Size: 1472
Comment:
|
Size: 1891
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 2: | Line 2: |
== Travel Plan == | == Commissioners at the site == |
Line 25: | Line 25: |
== Initial Alignment == | == What we do == * confirm mirror actuators (picomotors, coils, OSEMs) work from digital system * prepare oplevs and cameras * prepare RT models and MEDM screens for mirrors and LSC * prepare feet, pedestals for large beam profiler and DC PDs * REFL optics * stable operation of IMC * initial alignment: [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/DocDB/ShowDocument?docid=4823|JGW-T1604823]] * lock 3km Michelson |
iKAGRA Commissioning
Commissioners at the site
- Feb 24 (Wed): Miyakawa, Kokeyama
- Feb 25 (Thu): Miyakawa, Kokeyama
- Feb 26 (Fri): Miyakawa, Kokeyama
- Feb 27 (Sat): Kokeyama
- Feb 28 (Sun):
- Feb 29 (Mon): Miyakawa, Kokeyama, Michimura, Enomoto, Kataoka
- Mar 01 (Tue): Miyakawa, Kokeyama, Michimura, Enomoto, Kataoka
- Mar 02 (Wed): Miyakawa, Kokeyama, Michimura, Enomoto
- Mar 03 (Thu): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara
- Mar 04 (Fri): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara
- Mar 05 (Sat): Kokeyama, Kataoka
- Mar 06 (Sun): Kataoka
- Mar 07 (Mon): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Kataoka
- Mar 08 (Tue): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Kataoka
- Mar 09 (Wed): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara
- Mar 10 (Thu): Miyakawa, Kokeyama, Michimura, Enomoto
- Mar 11 (Fri): Miyakawa, Kokeyama, Michimura, Enomoto
- Mar 12 (Sat): Kokeyama
- Mar 13 (Sun):
- Mar 14 (Mon): Miyakawa, Kokeyama
- Mar 15 (Tue): Miyakawa, Michimura
What we do
- confirm mirror actuators (picomotors, coils, OSEMs) work from digital system
- prepare oplevs and cameras
- prepare RT models and MEDM screens for mirrors and LSC
- prepare feet, pedestals for large beam profiler and DC PDs
- REFL optics
- stable operation of IMC
initial alignment: JGW-T1604823
- lock 3km Michelson
LCGT Commissioning plan (As of Aug 2012)
Schedule
- List up issues to be addressed for installation procedure (September)
- Detailed installation plan (October)
- General Commissioning Strategy (how to deploy man power etc) (by the end of November)
List of items necessary for commissioning
The List is Here.