT1T QPD setup (Akutsu,Michimura,Kataoka) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=862|DONE]] * prepare for IXC+IXA vent (Kimura) * peel PR3 first contact (Shoda,Fujii) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=863|DONE]] * check PR2 picomotors (Aso,Miyo) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=869|DONE]] * EX camera (Kokeyama) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=865|DONE]] === we are here! === * Mar 01 (Tue): Miyakawa, Kokeyama, Michimura, Enomoto, Kataoka, Akutsu, Aso * IMC stabilization (Kawamura,Enomoto) * IXC+IXA vent (Kimura) * peel ETMX first contact (Ohishi,Shoda,Aso) * |-) install BS viewports for the oplev and the camera(Akutsu,Michimura,Kataoka) * |-) install PR2 viewport for the camera, and the camera (Akutsu,SOMEONE!) * check PR3 actuation model, calibrate PR3 oplev and turn on local damping (Shoda,Okutomi,Fujii) * Mar 02 (Wed): Miyakawa, Kokeyama, Michimura, Enomoto, Akutsu, Aso, Furuhata, Kambara * put PRM-PR3 bellows (MIRAPRO 8:00-11:00) * put BS-IXC, BS-IYC bellows (MIRAPRO PM?) * finish IMC stabilization (Kawamura,Enomoto) * finish IXA clean booth clean up (Kimura) * bring clean goods to IXA (Michimura) * peel ETMY first contact (Ohishi,Shoda,Aso) * |-) install EXA flange (Akutsu,Michimura) * |-) install PR3 viewport for the camera, and the camera (Akutsu,Shoda,Okutomi) * k1cam0 and k1cam1 setup (Kokeyama,SOMEONE!) * ETMX picomotor (Miyo) * Mar 03 (Thu): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Akutsu, Aso, Furuhata, Kambara * check IMMT2 picomotor (Miyo,Doi) * [[KAGRA/Subgroups/MIF/Commissioning/PR2Alignment|PR2 alignment]] * [[KAGRA/Subgroups/MIF/Commissioning/PR2Alignment|beam profiling]] at PR3 * Mar 04 (Fri): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Aso, Furuhata, Kambara * PR3 rough alignment into IXA (Michimura,Ushiba,Furuhata,Kambara) * beam profiling at IXA (Michimura,Ushiba,Furuhata,Kambara) * pedestals for PDs should be delivered at this point (Michimura,Tomaru) * setup PDs at EXA, EYA (Michimura,Kokeyama,Kuwahara) * DQ channels should work at this point (Miyakawa,Kokeyama) * Mar 05 (Sat): Kokeyama, Kataoka * sweep PR3 and wait for end PDs to get any signal (automatically or Kataoka?) * Mar 06 (Sun): Kataoka * sweep PR3 and wait for end PDs to get any signal (automatically or Kataoka?) * Mar 07 (Mon): Miyakawa, Kokeyama, Michimura, Ushiba, Kuwahara, Kataoka, Akutsu, Aso, Furuhata, Kambara * beam profiling at EXA (Michimura,Ushiba,Furuhata,Kambara) * check ETMX actuation model and calibrate ETMX oplev (Akutsu,Kokeyama,Kuwahara) * take PD from EXA and setup PD at BS (Michimura,Kokeyama,Kuwahara) * Mar 08 (Tue): Miyakawa, Kokeyama, Michimura, Ushiba, Kuwahara, Kataoka, Akutsu, Aso, Furuhata, Kambara * sweep ETMX and wait for AS PD to get any signal (automatically or ?) * set up REFL optics and cabling (Michimura) * get the beam back to IFI and then to REFL (Ushiba,Kataoka) * check BS actuation model and calibrate BS oplev (Akutsu,Kokeyama,Kuwahara) * Mar 09 (Wed): Miyakawa, Kokeyama, Michimura, Ushiba, Kuwahara, Akutsu, Aso, Furuhata, Kambara * block X beam (Michimura) * sweep BS and wait for ETMY PD to get any signal (automatically or ?) * some spare time * Mar 10 (Thu): Miyakawa, Kokeyama, Michimura, Akutsu, Aso, Furuhata, Kambara * sweep BS and wait for ETMY PD to get any signal (automatically or ?) * check ETMY actuation model and calibrate ETMY oplev (Akutsu,Kokeyama,Michimura) * Mar 11 (Fri): Miyakawa, Kokeyama, Michimura, Akutsu?, Aso, Furuhata, Kambara * sweep ETMY and wait for AS PD to get any signal (automatically or ?) * get fringe at REFL/AS (Michimura,Akutsu?) * Mar 12 (Sat): Kokeyama * close everything and slowly start evacuation * Mar 13 (Sun): * Mar 14 (Mon): Miyakawa, Kokeyama, Michimura?, Aso * check LSC model * lock Michelson and measure openloop transfer function * check calibration model * get strain spectrum * Mar 15 (Tue): Miyakawa, Michimura, Aso * start observation == What we do == * confirm mirror actuators (picomotors, coils, OSEMs) work from digital system * prepare oplevs and cameras * prepare RT models and MEDM screens for mirrors and LSC * prepare feet for large beam profiler * prepare pedestals for DC PDs * REFL optics * stable operation of IMC * initial alignment: [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/DocDB/ShowDocument?docid=4823|JGW-T1604823]] * lock 3km Michelson ---- = LCGT Commissioning plan (As of Aug 2012) = == Schedule == * List up issues to be addressed for installation procedure (September) * Detailed installation plan (October) * General Commissioning Strategy (how to deploy man power etc) (by the end of November) |
Line 4: | Line 109: |
The List is [[/ItemList|Here]]. |
The List is [[KAGRA/Subgroups/MIF/Commissioning/ItemList|Here]]. |
iKAGRA Commissioning
Commissioners at the site
- Feb 24 (Wed): Miyakawa, Kokeyama, Aso
PR2 install (Aso et al)
DONE
- PR3 install (Shoda et al)
- Feb 25 (Thu): Miyakawa, Kokeyama, Aso
- Feb 26 (Fri): Miyakawa, Kokeyama
- Feb 27 (Sat): Kokeyama, Akutsu
- install Y end machines (Kokeyama)
EY camera (Kokeyama)
DONE
- Feb 28 (Sun):
- Feb 29 (Mon): Miyakawa, Kokeyama, Michimura, Enomoto, Kataoka, Akutsu, Aso
we are here!
- Mar 01 (Tue): Miyakawa, Kokeyama, Michimura, Enomoto, Kataoka, Akutsu, Aso
- IMC stabilization (Kawamura,Enomoto)
- IXC+IXA vent (Kimura)
- peel ETMX first contact (Ohishi,Shoda,Aso)
install BS viewports for the oplev and the camera(Akutsu,Michimura,Kataoka)
install PR2 viewport for the camera, and the camera (Akutsu,SOMEONE!)
- check PR3 actuation model, calibrate PR3 oplev and turn on local damping (Shoda,Okutomi,Fujii)
- Mar 02 (Wed): Miyakawa, Kokeyama, Michimura, Enomoto, Akutsu, Aso, Furuhata, Kambara
- put PRM-PR3 bellows (MIRAPRO 8:00-11:00)
- put BS-IXC, BS-IYC bellows (MIRAPRO PM?)
- finish IMC stabilization (Kawamura,Enomoto)
- finish IXA clean booth clean up (Kimura)
- bring clean goods to IXA (Michimura)
- peel ETMY first contact (Ohishi,Shoda,Aso)
install EXA flange (Akutsu,Michimura)
install PR3 viewport for the camera, and the camera (Akutsu,Shoda,Okutomi)
- k1cam0 and k1cam1 setup (Kokeyama,SOMEONE!)
- ETMX picomotor (Miyo)
- Mar 03 (Thu): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Akutsu, Aso, Furuhata, Kambara
- check IMMT2 picomotor (Miyo,Doi)
beam profiling at PR3
- Mar 04 (Fri): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Aso, Furuhata, Kambara
- PR3 rough alignment into IXA (Michimura,Ushiba,Furuhata,Kambara)
- beam profiling at IXA (Michimura,Ushiba,Furuhata,Kambara)
- pedestals for PDs should be delivered at this point (Michimura,Tomaru)
- setup PDs at EXA, EYA (Michimura,Kokeyama,Kuwahara)
- DQ channels should work at this point (Miyakawa,Kokeyama)
- Mar 05 (Sat): Kokeyama, Kataoka
- sweep PR3 and wait for end PDs to get any signal (automatically or Kataoka?)
- Mar 06 (Sun): Kataoka
- sweep PR3 and wait for end PDs to get any signal (automatically or Kataoka?)
- Mar 07 (Mon): Miyakawa, Kokeyama, Michimura, Ushiba, Kuwahara, Kataoka, Akutsu, Aso, Furuhata, Kambara
- beam profiling at EXA (Michimura,Ushiba,Furuhata,Kambara)
- check ETMX actuation model and calibrate ETMX oplev (Akutsu,Kokeyama,Kuwahara)
- take PD from EXA and setup PD at BS (Michimura,Kokeyama,Kuwahara)
- Mar 08 (Tue): Miyakawa, Kokeyama, Michimura, Ushiba, Kuwahara, Kataoka, Akutsu, Aso, Furuhata, Kambara
- sweep ETMX and wait for AS PD to get any signal (automatically or ?)
- set up REFL optics and cabling (Michimura)
- get the beam back to IFI and then to REFL (Ushiba,Kataoka)
- check BS actuation model and calibrate BS oplev (Akutsu,Kokeyama,Kuwahara)
- Mar 09 (Wed): Miyakawa, Kokeyama, Michimura, Ushiba, Kuwahara, Akutsu, Aso, Furuhata, Kambara
- block X beam (Michimura)
- sweep BS and wait for ETMY PD to get any signal (automatically or ?)
- some spare time
- Mar 10 (Thu): Miyakawa, Kokeyama, Michimura, Akutsu, Aso, Furuhata, Kambara
- sweep BS and wait for ETMY PD to get any signal (automatically or ?)
- check ETMY actuation model and calibrate ETMY oplev (Akutsu,Kokeyama,Michimura)
- Mar 11 (Fri): Miyakawa, Kokeyama, Michimura, Akutsu?, Aso, Furuhata, Kambara
- sweep ETMY and wait for AS PD to get any signal (automatically or ?)
- get fringe at REFL/AS (Michimura,Akutsu?)
- Mar 12 (Sat): Kokeyama
- close everything and slowly start evacuation
- Mar 13 (Sun):
- Mar 14 (Mon): Miyakawa, Kokeyama, Michimura?, Aso
- check LSC model
- lock Michelson and measure openloop transfer function
- check calibration model
- get strain spectrum
- Mar 15 (Tue): Miyakawa, Michimura, Aso
- start observation
What we do
- confirm mirror actuators (picomotors, coils, OSEMs) work from digital system
- prepare oplevs and cameras
- prepare RT models and MEDM screens for mirrors and LSC
- prepare feet for large beam profiler
- prepare pedestals for DC PDs
- REFL optics
- stable operation of IMC
initial alignment: JGW-T1604823
- lock 3km Michelson
LCGT Commissioning plan (As of Aug 2012)
Schedule
- List up issues to be addressed for installation procedure (September)
- Detailed installation plan (October)
- General Commissioning Strategy (how to deploy man power etc) (by the end of November)
List of items necessary for commissioning
The List is Here.