Line 33: | Line 33: |
* finish IXA clean booth clean up, bring clean goods (Kimura,Tomaru) B) DONE | |
Line 39: | Line 40: |
* Mar 03 (Thu): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Akutsu, Aso, Furuhata, Kambara * high power IMC (Enomoto) B) DONE (~850 mW) * [[KAGRA/Subgroups/MIF/Commissioning/PR2Alignment|PR2 alignment, beam profiling at PR3]] [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=886|half done]] (beam profiling not yet) * check IMMT2 picomotor (Miyo,Doi) B) DONE * ETMX,ETMY,BS picomotor (Miyo) B) [[KAGRA/Subgroups/DGS/Projects/PicoMotor|DONE]] |
|
Line 42: | Line 48: |
* Mar 03 (Thu): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Akutsu, Aso, Furuhata, Kambara * finish IMC stabilization (Enomoto) * finish IXA clean booth clean up, bring clean goods (Kimura,Tomaru) * check IMMT2 picomotor (Miyo,Doi) * [[KAGRA/Subgroups/MIF/Commissioning/PR2Alignment|PR2 alignment, beam profiling at PR3]] * ETMX,ETMY,BS picomotor (Miyo) |
|
Line 53: | Line 58: |
* PR3 rough alignment into IXA (Aso,Michimura,Ushiba,Kuwahara,Okutomi,Kambara) | * [[KAGRA/Subgroups/MIF/Commissioning/iKAGRA0304|PR3 rough alignment into IXA]] (Aso,Michimura,Ushiba,Kuwahara,Okutomi,Kambara) |
Line 58: | Line 63: |
iKAGRA Commissioning
Commissioners at the site
- Feb 24 (Wed): Miyakawa, Kokeyama, Aso
PR2 install (Aso et al)
DONE
- PR3 install (Shoda et al)
- Feb 25 (Thu): Miyakawa, Kokeyama, Aso
- Feb 26 (Fri): Miyakawa, Kokeyama
- Feb 27 (Sat): Kokeyama, Akutsu
install Y end machines (Kokeyama)
DONE?
EY camera (Kokeyama)
DONE
- Feb 28 (Sun):
- Feb 29 (Mon): Miyakawa, Kokeyama, Michimura, Enomoto, Kataoka, Akutsu, Aso
- IMC stabilization (Kawamura,Enomoto)
finish IMMT1T QPD setup (Akutsu,Michimura,Kataoka)
DONE
- prepare for IXC+IXA vent (Kimura)
peel PR3 first contact (Shoda,Fujii)
DONE
check PR2 picomotors (Aso,Miyo)
DONE
EX camera (Kokeyama)
DONE
install PR2 viewport for the camera, and the camera (Akutsu,Kokeyama) half done (no camera yet)
- Mar 01 (Tue): Miyakawa, Kokeyama, Michimura, Enomoto, Kataoka, Akutsu, Aso
turn on PR3 local damping (Shoda,Okutomi,Fujii)
DONE
pedestals for PDs (Michimura,Tomaru)
ARRIVED
- Mar 02 (Wed): Miyakawa, Kokeyama, Michimura, Enomoto, Akutsu, Aso, Furuhata, Kambara
put PRM-PR3 bellows (MIRAPRO 8:00-11:00)
DONE
put BS-IXC bellows (MIRAPRO PM?)
DONE?
- IMC stabilization (Kawamura,Enomoto)
IXC+IXA vent (Kimura)
DONE
finish IXA clean booth clean up, bring clean goods (Kimura,Tomaru)
DONE
- peel ETMX first contact and set coils (Ohishi,Shoda,Aso) REMAINING ISSUE
install BS viewports for the oplev and the camera(Akutsu,Michimura,Kambara,Furuhata) half done (45deg issue, IPC issue)
install PR3 viewport for the camera, and the camera (Akutsu,Shoda,Okutomi,Fujii) half done (no camera yet)
k1cam0 and k1cam1 setup (Kokeyama)
DONE
DAQ networks for EX and EY (Miyakawa,Kokeyama)
DONE
calibrate PR3 oplev (Shoda,Okutomi,Fujii)
DONE
- Mar 03 (Thu): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Akutsu, Aso, Furuhata, Kambara
high power IMC (Enomoto)
DONE (~850 mW)
PR2 alignment, beam profiling at PR3 half done (beam profiling not yet)
check IMMT2 picomotor (Miyo,Doi)
DONE
ETMX,ETMY,BS picomotor (Miyo)
DONE
we are here!
- install EXA flanges (Akutsu,Uchiyama,Fujii,Kambara)
- ETMX first contact issue (Ohishi,Akutsu)
- PR2, PR3, BS, IMMT1T cameras (Kokeyama)
- Mar 04 (Fri): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Aso, Furuhata, Kambara
PR3 rough alignment into IXA (Aso,Michimura,Ushiba,Kuwahara,Okutomi,Kambara)
- BS rough alignment into Yarm (Aso,Michimura,Ushiba,Kuwahara,Okutomi,Kambara)
- beam profiling at IXA (Aso,Michimura,Ushiba,Kuwahara,Okutomi,Kambara)
- setup PDs at EXA, EYA (SOMEONE! Tomaru?,Uchiyama?)
- peel ETMY first contact and set coils (Ohishi,Shoda)
- Mar 05 (Sat): Kokeyama, Kataoka
- sweep PR3 and wait for end PDs to get any signal (automatically or Kataoka?)
- Mar 06 (Sun): Kataoka
- sweep PR3 and wait for end PDs to get any signal (automatically or Kataoka?)
- Mar 07 (Mon): Miyakawa, Kokeyama, Michimura, Ushiba, Kuwahara, Kataoka, Akutsu, Aso, Furuhata, Kambara
- beam profiling at EXA (Michimura,Ushiba,Furuhata,Kambara)
- check ETMX actuation model and calibrate ETMX oplev (Akutsu,Kokeyama,Kuwahara)
- take PD from EXA and setup PD at BS (Michimura,Kokeyama,Kuwahara)
- Mar 08 (Tue): Miyakawa, Kokeyama, Michimura, Ushiba, Kuwahara, Kataoka, Akutsu, Aso, Furuhata, Kambara
- sweep ETMX and wait for AS PD to get any signal (automatically or ?)
- set up REFL optics and cabling (Michimura)
- get the beam back to IFI and then to REFL (Ushiba,Kataoka)
- check BS actuation model and calibrate BS oplev (Akutsu,Kokeyama,Kuwahara)
- install EYA flanges (Akutsu,SOMEONE!)
- Mar 09 (Wed): Miyakawa, Kokeyama, Michimura, Ushiba, Kuwahara, Akutsu, Aso, Furuhata, Kambara
- block X beam (Michimura)
- sweep BS and wait for ETMY PD to get any signal (automatically or ?)
- some spare time
- Mar 10 (Thu): Miyakawa, Kokeyama, Michimura, Akutsu, Aso, Furuhata, Kambara
- sweep BS and wait for ETMY PD to get any signal (automatically or ?)
- check ETMY actuation model and calibrate ETMY oplev (Akutsu,Kokeyama,Michimura)
- Mar 11 (Fri): Miyakawa, Kokeyama, Michimura, Akutsu?, Aso, Furuhata, Kambara
- sweep ETMY and wait for AS PD to get any signal (automatically or ?)
- get fringe at REFL/AS (Michimura,Akutsu?)
- Mar 12 (Sat): Kokeyama
- close everything and slowly start evacuation
- Mar 13 (Sun):
- Mar 14 (Mon): Miyakawa, Kokeyama, Michimura?, Aso
- check LSC model
- lock Michelson and measure openloop transfer function
- check calibration model
- get strain spectrum
- Mar 15 (Tue): Miyakawa, Michimura, Aso
- start observation
What we do
- confirm mirror actuators (picomotors, coils, OSEMs) work from digital system
- prepare oplevs and cameras
- prepare RT models and MEDM screens for mirrors and LSC
- prepare feet for large beam profiler
- prepare pedestals for DC PDs
- REFL optics
- stable operation of IMC
initial alignment: JGW-T1604823
- lock 3km Michelson
LCGT Commissioning plan (As of Aug 2012)
Schedule
- List up issues to be addressed for installation procedure (September)
- Detailed installation plan (October)
- General Commissioning Strategy (how to deploy man power etc) (by the end of November)
List of items necessary for commissioning
The List is Here.