Size: 5365
Comment:
|
Size: 5361
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 32: | Line 32: |
* Mar 03 (Thu): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Akutsu, Aso, Furuhata?, Kambara? | * Mar 03 (Thu): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Akutsu, Aso, Furuhata, Kambara |
Line 36: | Line 36: |
* Mar 04 (Fri): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Aso, Furuhata?, Kambara? | * Mar 04 (Fri): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Aso, Furuhata, Kambara |
iKAGRA Commissioning
Commissioners at the site
- Feb 24 (Wed): Miyakawa, Kokeyama, Aso
PR2 install (Aso et al)
DONE
- PR3 install (Shoda et al)
- Feb 25 (Thu): Miyakawa, Kokeyama, Aso
- Feb 26 (Fri): Miyakawa, Kokeyama
- Feb 27 (Sat): Kokeyama, Akutsu
- install Y end machines (Kokeyama)
- Feb 28 (Sun):
- Feb 29 (Mon): Miyakawa, Kokeyama, Michimura, Enomoto, Kataoka, Akutsu, Aso
- IMC stabilization (Kawamura,Enomoto)
finish IMMT1T QPD setup (Akutsu,Michimura,Kataoka)
DONE
install BS viewports for the oplev and the camera(Akutsu,Michimura,Kataoka)
- prepare for IXC+IXA vent (Kimura)
- Mar 01 (Tue): Miyakawa, Kokeyama, Michimura, Enomoto, Kataoka, Akutsu, Aso
- IMC stabilization (Kawamura,Enomoto)
- IXC+IXA vent (Kimura)
- some digital work, oplev calibration (Michimura,Kataoka)
Install PR2 viewport for the camera, and the camera (Akutsu,SOMEONE!)
Install PR3 viewport for the camera, and the camera (Akutsu,SOMEONE!)
- Mar 02 (Wed): Miyakawa, Kokeyama, Michimura, Enomoto, Akutsu, Aso
- finish IMC stabilization (Kawamura,Enomoto)
- check PR2 picomotors (Aso)
- finish IXA clean booth clean up (Kimura)
- some digital work (Michimura)
- Mar 03 (Thu): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Akutsu, Aso, Furuhata, Kambara
PR2 alignment (Michimura,Ushiba,Furuhata,Kambara)
beam profiling at PR3 (Michimura,Ushiba,Furuhata,Kambara)
- check PR3 actuation model and calibrate PR3 oplev (Akutsu,Shoda,Kokeyama,Kuwahara)
- Mar 04 (Fri): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Aso, Furuhata, Kambara
- PR3 rough alignment into IXA (Michimura,Ushiba,Furuhata,Kambara)
- beam profiling at IXA (Michimura,Ushiba,Furuhata,Kambara)
- pedestals for PDs should be delivered at this point (Michimura,Tomaru)
- setup PDs at EXA, EYA (Michimura,Kokeyama,Kuwahara)
- DQ channels should work at this point (Miyakawa,Kokeyama)
- Mar 05 (Sat): Kokeyama, Kataoka
- sweep PR3 and wait for end PDs to get any signal (automatically or Kataoka?)
- Mar 06 (Sun): Kataoka
- sweep PR3 and wait for end PDs to get any signal (automatically or Kataoka?)
- Mar 07 (Mon): Miyakawa, Kokeyama, Michimura, Ushiba, Kuwahara, Kataoka, Akutsu, Aso
- beam profiling at EXA (Michimura,Ushiba,Furuhata,Kambara)
- check ETMX actuation model and calibrate ETMX oplev (Akutsu,Kokeyama,Kuwahara)
- take PD from EXA and setup PD at BS (Michimura,Kokeyama,Kuwahara)
- Mar 08 (Tue): Miyakawa, Kokeyama, Michimura, Ushiba, Kuwahara, Kataoka, Akutsu, Aso
- sweep ETMX and wait for AS PD to get any signal (automatically or ?)
- set up REFL optics and cabling (Michimura)
- get the beam back to IFI and then to REFL (Ushiba,Kataoka)
- check BS actuation model and calibrate BS oplev (Akutsu,Kokeyama,Kuwahara)
- Mar 09 (Wed): Miyakawa, Kokeyama, Michimura, Ushiba, Kuwahara, Akutsu, Aso
- block X beam (Michimura)
- sweep BS and wait for ETMY PD to get any signal (automatically or ?)
- some spare time
- Mar 10 (Thu): Miyakawa, Kokeyama, Michimura, Akutsu, Aso
- sweep BS and wait for ETMY PD to get any signal (automatically or ?)
- check ETMY actuation model and calibrate ETMY oplev (Akutsu,Kokeyama,Michimura)
- Mar 11 (Fri): Miyakawa, Kokeyama, Michimura, Akutsu?, Aso
- sweep ETMY and wait for AS PD to get any signal (automatically or ?)
- get fringe at REFL/AS (Michimura,Akutsu?)
- Mar 12 (Sat): Kokeyama
- close everything and slowly start evacuation
- Mar 13 (Sun):
- Mar 14 (Mon): Miyakawa, Kokeyama, Michimura?, Aso
- check LSC model
- lock Michelson and measure openloop transfer function
- check calibration model
- get strain spectrum
- Mar 15 (Tue): Miyakawa, Michimura, Aso
- start observation
What we do
- confirm mirror actuators (picomotors, coils, OSEMs) work from digital system
- prepare oplevs and cameras
- prepare RT models and MEDM screens for mirrors and LSC
- prepare feet for large beam profiler
- prepare pedestals for DC PDs
- REFL optics
- stable operation of IMC
initial alignment: JGW-T1604823
- lock 3km Michelson
LCGT Commissioning plan (As of Aug 2012)
Schedule
- List up issues to be addressed for installation procedure (September)
- Detailed installation plan (October)
- General Commissioning Strategy (how to deploy man power etc) (by the end of November)
List of items necessary for commissioning
The List is Here.