| == TO DO before Mar 26 == * insert PR2-BS duct * evacuate IXA and IYA * IOO cabling check * get PMC back to remote control mode * coil balancing for BS, ETMX, ETMY * coil offload with picomotors for BS, ETMX, ETMY (and PR3 yaw) * oplev damping for BS, ETMX, ETMY * more alignment to maximize contrast, clipping investigation * measure power at REFL port from X and Y arms * install REFL camera (steal IMMT1T camera) * check LSC model * lock Michelson and measure openloop transfer function * MICH guardian * calibration model * get strain spectrum | |
| Line 26: | Line 10: | 
| * open the GVs | |
| Line 33: | Line 18: | 
| * put the PMC control back to remote mode * stabilize IMC lock == TO DO before Mar 26 == * insert PR2-BS duct B) Done * evacuate IXA and IYA (we do not evacuate anything in March) * IOO cabling check (?) * get PMC back to remote control mode (To be done by Apr 11) * coil balancing for BS, ETMX, ETMY B) Done except BS * coil offload with picomotors for BS, ETMX, ETMY (and PR3 yaw) B) Done * oplev damping for BS, ETMX, ETMY, PR3 B) Done * more alignment to maximize contrast, clipping investigation B) Done, 75%MAX * measure power at REFL port from X and Y arms B) Done * install REFL camera (steal IMMT1T camera) B) Done * check LSC model B) Done * lock Michelson and measure openloop transfer function B) Done * MICH guardian B) Done * calibration model (Partially Done) * get strain spectrum (Done one shot, done for offline) | 
iKAGRA Commissioning
Commissioners at the site
http://densuke.biz/list?cd=wgUxhq6KHdfsUnWW
TO DO before Apr 11
- IMC and MICH Noise budgeting using Simulink NoiseBudget 
- replace EXA end viewport for EX2 camera
- check anchors and bolts for vacuum tanks
- open the GVs
- oplev stability, noise measurements (with mirror fixed)
- scattering noise investigation
- PR3 transfer function measurements, noise measurements
- IMC ASC
- EX, EY coil balance at higher frequency (~10Hz. Done for DC)
- Make online calibration model
- BS Oplev QPD diagonalization, coil balance
- put the PMC control back to remote mode
- stabilize IMC lock
TO DO before Mar 26
- insert PR2-BS duct  Done Done
- evacuate IXA and IYA (we do not evacuate anything in March)
- IOO cabling check (?)
- get PMC back to remote control mode (To be done by Apr 11)
- coil balancing for BS, ETMX, ETMY  Done except BS Done except BS
- coil offload with picomotors for BS, ETMX, ETMY (and PR3 yaw)  Done Done
- oplev damping for BS, ETMX, ETMY, PR3  Done Done
- more alignment to maximize contrast, clipping investigation  Done, 75%MAX Done, 75%MAX
- measure power at REFL port from X and Y arms  Done Done
- install REFL camera (steal IMMT1T camera)  Done Done
- check LSC model  Done Done
- lock Michelson and measure openloop transfer function  Done Done
- MICH guardian  Done Done
- calibration model (Partially Done)
- get strain spectrum (Done one shot, done for offline)
Initial alignment work
first week
- Feb 24 (Wed): Miyakawa, Kokeyama, Aso - PR2 install (Aso et al)  DONE DONE
- PR3 install (Shoda et al)
 
- Feb 25 (Thu): Miyakawa, Kokeyama, Aso
- Feb 26 (Fri): Miyakawa, Kokeyama
- Feb 27 (Sat): Kokeyama, Akutsu - install Y end machines (Kokeyama)  DONE DONE
- EY camera (Kokeyama)  DONE DONE
 
- Feb 28 (Sun):
- Feb 29 (Mon): Miyakawa, Kokeyama, Michimura, Enomoto, Kataoka, Akutsu, Aso - IMC stabilization (Kawamura,Enomoto)
- finish IMMT1T QPD setup (Akutsu,Michimura,Kataoka)  DONE DONE
- prepare for IXC+IXA vent (Kimura)
- peel PR3 first contact (Shoda,Fujii)  DONE DONE
- check PR2 picomotors (Aso,Miyo)  DONE DONE
- EX camera (Kokeyama)  DONE DONE
- install PR2 viewport for the camera, and the camera (Akutsu,Kokeyama) half done (no camera yet) 
 
- Mar 01 (Tue): Miyakawa, Kokeyama, Michimura, Enomoto, Kataoka, Akutsu, Aso - turn on PR3 local damping (Shoda,Okutomi,Fujii)  DONE DONE
- pedestals for PDs (Michimura,Tomaru)  ARRIVED ARRIVED
 
- Mar 02 (Wed): Miyakawa, Kokeyama, Michimura, Enomoto, Akutsu, Aso, Furuhata, Kambara - put PRM-PR3 bellows (MIRAPRO 8:00-11:00)  DONE DONE
- put BS-IXC bellows (MIRAPRO PM?)  DONE DONE
- IMC stabilization (Kawamura,Enomoto)
- IXC+IXA vent (Kimura)  DONE DONE
- finish IXA clean booth clean up, bring clean goods (Kimura,Tomaru)  DONE DONE
- peel ETMX first contact and set coils (Ohishi,Shoda,Aso) REMAINING ISSUE
- install BS viewports for the oplev and the camera(Akutsu,Michimura,Kambara,Furuhata) half done (45deg issue, IPC issue) 
- install PR3 viewport for the camera, and the camera (Akutsu,Shoda,Okutomi,Fujii) half done (no camera yet) 
- k1cam0 and k1cam1 setup (Kokeyama)  DONE DONE
- DAQ networks for EX and EY (Miyakawa,Kokeyama)  DONE DONE
- calibrate PR3 oplev (Shoda,Okutomi,Fujii)  DONE DONE
 
- Mar 03 (Thu): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Akutsu, Aso, Furuhata, Kambara - high power IMC (Enomoto)  DONE (~850 mW) DONE (~850 mW)
- PR2 alignment, beam profiling at PR3 half done (beam profiling not yet) 
- check IMMT2 picomotor (Miyo,Doi)  DONE DONE
- ETMX,ETMY,BS picomotor (Miyo)  mostly DONE (ETMX to be confirmed) mostly DONE (ETMX to be confirmed)
- setup PDs at EXA (Akutsu,Fujii)  DONE DONE
- peel ETMY first contact and set coils (Ohishi,Takahashi)  DONE DONE
- PR2, PR3, BS, IMMT1T cameras (Kokeyama) PR2 DONE, BS and PR3 to be done
- ETMX first contact issue: WE DECIDED TO GO WITH REMAINING FIRST CONTACT
 
- Mar 04 (Fri): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Furuhata, Kambara - PR3 rough alignment into IXA (Michimura,Ushiba,Kuwahara,Okutomi,Kambara,Furuhata)  DONE (beam profiling at IXA not yet) DONE (beam profiling at IXA not yet)
- DQ channels for EXA EYA PDs (Kokeyama)  Done Done
- fix IPC errors (Miyakawa, Kokeyama)  Done Done
- open BS-IXC GV (Saito,Uchiyama,Kimura)  DONE DONE
- place ND filters to MC_REFL and PMC_TRANS cameras, and check ghost beams (Enomoto)  DONE (decreased power to ~250 mW) DONE (decreased power to ~250 mW)
 
- Mar 05 (Sat): Kokeyama, Kataoka
- Mar 06 (Sun): Kataoka - block PSL beam for VAC work (Uchiyama)
 
second week
- Mar 07 (Mon) - beam clipping at BS check, BS rough alignment into Y, IXA beam check with respect to PR3 alignment, beam profiling at IXA?, sweep PR3 at night (Michimura,Ushiba,Kataoka,Kambara,Furuhata,Okutomi)
- check ETMX actuation (Ohishi,Takahashi)  DONE DONE
- calibrate ETMX oplev (Kuwahara)  DONE DONE
- ETMX picomotor check (Miyo)  DONE DONE
- install EXA end flange (Tomaru)  DONE DONE
- calibrate ETMY oplev (Kokeyama,Kuwahara)  DONE DONE
- PR3 oplev calibration result, check PR3 oplev channels (Kokeyama,Okutomi)  DONE DONE
- RFM test between center area and both ends (Kokeyama)
 
- Mar 08 (Tue) - install BS oplev and calibrate (Akutsu,Hasegawa,Kuwahara)  DONE DONE
- fine adjustment of PR3 alignment to BS and IXA, Xarm viewport, PR3 sweep to EXA (Michimura,Shoda,Okutomi,Ushiba,Furuhata,Kagawa,Fujisawa)  DONE DONE
- install EXA end viewport (Akutsu,Hasegawa,Kuwahara)  DONE DONE
- check ETMY actuation (Ohishi,Takahashi,Kuwahara)  DONE DONE
- install EYA end flange (Kimura,Tomaru)  DONE DONE
- VIS guardian (Shoda,Okutomi,Kokeyama)  DONE DONE
 
- Mar 09 (Wed) - BS actuation check (Ushiba,Kuwahara,Furuhata)  DONE DONE
- setup PD at EYA (Akutsu,Hasegawa,Kambara)  DONE DONE
- install EYA end viewport (Akutsu,Hasegawa,Kambara)  DONE DONE
- take PD from EXA, EXA beam check, ETMX rough alignment (Michimura,Fujii)  DONE, DONE DONE, DONE
- setup PD at BS (Akutsu,Hasegawa,Kambara)  DONE DONE
- EXA end, EYA end cameras (Kokeyama)  DONE DONE
- RFM network between center and Yend (Kokeyama)  DONE DONE
 
- Mar 10 (Thu) - connect BS-IYC (MIRAPRO)  DONE DONE
- start EXA evacuation (Kimura)  DONE DONE
- block Y arm beam (Akutsu,Kambara,Hasegawa) investigated 
- LED from EYA to BS (Miyoki) failed -> try brighter LED 
 
- Mar 11 (Fri) - connect PR2-PR3 duct (MIRAPRO)  DONE DONE
- sweep ETMX and wait for AS PD to get any signal (Miyo,Hasegawa)
- sweep BS and wait for ETMY PD to get any signal (Fujii,Furuhata)
 
- Mar 12 (Sat) - partially connect PR2-BS duct (MIRAPRO)
- LED from EYA to BS (Tomaru,Uchiyama,Hasegawa,Miyo) failed
 
- Mar 13 (Sun) - BS PD to face X (Uchiyama)  DONE DONE
 
third week
- EXA vent (Saito,Tomaru)  DONE DONE
- ETMX alignment re-adjustment (Uchiyama)  DONE DONE
- viewport for IXA (Michimura)  DONE DONE
- BS alignment re-adjustment (Uchiyama?)  DONE DONE
- ETMY oplev re-calibration  DONE DONE
- IYA vent (Kimura?)  DONE DONE
- get the beam back to IFI and then to REFL  DONE DONE
- set up REFL optics and cabling  DONE DONE
- beam to and from X and Y arms  DONE DONE
What we do
- confirm mirror actuators (picomotors, coils, OSEMs) work from digital system
- prepare oplevs and cameras
- prepare RT models and MEDM screens for mirrors and LSC
- prepare feet for large beam profiler
- prepare pedestals for DC PDs
- REFL optics
- stable operation of IMC
- initial alignment: JGW-T1604823 
- lock 3km Michelson
LCGT Commissioning plan (As of Aug 2012)
Schedule
- List up issues to be addressed for installation procedure (September)
- Detailed installation plan (October)
- General Commissioning Strategy (how to deploy man power etc) (by the end of November)
List of items necessary for commissioning
The List is Here.