| = bKAGRA Phase 1 Initial Alignment = == Commissioners at the site == * Type-Bp team: Shoda (absent in the week of 10/10), Miyo (absent from 10/19), Arai * Type-B team: Mark (absent during 10/15-24), Fabian, Enzo * Kokeyama (absent during 10/15-10/31), Enomoto (10/10-13, 10/16-20), Nakano (basically at the site), Izumi (absent on 10/4 and occasionally), Inoue (10/3-5?, 10/16?-), Yokozawa (10/9-20), Aso (10/16-), Michimura (10/3-4) * [[https://teamup.com/kswnmta8p18h6u1uab|KAGRA Commissioning Planner]] == Schedule == * Oct 2 - 6: Initial alignment preparations (Kokeyama, Michimura) * some dirty work in the SR2 area * Oct 10 - 13: Initial alignment to PR3 (Kokeyama) * Oct 16 - 20: Initial alignment to EX (Inoue, Izumi) * Oct 23 - 27: Initial alignment to EY (Inoue, Izumi) * Oct 30 - : Beam position measurements (Uchiyama) ---- | |
| Line 2: | Line 19: | 
| == Test run summary == * [[KAGRA/Observation/iKAGRA/ChannelList|Channel list]] * Summary of iKAGRA Test Run March 2016 ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/DocDB/ShowDocument?docid=5101|JGW-T1605101]]) * Summary of iKAGRA Test Run March 2017 ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/DocDB/ShowDocument?docid=5177|JGW-T1605177]]) == TO DO after Apr test run but before iKAGRA ends == * oplev stability, noise measurements (with mirror fixed) * scattering noise investigation * PR3 height check * measure PR3 suspension Q values * save and note all the interferometer settings, configurations to write a paper * investigate 15 Hz resonance in ETM suspensions B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1301|1301]] * calibration confirmation, actuator efficiency measurement(including BS) * stop the clean booth filters and see if the noise changes * take noise spectra using an analog FFT analyser up to very high frequency. Compare it with the spectrum taken by the digital system * measure the accurate position of the mirrors (PR3 and BS) with respect to the markings on the floor * remove REFL aluminum foil and see if the noise changes * measure Schnupp asymmetry (how?) === Some issues to remember === * unknown 550 Hz LPF in MICH OLTF [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1645|klog #1645]] * why sensitivity improved over 2 kHz? after Apr 12 commissioning break? ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1531|klog #1531]]) * why there are no 60 Hz line noise? * RF PD issues: breaks easily with single power supply, Dsub 9pin connectors don't fix tight | |
| Line 3: | Line 46: | 
| * Mar 31 to Apr 11: http://densuke.biz/list?cd=RGpffPNuJw6xwBMF * Mar 7 to Mar 20: http://densuke.biz/list?cd=wgUxhq6KHdfsUnWW == April Commissioning Break (Apr 1-10) == * Apr 1 (Fri) GV opening day (Leader: Kokeyama) * k1boot backup (Miyakawa) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1326|1326]] * time adjust k1fw0, k1fw1 (Miyakawa) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1328|1328]] * fix GE RFM on k1ex0 (Miyakawa) * reboot and update display driver for monitor PCs (Miyakawa) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1328|1328]] * unreel power cables around racks (Kokeyama,Michimura) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1330|1330]] * close IOO rack (Kokeyama,Michimura) B) * open GVs close to IXA,IYA (Saito) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1336|1336]] * restore Michelson (Kokeyama,Michimura,Komori) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1336|1336]] * cable making for seismometer,thermometer,hygrometer,barometer(Hayama) * Apr 2 (Sat) Spare day (Leader: Michimura) * redo calibration and noise comparison before and after GV opening (Komori,Michimura) * ETMX, ETMY coil balance (Komori,Michimura) :o [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1340|1340]] * better MICH locking (Komori,Michimura) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1344|1344]] * Apr 3 (Sun) PSL&IMC day (Leader: Michimura) * collect broken EXA viewport (Akutsu, Michimura) B) * replace ETMX oplev collimator holders (Akutsu,Michimura) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1346|1346]] * longer cable for IMC EOM (Nakano,Enomoto) B) DONE * re-alignment of PMC (Nakano,Enomoto) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1349|1349]] * replace TTFSS to the modified one (Nakano,Enomoto) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1348|1348]] * investigate TTFSS Interface slow nob (Nakano,Enomoto) [later] * put the PMC control back to remote mode (Nakano,Enomoto) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1351|1351]] * replace 100 kHz LPF for IMC lock from SR560 to RC circuit, modify connectors to screw cables (Enomoto,Nakano) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1350|1350]] [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1359|1359]] * make sure history of circuits are properly recorded on JGW Doc S numbers (Nakano,Enomoto) * put N terminators for RF distributor (Michimura) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1352|1352]] * replace Dsub 9pin cable for IMC REFL RF PD connected in series with longer one (Komori,Miyamoto) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1352|1352]] * protect IMC picomotor drivers and devices on the floor (Komori,Miyamoto) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1352|1352]] * tighten SMA cable connectors with wrench (Nakano,Enomoto,Komori,Miyamoto) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1352|1352]] * measure ADC noise, PD dark noise (Komori,Michimura) * Apr 4 (Mon) PSL&IMC day (Leader: Michimura) * connect PR2-BS bellows, VAC safety check (Saito, from PM) * BS coil balance, sign check (Komori,Uchiyama,Ohishi) |) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1354|1354]] * update PMC guardian (Nakano) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1353|1353]] * check lens/mirror mounts, pedestals, forks are properly fixed tight (Nakano,Enomoto,Nagano) * put orange and yellow power cables between PR3 to IOO rack (Hasegawa) B) * fix IQ demodulator being too hot issue (Nakano,Enomoto,Nagano) :\ [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1401|1401]] [later] * replace IMC coil differential cable with diff to single board (Nakano,Enomoto,Nagano) [later] * cancel --- (ETMY PZT cabling (Ohishi,Miyoki,Miyo) * change ETMY oplev to folded configuration, redo calibration (Akutsu,Miyamoto) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1355|1355]], [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1374|1374]] * replace PR3 oplev collimator holder (Akutsu,Hasegawa) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1356|1356]] * fix conlog, install printer, install VNC (Sasaki) * make a state monitor on MEDM (Miyo) B) [LOCK_STATUS guardian] * cable making for seismometer,thermometer,hygrometer,barometer(Hayama) * Apr 5 (Tue) PSL&IMC, PR3 day (Leader: Kawamura) * connect PR2-BS bellows, VAC safety check (Saito) B) * re-alignment of IMC and stabilize IMC lock (Nakano,Enomoto,Nagano) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1386|1386]],[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1499|1499]] * RF PD for Michelson REFL (Hasegawa,Miyamoto,Nagano) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1377|1377]] * fix PR3 LVDT WD issue (Shoda,Fujii,Miyakawa) [later] * PR3 LVDT offload with fishing lod (Shoda,Fujii) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1382|1382]] * install the remote control system of the motors (Shoda,Fujii) [later] * check PR3 yaw picomotor (Shoda,Fujii) B) IT WORKS * change ETMX oplev to folded configuration, redo calibration (Akutsu,Miyamoto) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1406|1406]], [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1436|1436]] * safety check (Kawamura,Awai,Kimura,Tomaru) B) [partially done] * add memories on k1fw0, k1fw1, k1dc0 for 64sec frame data (Miyakawa) * install PEMs, GIF maintenance (Araya,Miyo,Hayama,Kataoka) * Apr 6 (Wed) PR3, MICH day (Leader: Michimura) * connect PR2-BS bellows, VAC safety check (Saito, until AM) * Simulink Noise``Budget for Michelson (Shimoda,Michimura,Kokeyama) B) * online calibration model, UGF servo (Aritomi,Michimura,Kokeyama) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1425|1425]], [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1472|1472]] * auto alignment (Miyo,Aso,Kokeyama) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1484|1484]] [for IMC] * replace IMC, BS oplev collimator holders (Akutsu) [CANCEL] * water gage setting (Hayama, Kataoka) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1392|1392]] * realtime model for environmental sensors (Hayama, ?) * Apr 7 (Thu) MICH day (Leader: Aso) * feedback MICH also to BS (Aso) [CANCEL] * try to use REFL RF PD for MICH lock (Nakano) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1388|1388]] * cancel --- (feedback MICH also to ETMY PZT (Miyo,Aso)) * realtime model for environmental sensors (Hayama, ?) * Apr 8 (Fri) MICH day (Leader: Kokeyama) * make MICH_LOCK guardian script to check calibration filter settings (Miyo) * Apr 9 (Sat) Spare day * Apr 10 (Sun) Spare day * Apr 11 (Mon) Start test run 2nd round == TO DO before Apr 11 == * PSL, IMC related * re-alignment of PMC * put the PMC control back to remote mode [Apr 1-5] * replace TTFSS to the modified one [Apr 1-5] * Add a monitor of laser power right after the laser [Apr 1-5] * re-alignment of IMC and stabilize IMC lock [Apr 6-8] * replace 100 kHz LPF for IMC lock, from SR560 to RC circuit [Apr 6-8] * replace IMC REFL RF PD to the one which has DC output B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1272|DONE]] * close IOO rack (may need RF distributor modification) [Apr 1-5] * fix IQ demodulator being too hot issue [Apr 1-5] * Exchange holders for IMC oplev light sources (if required) [Apr 4-7] * ISC related * BS Oplev QPD diagonalization, coil balance [Apr 1-5, no laser hazard] * EX, EY coil balance at higher frequency (~10Hz. Done for DC) [Apr 1-5] * EY PZT [Apr 1-5] * IMC and MICH Noise budgeting using Simulink Noise``Budget [Apr 6-8] * auto alignment for IMC and MICH (dithering? ASC?) [Apr 6-8] * make online calibration model, UGF servo (auto gain adjuster using calibration lines) [Apr 6-8] * feedback MICH also to BS to increase MICH feedback range [Apr 6-8] * Exchange holders for BS/ETMs oplev light sources (if required) [Apr 4-7] * DetChar related * lock loss investigation (use 3/25-3/11 data) * AOS related * replace EXA end viewport for EX2 camera [Apr 4-7] * VAC related * connect PR2-BS duct [Apr 4-5, no laser hazard] * open the GVs (close to IXA,IYA) to reduce clipping [Apr 1] * check anchors and bolts for vacuum tanks [Apr 4-5] * PR3 related * PR3 transfer function measurements, noise measurements [Apr 5-6] * PR3 LVDT offload with fishing lod [Apr 5-6] * fix PR3 LVDT WD issue [Apr 5-6] * install the remote control system of the motors [Apr 5-6] * check PR3 yaw picomotor [Apr 5-6] * Exchange holder for PR3 oplev light source (if required) [Apr 4-7] * DGS related * k1boot backup [Apr 1, Miyakawa] * Time adjust on k1fw0, k1fw1 [Apr 1, Miyakawa] * Add memories on k1fw0, k1fw1, k1dc0 for 64sec frame data[Apr 5-8, Miyakawa] * Fix camera noise [Kokeyama] * Fix conlog [Apr 4-8, Sasaki] * Fix GE RFM on k1ex0 [Apr 1, Miyakawa] * Reboot and update display driver for monitor PCs [Apr 1, Miyakawa] * Install printer of 2nd floor for k1ctr0-4 [Apr 4-8, Sasaki] * Install VNC for monitor k1mon0-2 [Apr 4-8, Sasaki] * Make a state monitor on MEDM [Apr 4-8, Miyo] * General * Safety check ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4988|reported by Awai]]) [Apr 1-10] ----- == Initial alignment work == === first week === | |
| Line 4: | Line 189: | 
| * PR2 install (Aso et al) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=825|DONE]] | * PR2 install (Aso et al) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=825|DONE]] | 
| Line 8: | Line 193: | 
| * oplev and camera for ETMX (Akutsu,Kokeyama) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=834|DONE]] (not calibrated yet) | * oplev and camera for ETMX (Akutsu,Kokeyama) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=834|DONE]] (not calibrated yet) | 
| Line 10: | Line 195: | 
| * PR3 install, check signals (Shoda et al) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=852|DONE]] | * PR3 install, check signals (Shoda et al) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=852|DONE]] | 
| Line 12: | Line 197: | 
| * oplev and camera for ETMY (Akutsu,Simon) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=854|DONE]] (not calibrated yet) | * oplev and camera for ETMY (Akutsu,Simon) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=854|DONE]] (not calibrated yet) | 
| Line 14: | Line 199: | 
| * install Y end machines (Kokeyama) | * install Y end machines (Kokeyama) B) DONE | 
| Line 19: | Line 204: | 
| * finish IMMT1T QPD setup (Akutsu,Michimura,Kataoka) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=862|DONE]] | * finish IMMT1T QPD setup (Akutsu,Michimura,Kataoka) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=862|DONE]] | 
| Line 24: | Line 209: | 
| === we are here! === | * install PR2 viewport for the camera, and the camera (Akutsu,Kokeyama) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=866|half done]] (no camera yet) | 
| Line 27: | Line 211: | 
| * turn on PR3 local damping (Shoda,Okutomi,Fujii) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=872|DONE]] * pedestals for PDs (Michimura,Tomaru) B) ARRIVED * Mar 02 (Wed): Miyakawa, Kokeyama, Michimura, Enomoto, Akutsu, Aso, Furuhata, Kambara * put PRM-PR3 bellows (MIRAPRO 8:00-11:00) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=878|DONE]] * put BS-IXC bellows (MIRAPRO PM?) B) DONE | |
| Line 28: | Line 217: | 
| * IXC+IXA vent (Kimura) * peel ETMX first contact (Ohishi,Shoda,Aso) * |-) install BS viewports for the oplev and the camera(Akutsu,Michimura,Kataoka) * |-) install PR2 viewport for the camera, and the camera (Akutsu,SOMEONE!) * check PR3 actuation model, calibrate PR3 oplev and turn on local damping (Shoda,Okutomi,Fujii) * Mar 02 (Wed): Miyakawa, Kokeyama, Michimura, Enomoto, Akutsu, Aso * put PRM-PR3 bellows (MIRAPRO 8:00-11:00) * put BS-IXC, BS-IYC bellows (MIRAPRO PM?) * finish IMC stabilization (Kawamura,Enomoto) * finish IXA clean booth clean up (Kimura) * bring clean goods to IXA (Michimura) * peel ETMY first contact (Ohishi,Shoda,Aso) * |-) install EXA flange (Akutsu,Michimura) * |-) install PR3 viewport for the camera, and the camera (Akutsu,Shoda,Okutomi) * k1cam0 and k1cam1 setup (Kokeyama,SOMEONE!) | * IXC+IXA vent (Kimura) B) DONE * finish IXA clean booth clean up, bring clean goods (Kimura,Tomaru) B) DONE * peel ETMX first contact and set coils (Ohishi,Shoda,Aso) REMAINING ISSUE * install BS viewports for the oplev and the camera(Akutsu,Michimura,Kambara,Furuhata) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=882|half done]] (45deg issue, IPC issue) * install PR3 viewport for the camera, and the camera (Akutsu,Shoda,Okutomi,Fujii) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=876|half done]] (no camera yet) * k1cam0 and k1cam1 setup (Kokeyama) B) DONE * DAQ networks for EX and EY (Miyakawa,Kokeyama) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=874|DONE]] * calibrate PR3 oplev (Shoda,Okutomi,Fujii) B) DONE | 
| Line 45: | Line 226: | 
| * check IMMT2 picomotor (Miyo,Doi) * [[KAGRA/Subgroups/MIF/Commissioning/PR2Alignment|PR2 alignment]] * [[KAGRA/Subgroups/MIF/Commissioning/PR2Alignment|beam profiling]] at PR3 * Mar 04 (Fri): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Aso, Furuhata, Kambara * PR3 rough alignment into IXA (Michimura,Ushiba,Furuhata,Kambara) * beam profiling at IXA (Michimura,Ushiba,Furuhata,Kambara) * pedestals for PDs should be delivered at this point (Michimura,Tomaru) * setup PDs at EXA, EYA (Michimura,Kokeyama,Kuwahara) * DQ channels should work at this point (Miyakawa,Kokeyama) | * high power IMC (Enomoto) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=891|DONE]] (~850 mW) * [[KAGRA/Subgroups/MIF/Commissioning/PR2Alignment|PR2 alignment, beam profiling at PR3]] [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=886|half done]] (beam profiling not yet) * check IMMT2 picomotor (Miyo,Doi) B) DONE * ETMX,ETMY,BS picomotor (Miyo) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=888|mostly DONE]] (ETMX to be confirmed) * setup PDs at EXA (Akutsu,Fujii) B) DONE * peel ETMY first contact and set coils (Ohishi,Takahashi) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=893|DONE]] * PR2, PR3, BS, IMMT1T cameras (Kokeyama) PR2 DONE, BS and PR3 to be done * ETMX first contact issue: WE DECIDED TO GO WITH REMAINING FIRST CONTACT * Mar 04 (Fri): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Furuhata, Kambara * [[KAGRA/Subgroups/MIF/Commissioning/iKAGRA0304|PR3 rough alignment into IXA]] (Michimura,Ushiba,Kuwahara,Okutomi,Kambara,Furuhata) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=907|DONE]] (beam profiling at IXA not yet) * DQ channels for EXA EYA PDs (Kokeyama) B) Done * fix IPC errors (Miyakawa, Kokeyama) B) Done * open BS-IXC GV (Saito,Uchiyama,Kimura) B) DONE * place ND filters to MC_REFL and PMC_TRANS cameras, and check ghost beams (Enomoto) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=905|DONE]] (decreased power to ~250 mW) | 
| Line 55: | Line 241: | 
| * sweep PR3 and wait for end PDs to get any signal (automatically or Kataoka?) | * sweep PR3 and wait for end PDs to get any signal (automatically or Kataoka?) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=923|NO SUCESS]] * Swap picomotor network switch and install new pico switch on IOO rack (Kataoka, Kokeyama) * Install the second camera POE switch on PR2 rack (Kataoka, Kokeyama) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=921|DONE]] * Set RFM card to k1ioo chassis (Kokeyama) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=922|DONE]] | 
| Line 57: | Line 246: | 
| * sweep PR3 and wait for end PDs to get any signal (automatically or Kataoka?) * Mar 07 (Mon): Miyakawa, Kokeyama, Michimura, Ushiba, Kuwahara, Kataoka, Akutsu, Aso * beam profiling at EXA (Michimura,Ushiba,Furuhata,Kambara) * check ETMX actuation model and calibrate ETMX oplev (Akutsu,Kokeyama,Kuwahara) * take PD from EXA and setup PD at BS (Michimura,Kokeyama,Kuwahara) * Mar 08 (Tue): Miyakawa, Kokeyama, Michimura, Ushiba, Kuwahara, Kataoka, Akutsu, Aso * sweep ETMX and wait for AS PD to get any signal (automatically or ?) * set up REFL optics and cabling (Michimura) * get the beam back to IFI and then to REFL (Ushiba,Kataoka) * check BS actuation model and calibrate BS oplev (Akutsu,Kokeyama,Kuwahara) * Mar 09 (Wed): Miyakawa, Kokeyama, Michimura, Ushiba, Kuwahara, Akutsu, Aso * block X beam (Michimura) * sweep BS and wait for ETMY PD to get any signal (automatically or ?) * some spare time * Mar 10 (Thu): Miyakawa, Kokeyama, Michimura, Akutsu, Aso * sweep BS and wait for ETMY PD to get any signal (automatically or ?) * check ETMY actuation model and calibrate ETMY oplev (Akutsu,Kokeyama,Michimura) * Mar 11 (Fri): Miyakawa, Kokeyama, Michimura, Akutsu?, Aso * sweep ETMY and wait for AS PD to get any signal (automatically or ?) * get fringe at REFL/AS (Michimura,Akutsu?) * Mar 12 (Sat): Kokeyama * close everything and slowly start evacuation * Mar 13 (Sun): * Mar 14 (Mon): Miyakawa, Kokeyama, Michimura?, Aso * check LSC model * lock Michelson and measure openloop transfer function * check calibration model * get strain spectrum * Mar 15 (Tue): Miyakawa, Michimura, Aso * start observation | * block PSL beam for VAC work (Uchiyama) === second week === * Mar 07 (Mon) * beam clipping at BS check, BS rough alignment into Y, IXA beam check with respect to PR3 alignment, beam profiling at IXA?, sweep PR3 at night (Michimura,Ushiba,Kataoka,Kambara,Furuhata,Okutomi) * check ETMX actuation (Ohishi,Takahashi) B) DONE * calibrate ETMX oplev (Kuwahara) B) DONE * ETMX picomotor check (Miyo) B) DONE * install EXA end flange (Tomaru) B) DONE * calibrate ETMY oplev (Kokeyama,Kuwahara) B) DONE * PR3 oplev calibration result, check PR3 oplev channels (Kokeyama,Okutomi) B) DONE * RFM test between center area and both ends (Kokeyama) * Mar 08 (Tue) * install BS oplev and calibrate (Akutsu,Hasegawa,Kuwahara) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=949|DONE]] * fine adjustment of PR3 alignment to BS and IXA, Xarm viewport, PR3 sweep to EXA (Michimura,Shoda,Okutomi,Ushiba,Furuhata,Kagawa,Fujisawa) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=946|DONE]] * install EXA end viewport (Akutsu,Hasegawa,Kuwahara) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=948|DONE]] * check ETMY actuation (Ohishi,Takahashi,Kuwahara) B) DONE * install EYA end flange (Kimura,Tomaru) B) DONE * VIS guardian (Shoda,Okutomi,Kokeyama) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=950|DONE]] * Mar 09 (Wed) * BS actuation check (Ushiba,Kuwahara,Furuhata) B) DONE * setup PD at EYA (Akutsu,Hasegawa,Kambara) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=968|DONE]] * install EYA end viewport (Akutsu,Hasegawa,Kambara) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=966|DONE]] * take PD from EXA, EXA beam check, ETMX rough alignment (Michimura,Fujii) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=972|DONE]], [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=975|DONE]] * setup PD at BS (Akutsu,Hasegawa,Kambara) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=967|DONE]] * EXA end, EYA end cameras (Kokeyama) B) DONE * RFM network between center and Yend (Kokeyama) B) DONE * Mar 10 (Thu) * connect BS-IYC (MIRAPRO) B) DONE * start EXA evacuation (Kimura) B) DONE * block Y arm beam (Akutsu,Kambara,Hasegawa) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=981|investigated]] * LED from EYA to BS (Miyoki) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=983|failed]] -> try brighter LED * Mar 11 (Fri) * connect PR2-PR3 duct (MIRAPRO) B) DONE * sweep ETMX and wait for AS PD to get any signal (Miyo,Hasegawa) * sweep BS and wait for ETMY PD to get any signal (Fujii,Furuhata) * Mar 12 (Sat) * partially connect PR2-BS duct (MIRAPRO) * LED from EYA to BS (Tomaru,Uchiyama,Hasegawa,Miyo) failed * Mar 13 (Sun) * BS PD to face X (Uchiyama) B) DONE === third week === * EXA vent (Saito,Tomaru) B) DONE * ETMX alignment re-adjustment (Uchiyama) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1034|DONE]] * viewport for IXA (Michimura) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1023|DONE]] * BS alignment re-adjustment (Uchiyama?) B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1029|DONE]] * ETMY oplev re-calibration B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1031|DONE]] * IYA vent (Kimura?) B) DONE * get the beam back to IFI and then to REFL B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1037|DONE]] * set up REFL optics and cabling B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1039|DONE]] * beam to and from X and Y arms B) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1058|DONE]] == TO DO before Mar 26 == * insert PR2-BS duct B) Done * evacuate IXA and IYA (we do not evacuate anything in March) * IOO cabling check (?) * get PMC back to remote control mode (To be done by Apr 11) * coil balancing for BS, ETMX, ETMY B) Done except BS * coil offload with picomotors for BS, ETMX, ETMY (and PR3 yaw) B) Done * oplev damping for BS, ETMX, ETMY, PR3 B) Done * more alignment to maximize contrast, clipping investigation B) Done, 75%MAX * measure power at REFL port from X and Y arms B) Done * install REFL camera (steal IMMT1T camera) B) Done * check LSC model B) Done * lock Michelson and measure openloop transfer function B) Done * MICH guardian B) Done * calibration model B) Done * get strain spectrum B) Done | 
bKAGRA Phase 1 Initial Alignment
Commissioners at the site
- Type-Bp team: Shoda (absent in the week of 10/10), Miyo (absent from 10/19), Arai
- Type-B team: Mark (absent during 10/15-24), Fabian, Enzo
- Kokeyama (absent during 10/15-10/31), Enomoto (10/10-13, 10/16-20), Nakano (basically at the site), Izumi (absent on 10/4 and occasionally), Inoue (10/3-5?, 10/16?-), Yokozawa (10/9-20), Aso (10/16-), Michimura (10/3-4)
Schedule
- Oct 2 - 6: Initial alignment preparations (Kokeyama, Michimura) - some dirty work in the SR2 area
 
- Oct 10 - 13: Initial alignment to PR3 (Kokeyama)
- Oct 16 - 20: Initial alignment to EX (Inoue, Izumi)
- Oct 23 - 27: Initial alignment to EY (Inoue, Izumi)
- Oct 30 - : Beam position measurements (Uchiyama)
iKAGRA Commissioning
Test run summary
- Summary of iKAGRA Test Run March 2016 (JGW-T1605101) 
- Summary of iKAGRA Test Run March 2017 (JGW-T1605177) 
TO DO after Apr test run but before iKAGRA ends
- oplev stability, noise measurements (with mirror fixed)
- scattering noise investigation
- PR3 height check
- measure PR3 suspension Q values
- save and note all the interferometer settings, configurations to write a paper
- investigate 15 Hz resonance in ETM suspensions  1301 1301
- calibration confirmation, actuator efficiency measurement(including BS)
- stop the clean booth filters and see if the noise changes
- take noise spectra using an analog FFT analyser up to very high frequency. Compare it with the spectrum taken by the digital system
- measure the accurate position of the mirrors (PR3 and BS) with respect to the markings on the floor
- remove REFL aluminum foil and see if the noise changes
- measure Schnupp asymmetry (how?)
Some issues to remember
- unknown 550 Hz LPF in MICH OLTF klog #1645 
- why sensitivity improved over 2 kHz? after Apr 12 commissioning break? (klog #1531) 
- why there are no 60 Hz line noise?
- RF PD issues: breaks easily with single power supply, Dsub 9pin connectors don't fix tight
Commissioners at the site
- Mar 31 to Apr 11: http://densuke.biz/list?cd=RGpffPNuJw6xwBMF 
- Mar 7 to Mar 20: http://densuke.biz/list?cd=wgUxhq6KHdfsUnWW 
April Commissioning Break (Apr 1-10)
- Apr 1 (Fri)  GV opening day (Leader: Kokeyama) - k1boot backup (Miyakawa)  1326 1326
- time adjust k1fw0, k1fw1 (Miyakawa)  1328 1328
- fix GE RFM on k1ex0 (Miyakawa)
- reboot and update display driver for monitor PCs (Miyakawa)  1328 1328
- unreel power cables around racks (Kokeyama,Michimura)  1330 1330
- close IOO rack (Kokeyama,Michimura)   
- open GVs close to IXA,IYA (Saito)  1336 1336
- restore Michelson (Kokeyama,Michimura,Komori)  1336 1336
- cable making for seismometer,thermometer,hygrometer,barometer(Hayama)
 
- Apr 2 (Sat) Spare day (Leader: Michimura)
- Apr 3 (Sun) PSL&IMC day (Leader: Michimura) - collect broken EXA viewport (Akutsu, Michimura)   
- replace ETMX oplev collimator holders (Akutsu,Michimura)  1346 1346
- longer cable for IMC EOM (Nakano,Enomoto)  DONE DONE
- re-alignment of PMC (Nakano,Enomoto)  1349 1349
- replace TTFSS to the modified one (Nakano,Enomoto)  1348 1348
- investigate TTFSS Interface slow nob (Nakano,Enomoto) [later]
- put the PMC control back to remote mode (Nakano,Enomoto)  1351 1351
- replace 100 kHz LPF for IMC lock from SR560 to RC circuit, modify connectors to screw cables (Enomoto,Nakano)  1350 1359 1350 1359
- make sure history of circuits are properly recorded on JGW Doc S numbers (Nakano,Enomoto)
- put N terminators for RF distributor (Michimura)  1352 1352
- replace Dsub 9pin cable for IMC REFL RF PD connected in series with longer one (Komori,Miyamoto)  1352 1352
- protect IMC picomotor drivers and devices on the floor (Komori,Miyamoto)  1352 1352
- tighten SMA cable connectors with wrench (Nakano,Enomoto,Komori,Miyamoto)  1352 1352
- measure ADC noise, PD dark noise (Komori,Michimura)
 
- Apr 4 (Mon) PSL&IMC day (Leader: Michimura) - connect PR2-BS bellows, VAC safety check (Saito, from PM)
- BS coil balance, sign check (Komori,Uchiyama,Ohishi)  1354 1354
- update PMC guardian (Nakano)  1353 1353
- check lens/mirror mounts, pedestals, forks are properly fixed tight (Nakano,Enomoto,Nagano)
- put orange and yellow power cables between PR3 to IOO rack (Hasegawa)   
- fix IQ demodulator being too hot issue (Nakano,Enomoto,Nagano)  1401 [later] 1401 [later]
- replace IMC coil differential cable with diff to single board (Nakano,Enomoto,Nagano) [later]
- cancel --- (ETMY PZT cabling (Ohishi,Miyoki,Miyo)
- change ETMY oplev to folded configuration, redo calibration (Akutsu,Miyamoto)  1355, 1374 1355, 1374
- replace PR3 oplev collimator holder (Akutsu,Hasegawa)  1356 1356
- fix conlog, install printer, install VNC (Sasaki)
- make a state monitor on MEDM (Miyo)  [LOCK_STATUS guardian] [LOCK_STATUS guardian]
- cable making for seismometer,thermometer,hygrometer,barometer(Hayama)
 
- Apr 5 (Tue) PSL&IMC, PR3 day (Leader: Kawamura) - connect PR2-BS bellows, VAC safety check (Saito)   
- re-alignment of IMC and stabilize IMC lock (Nakano,Enomoto,Nagano)  1386,1499 1386,1499
- RF PD for Michelson REFL (Hasegawa,Miyamoto,Nagano)  1377 1377
- fix PR3 LVDT WD issue (Shoda,Fujii,Miyakawa) [later]
- PR3 LVDT offload with fishing lod (Shoda,Fujii)  1382 1382
- install the remote control system of the motors (Shoda,Fujii) [later]
- check PR3 yaw picomotor (Shoda,Fujii)  IT WORKS IT WORKS
- change ETMX oplev to folded configuration, redo calibration (Akutsu,Miyamoto)  1406, 1436 1406, 1436
- safety check (Kawamura,Awai,Kimura,Tomaru)  [partially done] [partially done]
- add memories on k1fw0, k1fw1, k1dc0 for 64sec frame data (Miyakawa)
- install PEMs, GIF maintenance (Araya,Miyo,Hayama,Kataoka)
 
- Apr 6 (Wed) PR3, MICH day (Leader: Michimura) - connect PR2-BS bellows, VAC safety check (Saito, until AM)
- Simulink NoiseBudget for Michelson (Shimoda,Michimura,Kokeyama)   
- online calibration model, UGF servo (Aritomi,Michimura,Kokeyama)  1425, 1472 1425, 1472
- auto alignment (Miyo,Aso,Kokeyama)  1484 [for IMC] 1484 [for IMC]
- replace IMC, BS oplev collimator holders (Akutsu) [CANCEL]
- water gage setting (Hayama, Kataoka)  1392 1392
- realtime model for environmental sensors (Hayama, ?)
 
- Apr 7 (Thu) MICH day (Leader: Aso) - feedback MICH also to BS (Aso) [CANCEL]
- try to use REFL RF PD for MICH lock (Nakano)  1388 1388
- cancel --- (feedback MICH also to ETMY PZT (Miyo,Aso))
- realtime model for environmental sensors (Hayama, ?)
 
- Apr 8 (Fri) MICH day (Leader: Kokeyama) - make MICH_LOCK guardian script to check calibration filter settings (Miyo)
 
- Apr 9 (Sat) Spare day
- Apr 10 (Sun) Spare day
- Apr 11 (Mon) Start test run 2nd round
TO DO before Apr 11
- PSL, IMC related - re-alignment of PMC
- put the PMC control back to remote mode [Apr 1-5]
- replace TTFSS to the modified one [Apr 1-5]
- Add a monitor of laser power right after the laser [Apr 1-5]
- re-alignment of IMC and stabilize IMC lock [Apr 6-8]
- replace 100 kHz LPF for IMC lock, from SR560 to RC circuit [Apr 6-8]
- replace IMC REFL RF PD to the one which has DC output  DONE DONE
- close IOO rack (may need RF distributor modification) [Apr 1-5]
- fix IQ demodulator being too hot issue [Apr 1-5]
- Exchange holders for IMC oplev light sources (if required) [Apr 4-7]
 
- ISC related - BS Oplev QPD diagonalization, coil balance [Apr 1-5, no laser hazard]
- EX, EY coil balance at higher frequency (~10Hz. Done for DC) [Apr 1-5]
- EY PZT [Apr 1-5]
- IMC and MICH Noise budgeting using Simulink NoiseBudget [Apr 6-8] 
- auto alignment for IMC and MICH (dithering? ASC?) [Apr 6-8]
- make online calibration model, UGF servo (auto gain adjuster using calibration lines) [Apr 6-8]
- feedback MICH also to BS to increase MICH feedback range [Apr 6-8]
- Exchange holders for BS/ETMs oplev light sources (if required) [Apr 4-7]
 
- DetChar related - lock loss investigation (use 3/25-3/11 data)
 
- AOS related - replace EXA end viewport for EX2 camera [Apr 4-7]
 
- VAC related - connect PR2-BS duct [Apr 4-5, no laser hazard]
- open the GVs (close to IXA,IYA) to reduce clipping [Apr 1]
- check anchors and bolts for vacuum tanks [Apr 4-5]
 
- PR3 related - PR3 transfer function measurements, noise measurements [Apr 5-6]
- PR3 LVDT offload with fishing lod [Apr 5-6]
- fix PR3 LVDT WD issue [Apr 5-6]
- install the remote control system of the motors [Apr 5-6]
- check PR3 yaw picomotor [Apr 5-6]
- Exchange holder for PR3 oplev light source (if required) [Apr 4-7]
 
- DGS related - k1boot backup [Apr 1, Miyakawa]
- Time adjust on k1fw0, k1fw1 [Apr 1, Miyakawa]
- Add memories on k1fw0, k1fw1, k1dc0 for 64sec frame data[Apr 5-8, Miyakawa]
- Fix camera noise [Kokeyama]
- Fix conlog [Apr 4-8, Sasaki]
- Fix GE RFM on k1ex0 [Apr 1, Miyakawa]
- Reboot and update display driver for monitor PCs [Apr 1, Miyakawa]
- Install printer of 2nd floor for k1ctr0-4 [Apr 4-8, Sasaki]
- Install VNC for monitor k1mon0-2 [Apr 4-8, Sasaki]
- Make a state monitor on MEDM [Apr 4-8, Miyo]
 
- General - Safety check (reported by Awai) [Apr 1-10] 
 
Initial alignment work
first week
- Feb 24 (Wed): Miyakawa, Kokeyama, Aso - PR2 install (Aso et al)  DONE DONE
- PR3 install (Shoda et al)
 
- Feb 25 (Thu): Miyakawa, Kokeyama, Aso
- Feb 26 (Fri): Miyakawa, Kokeyama
- Feb 27 (Sat): Kokeyama, Akutsu - install Y end machines (Kokeyama)  DONE DONE
- EY camera (Kokeyama)  DONE DONE
 
- Feb 28 (Sun):
- Feb 29 (Mon): Miyakawa, Kokeyama, Michimura, Enomoto, Kataoka, Akutsu, Aso - IMC stabilization (Kawamura,Enomoto)
- finish IMMT1T QPD setup (Akutsu,Michimura,Kataoka)  DONE DONE
- prepare for IXC+IXA vent (Kimura)
- peel PR3 first contact (Shoda,Fujii)  DONE DONE
- check PR2 picomotors (Aso,Miyo)  DONE DONE
- EX camera (Kokeyama)  DONE DONE
- install PR2 viewport for the camera, and the camera (Akutsu,Kokeyama) half done (no camera yet) 
 
- Mar 01 (Tue): Miyakawa, Kokeyama, Michimura, Enomoto, Kataoka, Akutsu, Aso - turn on PR3 local damping (Shoda,Okutomi,Fujii)  DONE DONE
- pedestals for PDs (Michimura,Tomaru)  ARRIVED ARRIVED
 
- Mar 02 (Wed): Miyakawa, Kokeyama, Michimura, Enomoto, Akutsu, Aso, Furuhata, Kambara - put PRM-PR3 bellows (MIRAPRO 8:00-11:00)  DONE DONE
- put BS-IXC bellows (MIRAPRO PM?)  DONE DONE
- IMC stabilization (Kawamura,Enomoto)
- IXC+IXA vent (Kimura)  DONE DONE
- finish IXA clean booth clean up, bring clean goods (Kimura,Tomaru)  DONE DONE
- peel ETMX first contact and set coils (Ohishi,Shoda,Aso) REMAINING ISSUE
- install BS viewports for the oplev and the camera(Akutsu,Michimura,Kambara,Furuhata) half done (45deg issue, IPC issue) 
- install PR3 viewport for the camera, and the camera (Akutsu,Shoda,Okutomi,Fujii) half done (no camera yet) 
- k1cam0 and k1cam1 setup (Kokeyama)  DONE DONE
- DAQ networks for EX and EY (Miyakawa,Kokeyama)  DONE DONE
- calibrate PR3 oplev (Shoda,Okutomi,Fujii)  DONE DONE
 
- Mar 03 (Thu): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Akutsu, Aso, Furuhata, Kambara - high power IMC (Enomoto)  DONE (~850 mW) DONE (~850 mW)
- PR2 alignment, beam profiling at PR3 half done (beam profiling not yet) 
- check IMMT2 picomotor (Miyo,Doi)  DONE DONE
- ETMX,ETMY,BS picomotor (Miyo)  mostly DONE (ETMX to be confirmed) mostly DONE (ETMX to be confirmed)
- setup PDs at EXA (Akutsu,Fujii)  DONE DONE
- peel ETMY first contact and set coils (Ohishi,Takahashi)  DONE DONE
- PR2, PR3, BS, IMMT1T cameras (Kokeyama) PR2 DONE, BS and PR3 to be done
- ETMX first contact issue: WE DECIDED TO GO WITH REMAINING FIRST CONTACT
 
- Mar 04 (Fri): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Furuhata, Kambara - PR3 rough alignment into IXA (Michimura,Ushiba,Kuwahara,Okutomi,Kambara,Furuhata)  DONE (beam profiling at IXA not yet) DONE (beam profiling at IXA not yet)
- DQ channels for EXA EYA PDs (Kokeyama)  Done Done
- fix IPC errors (Miyakawa, Kokeyama)  Done Done
- open BS-IXC GV (Saito,Uchiyama,Kimura)  DONE DONE
- place ND filters to MC_REFL and PMC_TRANS cameras, and check ghost beams (Enomoto)  DONE (decreased power to ~250 mW) DONE (decreased power to ~250 mW)
 
- Mar 05 (Sat): Kokeyama, Kataoka
- Mar 06 (Sun): Kataoka - block PSL beam for VAC work (Uchiyama)
 
second week
- Mar 07 (Mon) - beam clipping at BS check, BS rough alignment into Y, IXA beam check with respect to PR3 alignment, beam profiling at IXA?, sweep PR3 at night (Michimura,Ushiba,Kataoka,Kambara,Furuhata,Okutomi)
- check ETMX actuation (Ohishi,Takahashi)  DONE DONE
- calibrate ETMX oplev (Kuwahara)  DONE DONE
- ETMX picomotor check (Miyo)  DONE DONE
- install EXA end flange (Tomaru)  DONE DONE
- calibrate ETMY oplev (Kokeyama,Kuwahara)  DONE DONE
- PR3 oplev calibration result, check PR3 oplev channels (Kokeyama,Okutomi)  DONE DONE
- RFM test between center area and both ends (Kokeyama)
 
- Mar 08 (Tue) - install BS oplev and calibrate (Akutsu,Hasegawa,Kuwahara)  DONE DONE
- fine adjustment of PR3 alignment to BS and IXA, Xarm viewport, PR3 sweep to EXA (Michimura,Shoda,Okutomi,Ushiba,Furuhata,Kagawa,Fujisawa)  DONE DONE
- install EXA end viewport (Akutsu,Hasegawa,Kuwahara)  DONE DONE
- check ETMY actuation (Ohishi,Takahashi,Kuwahara)  DONE DONE
- install EYA end flange (Kimura,Tomaru)  DONE DONE
- VIS guardian (Shoda,Okutomi,Kokeyama)  DONE DONE
 
- Mar 09 (Wed) - BS actuation check (Ushiba,Kuwahara,Furuhata)  DONE DONE
- setup PD at EYA (Akutsu,Hasegawa,Kambara)  DONE DONE
- install EYA end viewport (Akutsu,Hasegawa,Kambara)  DONE DONE
- take PD from EXA, EXA beam check, ETMX rough alignment (Michimura,Fujii)  DONE, DONE DONE, DONE
- setup PD at BS (Akutsu,Hasegawa,Kambara)  DONE DONE
- EXA end, EYA end cameras (Kokeyama)  DONE DONE
- RFM network between center and Yend (Kokeyama)  DONE DONE
 
- Mar 10 (Thu) - connect BS-IYC (MIRAPRO)  DONE DONE
- start EXA evacuation (Kimura)  DONE DONE
- block Y arm beam (Akutsu,Kambara,Hasegawa) investigated 
- LED from EYA to BS (Miyoki) failed -> try brighter LED 
 
- Mar 11 (Fri) - connect PR2-PR3 duct (MIRAPRO)  DONE DONE
- sweep ETMX and wait for AS PD to get any signal (Miyo,Hasegawa)
- sweep BS and wait for ETMY PD to get any signal (Fujii,Furuhata)
 
- Mar 12 (Sat) - partially connect PR2-BS duct (MIRAPRO)
- LED from EYA to BS (Tomaru,Uchiyama,Hasegawa,Miyo) failed
 
- Mar 13 (Sun) - BS PD to face X (Uchiyama)  DONE DONE
 
third week
- EXA vent (Saito,Tomaru)  DONE DONE
- ETMX alignment re-adjustment (Uchiyama)  DONE DONE
- viewport for IXA (Michimura)  DONE DONE
- BS alignment re-adjustment (Uchiyama?)  DONE DONE
- ETMY oplev re-calibration  DONE DONE
- IYA vent (Kimura?)  DONE DONE
- get the beam back to IFI and then to REFL  DONE DONE
- set up REFL optics and cabling  DONE DONE
- beam to and from X and Y arms  DONE DONE
TO DO before Mar 26
- insert PR2-BS duct  Done Done
- evacuate IXA and IYA (we do not evacuate anything in March)
- IOO cabling check (?)
- get PMC back to remote control mode (To be done by Apr 11)
- coil balancing for BS, ETMX, ETMY  Done except BS Done except BS
- coil offload with picomotors for BS, ETMX, ETMY (and PR3 yaw)  Done Done
- oplev damping for BS, ETMX, ETMY, PR3  Done Done
- more alignment to maximize contrast, clipping investigation  Done, 75%MAX Done, 75%MAX
- measure power at REFL port from X and Y arms  Done Done
- install REFL camera (steal IMMT1T camera)  Done Done
- check LSC model  Done Done
- lock Michelson and measure openloop transfer function  Done Done
- MICH guardian  Done Done
- calibration model  Done Done
- get strain spectrum  Done Done
What we do
- confirm mirror actuators (picomotors, coils, OSEMs) work from digital system
- prepare oplevs and cameras
- prepare RT models and MEDM screens for mirrors and LSC
- prepare feet for large beam profiler
- prepare pedestals for DC PDs
- REFL optics
- stable operation of IMC
- initial alignment: JGW-T1604823 
- lock 3km Michelson
LCGT Commissioning plan (As of Aug 2012)
Schedule
- List up issues to be addressed for installation procedure (September)
- Detailed installation plan (October)
- General Commissioning Strategy (how to deploy man power etc) (by the end of November)
List of items necessary for commissioning
The List is Here.