Differences between revisions 1 and 70 (spanning 69 versions)
Revision 1 as of 2012-08-03 15:02:29
Size: 115
Editor: YoichiAso
Comment:
Revision 70 as of 2016-03-03 17:33:30
Size: 6903
Comment:
Deletions are marked like this. Additions are marked like this.
Line 1: Line 1:
= LCGT Commissioning plan = = iKAGRA Commissioning =
== Commissioners at the site ==
 * Feb 24 (Wed): Miyakawa, Kokeyama, Aso
  * PR2 install (Aso et al) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=825|DONE]]
  * PR3 install (Shoda et al)
 * Feb 25 (Thu): Miyakawa, Kokeyama, Aso
  * PR3 install (Shoda et al) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=831|DONE]]
  * oplev and camera for ETMX (Akutsu,Kokeyama) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=834|DONE]] (not calibrated yet)
 * Feb 26 (Fri): Miyakawa, Kokeyama
  * PR3 install, check signals (Shoda et al) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=852|DONE]]
  * install X end machines (Kokeyama) B)  [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=853|DONE]]
  * oplev and camera for ETMY (Akutsu,Simon) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=854|DONE]] (not calibrated yet)
 * Feb 27 (Sat): Kokeyama, Akutsu
  * install Y end machines (Kokeyama) B) DONE?
  * EY camera (Kokeyama) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=856|DONE]]
 * Feb 28 (Sun):
 * Feb 29 (Mon): Miyakawa, Kokeyama, Michimura, Enomoto, Kataoka, Akutsu, Aso
  * IMC stabilization (Kawamura,Enomoto)
  * finish IMMT1T QPD setup (Akutsu,Michimura,Kataoka) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=862|DONE]]
  * prepare for IXC+IXA vent (Kimura)
  * peel PR3 first contact (Shoda,Fujii) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=863|DONE]]
  * check PR2 picomotors (Aso,Miyo) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=869|DONE]]
  * EX camera (Kokeyama) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=865|DONE]]
  * install PR2 viewport for the camera, and the camera (Akutsu,Kokeyama) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=866|half done]] (no camera yet)
 * Mar 01 (Tue): Miyakawa, Kokeyama, Michimura, Enomoto, Kataoka, Akutsu, Aso
  * turn on PR3 local damping (Shoda,Okutomi,Fujii) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=872|DONE]]
  * pedestals for PDs (Michimura,Tomaru) B) ARRIVED
 * Mar 02 (Wed): Miyakawa, Kokeyama, Michimura, Enomoto, Akutsu, Aso, Furuhata, Kambara
  * put PRM-PR3 bellows (MIRAPRO 8:00-11:00) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=878|DONE]]
  * put BS-IXC bellows (MIRAPRO PM?) B) DONE?
  * IMC stabilization (Kawamura,Enomoto)
  * IXC+IXA vent (Kimura) B) DONE
  * finish IXA clean booth clean up, bring clean goods (Kimura,Tomaru) B) DONE
  * peel ETMX first contact and set coils (Ohishi,Shoda,Aso) REMAINING ISSUE
  * install BS viewports for the oplev and the camera(Akutsu,Michimura,Kambara,Furuhata) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=882|half done]] (45deg issue, IPC issue)
  * install PR3 viewport for the camera, and the camera (Akutsu,Shoda,Okutomi,Fujii) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=876|half done]] (no camera yet)
  * k1cam0 and k1cam1 setup (Kokeyama) B) DONE
  * DAQ networks for EX and EY (Miyakawa,Kokeyama) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=874|DONE]]
  * calibrate PR3 oplev (Shoda,Okutomi,Fujii) B) DONE
 * Mar 03 (Thu): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Akutsu, Aso, Furuhata, Kambara
  * high power IMC (Enomoto) B) DONE (~850 mW)
  * [[KAGRA/Subgroups/MIF/Commissioning/PR2Alignment|PR2 alignment, beam profiling at PR3]] [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=886|half done]] (beam profiling not yet)
  * check IMMT2 picomotor (Miyo,Doi) B) DONE
  * ETMX,ETMY,BS picomotor (Miyo) B) [[KAGRA/Subgroups/DGS/Projects/PicoMotor|DONE]]

=== we are here! ===



  

  
  * install EXA flanges (Akutsu,Uchiyama,Fujii,Kambara)
  * ETMX first contact issue (Ohishi,Akutsu)
  * PR2, PR3, BS, IMMT1T cameras (Kokeyama)

 * Mar 04 (Fri): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Aso, Furuhata, Kambara
  * [[KAGRA/Subgroups/MIF/Commissioning/iKAGRA0304|PR3 rough alignment into IXA]] (Aso,Michimura,Ushiba,Kuwahara,Okutomi,Kambara)
  * BS rough alignment into Yarm (Aso,Michimura,Ushiba,Kuwahara,Okutomi,Kambara)
  * beam profiling at IXA (Aso,Michimura,Ushiba,Kuwahara,Okutomi,Kambara)
  * setup PDs at EXA, EYA (SOMEONE! Tomaru?,Uchiyama?)
  * peel ETMY first contact and set coils (Ohishi,Shoda)

 * Mar 05 (Sat): Kokeyama, Kataoka
  * sweep PR3 and wait for end PDs to get any signal (automatically or Kataoka?)
 * Mar 06 (Sun): Kataoka
  * sweep PR3 and wait for end PDs to get any signal (automatically or Kataoka?)
 * Mar 07 (Mon): Miyakawa, Kokeyama, Michimura, Ushiba, Kuwahara, Kataoka, Akutsu, Aso, Furuhata, Kambara
  * beam profiling at EXA (Michimura,Ushiba,Furuhata,Kambara)
  * check ETMX actuation model and calibrate ETMX oplev (Akutsu,Kokeyama,Kuwahara)
  * take PD from EXA and setup PD at BS (Michimura,Kokeyama,Kuwahara)
 * Mar 08 (Tue): Miyakawa, Kokeyama, Michimura, Ushiba, Kuwahara, Kataoka, Akutsu, Aso, Furuhata, Kambara
  * sweep ETMX and wait for AS PD to get any signal (automatically or ?)
  * set up REFL optics and cabling (Michimura)
  * get the beam back to IFI and then to REFL (Ushiba,Kataoka)
  * check BS actuation model and calibrate BS oplev (Akutsu,Kokeyama,Kuwahara)
  * install EYA flanges (Akutsu,SOMEONE!)
 * Mar 09 (Wed): Miyakawa, Kokeyama, Michimura, Ushiba, Kuwahara, Akutsu, Aso, Furuhata, Kambara
  * block X beam (Michimura)
  * sweep BS and wait for ETMY PD to get any signal (automatically or ?)
  * some spare time
 * Mar 10 (Thu): Miyakawa, Kokeyama, Michimura, Akutsu, Aso, Furuhata, Kambara
  * sweep BS and wait for ETMY PD to get any signal (automatically or ?)
  * check ETMY actuation model and calibrate ETMY oplev (Akutsu,Kokeyama,Michimura)
 * Mar 11 (Fri): Miyakawa, Kokeyama, Michimura, Akutsu?, Aso, Furuhata, Kambara
  * sweep ETMY and wait for AS PD to get any signal (automatically or ?)
  * get fringe at REFL/AS (Michimura,Akutsu?)
 * Mar 12 (Sat): Kokeyama
  * close everything and slowly start evacuation
 * Mar 13 (Sun):
 * Mar 14 (Mon): Miyakawa, Kokeyama, Michimura?, Aso
  * check LSC model
  * lock Michelson and measure openloop transfer function
  * check calibration model
  * get strain spectrum
 * Mar 15 (Tue): Miyakawa, Michimura, Aso
  * start observation

== What we do ==
 * confirm mirror actuators (picomotors, coils, OSEMs) work from digital system
 * prepare oplevs and cameras
 * prepare RT models and MEDM screens for mirrors and LSC
 * prepare feet for large beam profiler
 * prepare pedestals for DC PDs
 * REFL optics
 * stable operation of IMC
 * initial alignment: [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/DocDB/ShowDocument?docid=4823|JGW-T1604823]]
 * lock 3km Michelson

----

= LCGT Commissioning plan (As of Aug 2012) =
== Schedule ==
 * List up issues to be addressed for installation procedure (September)
 * Detailed installation plan (October)
 * General Commissioning Strategy (how to deploy man power etc) (by the end of November)
Line 4: Line 119:

The List is [[/ItemList|Here]].
The List is [[KAGRA/Subgroups/MIF/Commissioning/ItemList|Here]].

iKAGRA Commissioning

Commissioners at the site

  • Feb 24 (Wed): Miyakawa, Kokeyama, Aso
    • PR2 install (Aso et al) B) DONE

    • PR3 install (Shoda et al)
  • Feb 25 (Thu): Miyakawa, Kokeyama, Aso
    • PR3 install (Shoda et al) B) DONE

    • oplev and camera for ETMX (Akutsu,Kokeyama) B) DONE (not calibrated yet)

  • Feb 26 (Fri): Miyakawa, Kokeyama
    • PR3 install, check signals (Shoda et al) B) DONE

    • install X end machines (Kokeyama) B)  DONE

    • oplev and camera for ETMY (Akutsu,Simon) B) DONE (not calibrated yet)

  • Feb 27 (Sat): Kokeyama, Akutsu
    • install Y end machines (Kokeyama) B) DONE?

    • EY camera (Kokeyama) B) DONE

  • Feb 28 (Sun):
  • Feb 29 (Mon): Miyakawa, Kokeyama, Michimura, Enomoto, Kataoka, Akutsu, Aso
    • IMC stabilization (Kawamura,Enomoto)
    • finish IMMT1T QPD setup (Akutsu,Michimura,Kataoka) B) DONE

    • prepare for IXC+IXA vent (Kimura)
    • peel PR3 first contact (Shoda,Fujii) B) DONE

    • check PR2 picomotors (Aso,Miyo) B) DONE

    • EX camera (Kokeyama) B) DONE

    • install PR2 viewport for the camera, and the camera (Akutsu,Kokeyama) half done (no camera yet)

  • Mar 01 (Tue): Miyakawa, Kokeyama, Michimura, Enomoto, Kataoka, Akutsu, Aso
    • turn on PR3 local damping (Shoda,Okutomi,Fujii) B) DONE

    • pedestals for PDs (Michimura,Tomaru) B) ARRIVED

  • Mar 02 (Wed): Miyakawa, Kokeyama, Michimura, Enomoto, Akutsu, Aso, Furuhata, Kambara
    • put PRM-PR3 bellows (MIRAPRO 8:00-11:00) B) DONE

    • put BS-IXC bellows (MIRAPRO PM?) B) DONE?

    • IMC stabilization (Kawamura,Enomoto)
    • IXC+IXA vent (Kimura) B) DONE

    • finish IXA clean booth clean up, bring clean goods (Kimura,Tomaru) B) DONE

    • peel ETMX first contact and set coils (Ohishi,Shoda,Aso) REMAINING ISSUE
    • install BS viewports for the oplev and the camera(Akutsu,Michimura,Kambara,Furuhata) half done (45deg issue, IPC issue)

    • install PR3 viewport for the camera, and the camera (Akutsu,Shoda,Okutomi,Fujii) half done (no camera yet)

    • k1cam0 and k1cam1 setup (Kokeyama) B) DONE

    • DAQ networks for EX and EY (Miyakawa,Kokeyama) B) DONE

    • calibrate PR3 oplev (Shoda,Okutomi,Fujii) B) DONE

  • Mar 03 (Thu): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Akutsu, Aso, Furuhata, Kambara

we are here!

  • install EXA flanges (Akutsu,Uchiyama,Fujii,Kambara)
  • ETMX first contact issue (Ohishi,Akutsu)
  • PR2, PR3, BS, IMMT1T cameras (Kokeyama)
  • Mar 04 (Fri): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Aso, Furuhata, Kambara
    • PR3 rough alignment into IXA (Aso,Michimura,Ushiba,Kuwahara,Okutomi,Kambara)

    • BS rough alignment into Yarm (Aso,Michimura,Ushiba,Kuwahara,Okutomi,Kambara)
    • beam profiling at IXA (Aso,Michimura,Ushiba,Kuwahara,Okutomi,Kambara)
    • setup PDs at EXA, EYA (SOMEONE! Tomaru?,Uchiyama?)
    • peel ETMY first contact and set coils (Ohishi,Shoda)
  • Mar 05 (Sat): Kokeyama, Kataoka
    • sweep PR3 and wait for end PDs to get any signal (automatically or Kataoka?)
  • Mar 06 (Sun): Kataoka
    • sweep PR3 and wait for end PDs to get any signal (automatically or Kataoka?)
  • Mar 07 (Mon): Miyakawa, Kokeyama, Michimura, Ushiba, Kuwahara, Kataoka, Akutsu, Aso, Furuhata, Kambara
    • beam profiling at EXA (Michimura,Ushiba,Furuhata,Kambara)
    • check ETMX actuation model and calibrate ETMX oplev (Akutsu,Kokeyama,Kuwahara)
    • take PD from EXA and setup PD at BS (Michimura,Kokeyama,Kuwahara)
  • Mar 08 (Tue): Miyakawa, Kokeyama, Michimura, Ushiba, Kuwahara, Kataoka, Akutsu, Aso, Furuhata, Kambara
    • sweep ETMX and wait for AS PD to get any signal (automatically or ?)
    • set up REFL optics and cabling (Michimura)
    • get the beam back to IFI and then to REFL (Ushiba,Kataoka)
    • check BS actuation model and calibrate BS oplev (Akutsu,Kokeyama,Kuwahara)
    • install EYA flanges (Akutsu,SOMEONE!)
  • Mar 09 (Wed): Miyakawa, Kokeyama, Michimura, Ushiba, Kuwahara, Akutsu, Aso, Furuhata, Kambara
    • block X beam (Michimura)
    • sweep BS and wait for ETMY PD to get any signal (automatically or ?)
    • some spare time
  • Mar 10 (Thu): Miyakawa, Kokeyama, Michimura, Akutsu, Aso, Furuhata, Kambara
    • sweep BS and wait for ETMY PD to get any signal (automatically or ?)
    • check ETMY actuation model and calibrate ETMY oplev (Akutsu,Kokeyama,Michimura)
  • Mar 11 (Fri): Miyakawa, Kokeyama, Michimura, Akutsu?, Aso, Furuhata, Kambara
    • sweep ETMY and wait for AS PD to get any signal (automatically or ?)
    • get fringe at REFL/AS (Michimura,Akutsu?)
  • Mar 12 (Sat): Kokeyama
    • close everything and slowly start evacuation
  • Mar 13 (Sun):
  • Mar 14 (Mon): Miyakawa, Kokeyama, Michimura?, Aso
    • check LSC model
    • lock Michelson and measure openloop transfer function
    • check calibration model
    • get strain spectrum
  • Mar 15 (Tue): Miyakawa, Michimura, Aso
    • start observation

What we do

  • confirm mirror actuators (picomotors, coils, OSEMs) work from digital system
  • prepare oplevs and cameras
  • prepare RT models and MEDM screens for mirrors and LSC
  • prepare feet for large beam profiler
  • prepare pedestals for DC PDs
  • REFL optics
  • stable operation of IMC
  • initial alignment: JGW-T1604823

  • lock 3km Michelson


LCGT Commissioning plan (As of Aug 2012)

Schedule

  • List up issues to be addressed for installation procedure (September)
  • Detailed installation plan (October)
  • General Commissioning Strategy (how to deploy man power etc) (by the end of November)

List of items necessary for commissioning

The List is Here.

KAGRA/Subgroups/MIF/Commissioning (last edited 2017-10-03 09:39:55 by YutaMichimura)