iKAGRA Commissioning
Commissioners at the site
- Feb 24 (Wed): Miyakawa, Kokeyama, Aso
PR2 install (Aso et al)
DONE
- PR3 install (Shoda et al)
- Feb 25 (Thu): Miyakawa, Kokeyama, Aso
- Feb 26 (Fri): Miyakawa, Kokeyama
- Feb 27 (Sat): Kokeyama, Akutsu
- install Y end machines (Kokeyama)
- Feb 28 (Sun):
- Feb 29 (Mon): Miyakawa, Kokeyama, Michimura, Enomoto, Kataoka, Akutsu, Aso
- Mar 01 (Tue): Miyakawa, Kokeyama, Michimura, Enomoto, Kataoka, Akutsu, Aso
- IMC stabilization (Kawamura,Enomoto)
- IXC+IXA vent (Kimura)
- peel ETMX first contact (Ohishi,Shoda,Aso?)
install BS viewports for the oplev and the camera(Akutsu,Michimura,Kataoka)
Install PR2 viewport for the camera, and the camera (Akutsu,SOMEONE!)
Install PR3 viewport for the camera, and the camera (Akutsu,SOMEONE!)
- check PR3 actuation model, calibrate PR3 oplev and turn on local damping (Shoda,Okutomi,Fujii)
- Mar 02 (Wed): Miyakawa, Kokeyama, Michimura, Enomoto, Akutsu, Aso
- finish IMC stabilization (Kawamura,Enomoto)
check PR2 picomotors (Aso)
DONE
- finish IXA clean booth clean up (Kimura)
- some digital work (Michimura)
- Mar 03 (Thu): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Akutsu, Aso, Furuhata, Kambara
beam profiling at PR3
- Mar 04 (Fri): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Aso, Furuhata, Kambara
- PR3 rough alignment into IXA (Michimura,Ushiba,Furuhata,Kambara)
- beam profiling at IXA (Michimura,Ushiba,Furuhata,Kambara)
- pedestals for PDs should be delivered at this point (Michimura,Tomaru)
- setup PDs at EXA, EYA (Michimura,Kokeyama,Kuwahara)
- DQ channels should work at this point (Miyakawa,Kokeyama)
- Mar 05 (Sat): Kokeyama, Kataoka
- sweep PR3 and wait for end PDs to get any signal (automatically or Kataoka?)
- Mar 06 (Sun): Kataoka
- sweep PR3 and wait for end PDs to get any signal (automatically or Kataoka?)
- Mar 07 (Mon): Miyakawa, Kokeyama, Michimura, Ushiba, Kuwahara, Kataoka, Akutsu, Aso
- beam profiling at EXA (Michimura,Ushiba,Furuhata,Kambara)
- check ETMX actuation model and calibrate ETMX oplev (Akutsu,Kokeyama,Kuwahara)
- take PD from EXA and setup PD at BS (Michimura,Kokeyama,Kuwahara)
- Mar 08 (Tue): Miyakawa, Kokeyama, Michimura, Ushiba, Kuwahara, Kataoka, Akutsu, Aso
- sweep ETMX and wait for AS PD to get any signal (automatically or ?)
- set up REFL optics and cabling (Michimura)
- get the beam back to IFI and then to REFL (Ushiba,Kataoka)
- check BS actuation model and calibrate BS oplev (Akutsu,Kokeyama,Kuwahara)
- Mar 09 (Wed): Miyakawa, Kokeyama, Michimura, Ushiba, Kuwahara, Akutsu, Aso
- block X beam (Michimura)
- sweep BS and wait for ETMY PD to get any signal (automatically or ?)
- some spare time
- Mar 10 (Thu): Miyakawa, Kokeyama, Michimura, Akutsu, Aso
- sweep BS and wait for ETMY PD to get any signal (automatically or ?)
- check ETMY actuation model and calibrate ETMY oplev (Akutsu,Kokeyama,Michimura)
- Mar 11 (Fri): Miyakawa, Kokeyama, Michimura, Akutsu?, Aso
- sweep ETMY and wait for AS PD to get any signal (automatically or ?)
- get fringe at REFL/AS (Michimura,Akutsu?)
- Mar 12 (Sat): Kokeyama
- close everything and slowly start evacuation
- Mar 13 (Sun):
- Mar 14 (Mon): Miyakawa, Kokeyama, Michimura?, Aso
- check LSC model
- lock Michelson and measure openloop transfer function
- check calibration model
- get strain spectrum
- Mar 15 (Tue): Miyakawa, Michimura, Aso
- start observation
What we do
- confirm mirror actuators (picomotors, coils, OSEMs) work from digital system
- prepare oplevs and cameras
- prepare RT models and MEDM screens for mirrors and LSC
- prepare feet for large beam profiler
- prepare pedestals for DC PDs
- REFL optics
- stable operation of IMC
initial alignment: JGW-T1604823
- lock 3km Michelson
LCGT Commissioning plan (As of Aug 2012)
Schedule
- List up issues to be addressed for installation procedure (September)
- Detailed installation plan (October)
- General Commissioning Strategy (how to deploy man power etc) (by the end of November)
List of items necessary for commissioning
The List is Here.