iKAGRA Commissioning
Commissioners at the site
http://densuke.biz/list?cd=wgUxhq6KHdfsUnWW
TO DO before Mar 26
- insert PR2-BS duct
- IOO cabling check
- get PMC back to remote control mode
- coil balancing for BS, ETMX, ETMY
- coil offload with picomotors for BS, ETMX, ETMY (and PR3 yaw)
- more alignment to maximize contrast, clipping investigation
- measure power at REFL port from X nd Y arms
- install REFL camera (steal IMMT1T camera)
- check LSC model
- lock Michelson and measure openloop transfer function
- MICH guardian
- calibration model
- get strain spectrum
TO DO before Apr 11
IMC and MICH Noise budgeting using Simulink NoiseBudget
- replace EXA end viewport for EX2 camera
- check anchors and bolts for vacuum tanks
- oplev stability, noise measurements
- scattering noise investigation
- PR3 transfer function measurements, noise measurements
- IMC ASC
Initial alignment work
first week
- Feb 24 (Wed): Miyakawa, Kokeyama, Aso
PR2 install (Aso et al)
DONE
- PR3 install (Shoda et al)
- Feb 25 (Thu): Miyakawa, Kokeyama, Aso
- Feb 26 (Fri): Miyakawa, Kokeyama
- Feb 27 (Sat): Kokeyama, Akutsu
install Y end machines (Kokeyama)
DONE
EY camera (Kokeyama)
DONE
- Feb 28 (Sun):
- Feb 29 (Mon): Miyakawa, Kokeyama, Michimura, Enomoto, Kataoka, Akutsu, Aso
- IMC stabilization (Kawamura,Enomoto)
finish IMMT1T QPD setup (Akutsu,Michimura,Kataoka)
DONE
- prepare for IXC+IXA vent (Kimura)
peel PR3 first contact (Shoda,Fujii)
DONE
check PR2 picomotors (Aso,Miyo)
DONE
EX camera (Kokeyama)
DONE
install PR2 viewport for the camera, and the camera (Akutsu,Kokeyama) half done (no camera yet)
- Mar 01 (Tue): Miyakawa, Kokeyama, Michimura, Enomoto, Kataoka, Akutsu, Aso
turn on PR3 local damping (Shoda,Okutomi,Fujii)
DONE
pedestals for PDs (Michimura,Tomaru)
ARRIVED
- Mar 02 (Wed): Miyakawa, Kokeyama, Michimura, Enomoto, Akutsu, Aso, Furuhata, Kambara
put PRM-PR3 bellows (MIRAPRO 8:00-11:00)
DONE
put BS-IXC bellows (MIRAPRO PM?)
DONE
- IMC stabilization (Kawamura,Enomoto)
IXC+IXA vent (Kimura)
DONE
finish IXA clean booth clean up, bring clean goods (Kimura,Tomaru)
DONE
- peel ETMX first contact and set coils (Ohishi,Shoda,Aso) REMAINING ISSUE
install BS viewports for the oplev and the camera(Akutsu,Michimura,Kambara,Furuhata) half done (45deg issue, IPC issue)
install PR3 viewport for the camera, and the camera (Akutsu,Shoda,Okutomi,Fujii) half done (no camera yet)
k1cam0 and k1cam1 setup (Kokeyama)
DONE
DAQ networks for EX and EY (Miyakawa,Kokeyama)
DONE
calibrate PR3 oplev (Shoda,Okutomi,Fujii)
DONE
- Mar 03 (Thu): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Akutsu, Aso, Furuhata, Kambara
high power IMC (Enomoto)
DONE (~850 mW)
PR2 alignment, beam profiling at PR3 half done (beam profiling not yet)
check IMMT2 picomotor (Miyo,Doi)
DONE
ETMX,ETMY,BS picomotor (Miyo)
mostly DONE (ETMX to be confirmed)
setup PDs at EXA (Akutsu,Fujii)
DONE
peel ETMY first contact and set coils (Ohishi,Takahashi)
DONE
- PR2, PR3, BS, IMMT1T cameras (Kokeyama) PR2 DONE, BS and PR3 to be done
- ETMX first contact issue: WE DECIDED TO GO WITH REMAINING FIRST CONTACT
- Mar 04 (Fri): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Furuhata, Kambara
PR3 rough alignment into IXA (Michimura,Ushiba,Kuwahara,Okutomi,Kambara,Furuhata)
DONE (beam profiling at IXA not yet)
DQ channels for EXA EYA PDs (Kokeyama)
Done
fix IPC errors (Miyakawa, Kokeyama)
Done
open BS-IXC GV (Saito,Uchiyama,Kimura)
DONE
place ND filters to MC_REFL and PMC_TRANS cameras, and check ghost beams (Enomoto)
DONE (decreased power to ~250 mW)
- Mar 05 (Sat): Kokeyama, Kataoka
- Mar 06 (Sun): Kataoka
- block PSL beam for VAC work (Uchiyama)
second week
- Mar 07 (Mon)
- beam clipping at BS check, BS rough alignment into Y, IXA beam check with respect to PR3 alignment, beam profiling at IXA?, sweep PR3 at night (Michimura,Ushiba,Kataoka,Kambara,Furuhata,Okutomi)
check ETMX actuation (Ohishi,Takahashi)
DONE
calibrate ETMX oplev (Kuwahara)
DONE
ETMX picomotor check (Miyo)
DONE
install EXA end flange (Tomaru)
DONE
calibrate ETMY oplev (Kokeyama,Kuwahara)
DONE
PR3 oplev calibration result, check PR3 oplev channels (Kokeyama,Okutomi)
DONE
- RFM test between center area and both ends (Kokeyama)
- Mar 08 (Tue)
install BS oplev and calibrate (Akutsu,Hasegawa,Kuwahara)
DONE
fine adjustment of PR3 alignment to BS and IXA, Xarm viewport, PR3 sweep to EXA (Michimura,Shoda,Okutomi,Ushiba,Furuhata,Kagawa,Fujisawa)
DONE
install EXA end viewport (Akutsu,Hasegawa,Kuwahara)
DONE
check ETMY actuation (Ohishi,Takahashi,Kuwahara)
DONE
install EYA end flange (Kimura,Tomaru)
DONE
VIS guardian (Shoda,Okutomi,Kokeyama)
DONE
- Mar 09 (Wed)
BS actuation check (Ushiba,Kuwahara,Furuhata)
DONE
setup PD at EYA (Akutsu,Hasegawa,Kambara)
DONE
install EYA end viewport (Akutsu,Hasegawa,Kambara)
DONE
take PD from EXA, EXA beam check, ETMX rough alignment (Michimura,Fujii)
DONE, DONE
setup PD at BS (Akutsu,Hasegawa,Kambara)
DONE
EXA end, EYA end cameras (Kokeyama)
DONE
RFM network between center and Yend (Kokeyama)
DONE
- Mar 10 (Thu)
connect BS-IYC (MIRAPRO)
DONE
start EXA evacuation (Kimura)
DONE
block Y arm beam (Akutsu,Kambara,Hasegawa) investigated
LED from EYA to BS (Miyoki) failed -> try brighter LED
- Mar 11 (Fri)
connect PR2-PR3 duct (MIRAPRO)
DONE
- sweep ETMX and wait for AS PD to get any signal (Miyo,Hasegawa)
- sweep BS and wait for ETMY PD to get any signal (Fujii,Furuhata)
- Mar 12 (Sat)
- partially connect PR2-BS duct (MIRAPRO)
- LED from EYA to BS (Tomaru,Uchiyama,Hasegawa,Miyo) failed
- Mar 13 (Sun)
BS PD to face X (Uchiyama)
DONE
third week
EXA vent (Saito,Tomaru)
DONE
ETMX alignment re-adjustment (Uchiyama)
DONE
viewport for IXA (Michimura)
DONE
BS alignment re-adjustment (Uchiyama?)
DONE
ETMY oplev re-calibration
DONE
IYA vent (Kimura?)
DONE
get the beam back to IFI and then to REFL
DONE
set up REFL optics and cabling
DONE
beam to and from X and Y arms
DONE
What we do
- confirm mirror actuators (picomotors, coils, OSEMs) work from digital system
- prepare oplevs and cameras
- prepare RT models and MEDM screens for mirrors and LSC
- prepare feet for large beam profiler
- prepare pedestals for DC PDs
- REFL optics
- stable operation of IMC
initial alignment: JGW-T1604823
- lock 3km Michelson
LCGT Commissioning plan (As of Aug 2012)
Schedule
- List up issues to be addressed for installation procedure (September)
- Detailed installation plan (October)
- General Commissioning Strategy (how to deploy man power etc) (by the end of November)
List of items necessary for commissioning
The List is Here.