iKAGRA Commissioning
Commissioners at the site
Mar 31 to Apr 11: http://densuke.biz/list?cd=RGpffPNuJw6xwBMF
Mar 7 to Mar 20: http://densuke.biz/list?cd=wgUxhq6KHdfsUnWW
April Commissioning Break (Apr 1-10)
- Apr 1 (Fri) GV opening day (Leader: Kokeyama)
k1boot backup (Miyakawa)
1326 time adjust k1fw0, k1fw1 (Miyakawa)
1328 - fix GE RFM on k1ex0 (Miyakawa)
reboot and update display driver for monitor PCs (Miyakawa)
1328 unreel power cables around racks (Kokeyama,Michimura)
1330 close IOO rack (Kokeyama,Michimura)
open GVs close to IXA,IYA (Saito)
1336 restore Michelson (Kokeyama,Michimura,Komori)
1336 - cable making for seismometer,thermometer,hygrometer,barometer(Hayama)
- Apr 2 (Sat) Spare day (Leader: Michimura)
Apr 3 (Sun) PSL&IMC day (Leader: Michimura)
collect broken EXA viewport (Akutsu, Michimura)
replace ETMX oplev collimator holders (Akutsu,Michimura)
1346 - longer cable for IMC EOM (Nakano,Enomoto)
re-alignment of PMC (Nakano,Enomoto)
1349 replace TTFSS to the modified one (Nakano,Enomoto)
1348 - investigate TTFSS Interface slow nob (Nakano,Enomoto) [later]
replace 100 kHz LPF for IMC lock from SR560 to RC circuit, modify connectors to screw cables (Enomoto,Nakano)
1350 - make sure history of circuits are properly recorded on JGW Doc S numbers (Nakano,Enomoto)
put N terminators for RF distributor (Michimura)
replace Dsub 9pin cable for IMC REFL RF PD connected in series with longer one (Komori,Miyamoto)
protect IMC picomotor drivers and devices on the floor (Komori,Miyamoto)
tighten SMA cable connectors with wrench (Nakano,Enomoto,Komori,Miyamoto)
- measure ADC noise, PD dark noise (Komori,Michimura)
Apr 4 (Mon) PSL&IMC day (Leader: Michimura)
- connect PR2-BS bellows, VAC safety check (Saito, from PM)
- BS coil balance, sign check (Komori,Michimura)
- check lens/mirror mounts, pedestals, forks are properly fixed tight (Nakano,Enomoto,Nagano)
- replace orange power cable between PR3 to IOO rack to yellow one (Komori,Miyamoto)
- re-alignment of IMC and stabilize IMC lock (Nakano,Enomoto,Nagano)
- fix IQ demodulator being too hot issue (Nakano,Enomoto,Nagano)
- replace IMC coil differential cable with diff to single board (Nakano,Enomoto,Nagano)
- replace PR3 oplev collimator holder (Akutsu,Fujii)
- change ETMY oplev to folded configuration (Akutsu, Fujii)
- cancel --- (ETMY PZT cabling (Ohishi,Miyoki,Miyo)
- fix conlog, install printer, install VNC (Sasaki)
- make a state monitor on MEDM (Miyo)
- cable making for seismometer,thermometer,hygrometer,barometer(Hayama)
Apr 5 (Tue) PSL&IMC, PR3 day (Leader: Kawamura)
- connect PR2-BS bellows, VAC safety check (Saito)
- put the PMC control back to remote mode (Nakano,Enomoto,,Nagano,Kokeyama)
- fix PR3 LVDT WD issue (Shoda,Fujii,Miyakawa)
- PR3 LVDT offload with fishing lod (Shoda,Fujii)
- install the remote control system of the motors (Shoda,Fujii)
- check PR3 yaw picomotor (Shoda,Fujii)
- change ETMX oplev to folded configuration? (Akutsu, Hasegawa)
- safety check (Kawamura,Awai,Kimura,Tomaru)
- add memories on k1fw0, k1fw1, k1dc0 for 64sec frame data (Miyakawa)
- install PEMs, GIF maintenance (Araya,Miyo,Hayama,Kataoka)
- Apr 6 (Wed) PR3, MICH day (Leader: Michimura)
- connect PR2-BS bellows, VAC safety check (Saito, until AM)
Simulink NoiseBudget for Michelson (Shimoda,Michimura,Kokeyama)
- online calibration model, UGF servo (Aritomi,Michimura,Kokeyama)
- auto alignment (Miyo,Aso,Kokeyama)
- replace IMC, BS oplev collimator holders (Akutsu)
- watar gage setting (Hayama, Kataoka)
- realtime model for environmental sensors (Hayama, ?)
- Apr 7 (Thu) MICH day (Leader: Aso)
- feedback MICH also to BS (Aso)
- cancel --- (feedback MICH also to ETMY PZT (Miyo,Aso))
- realtime model for environmental sensors (Hayama, ?)
- Apr 8 (Fri) MICH day (Leader: Kokeyama)
- make MICH_LOCK guardian script to check calibration filter settings (Miyo)
- Apr 9 (Sat) Spare day
- Apr 10 (Sun) Spare day
- Apr 11 (Mon) Start test run 2nd round
TO DO after Apr test run but before iKAGRA ends
- oplev stability, noise measurements (with mirror fixed)
- scattering noise investigation
- PR3 height check
- measure PR3 suspension Q values
- save and note all the interferometer settings, configurations to write a paper
- investigate 15 Hz resonance in ETM suspensions
TO DO before Apr 11
- PSL, IMC related
- re-alignment of PMC
- put the PMC control back to remote mode [Apr 1-5]
- replace TTFSS to the modified one [Apr 1-5]
- Add a monitor of laser power right after the laser [Apr 1-5]
- re-alignment of IMC and stabilize IMC lock [Apr 6-8]
- replace 100 kHz LPF for IMC lock, from SR560 to RC circuit [Apr 6-8]
replace IMC REFL RF PD to the one which has DC output
DONE - close IOO rack (may need RF distributor modification) [Apr 1-5]
- fix IQ demodulator being too hot issue [Apr 1-5]
- Exchange holders for IMC oplev light sources (if required) [Apr 4-7]
- ISC related
- BS Oplev QPD diagonalization, coil balance [Apr 1-5, no laser hazard]
- EX, EY coil balance at higher frequency (~10Hz. Done for DC) [Apr 1-5]
- EY PZT [Apr 1-5]
IMC and MICH Noise budgeting using Simulink NoiseBudget [Apr 6-8]
- auto alignment for IMC and MICH (dithering? ASC?) [Apr 6-8]
- make online calibration model, UGF servo (auto gain adjuster using calibration lines) [Apr 6-8]
- feedback MICH also to BS to increase MICH feedback range [Apr 6-8]
- Exchange holders for BS/ETMs oplev light sources (if required) [Apr 4-7]
DetChar related
- lock loss investigation (use 3/25-3/11 data)
- AOS related
- replace EXA end viewport for EX2 camera [Apr 4-7]
- VAC related
- connect PR2-BS duct [Apr 4-5, no laser hazard]
- open the GVs (close to IXA,IYA) to reduce clipping [Apr 1]
- check anchors and bolts for vacuum tanks [Apr 4-5]
- PR3 related
- PR3 transfer function measurements, noise measurements [Apr 5-6]
- PR3 LVDT offload with fishing lod [Apr 5-6]
- fix PR3 LVDT WD issue [Apr 5-6]
- install the remote control system of the motors [Apr 5-6]
- check PR3 yaw picomotor [Apr 5-6]
- Exchange holder for PR3 oplev light source (if required) [Apr 4-7]
- DGS related
- k1boot backup [Apr 1, Miyakawa]
- Time adjust on k1fw0, k1fw1 [Apr 1, Miyakawa]
- Add memories on k1fw0, k1fw1, k1dc0 for 64sec frame data[Apr 5-8, Miyakawa]
- Fix camera noise [Kokeyama]
- Fix conlog [Apr 4-8, Sasaki]
- Fix GE RFM on k1ex0 [Apr 1, Miyakawa]
- Reboot and update display driver for monitor PCs [Apr 1, Miyakawa]
- Install printer of 2nd floor for k1ctr0-4 [Apr 4-8, Sasaki]
- Install VNC for monitor k1mon0-2 [Apr 4-8, Sasaki]
- Make a state monitor on MEDM [Apr 4-8, Miyo]
- General
Safety check (reported by Awai) [Apr 1-10]
Initial alignment work
first week
- Feb 24 (Wed): Miyakawa, Kokeyama, Aso
PR2 install (Aso et al)
DONE - PR3 install (Shoda et al)
- Feb 25 (Thu): Miyakawa, Kokeyama, Aso
- Feb 26 (Fri): Miyakawa, Kokeyama
- Feb 27 (Sat): Kokeyama, Akutsu
install Y end machines (Kokeyama)
DONE EY camera (Kokeyama)
DONE
- Feb 28 (Sun):
- Feb 29 (Mon): Miyakawa, Kokeyama, Michimura, Enomoto, Kataoka, Akutsu, Aso
- IMC stabilization (Kawamura,Enomoto)
finish IMMT1T QPD setup (Akutsu,Michimura,Kataoka)
DONE - prepare for IXC+IXA vent (Kimura)
peel PR3 first contact (Shoda,Fujii)
DONE check PR2 picomotors (Aso,Miyo)
DONE EX camera (Kokeyama)
DONE install PR2 viewport for the camera, and the camera (Akutsu,Kokeyama) half done (no camera yet)
- Mar 01 (Tue): Miyakawa, Kokeyama, Michimura, Enomoto, Kataoka, Akutsu, Aso
turn on PR3 local damping (Shoda,Okutomi,Fujii)
DONE pedestals for PDs (Michimura,Tomaru)
ARRIVED
- Mar 02 (Wed): Miyakawa, Kokeyama, Michimura, Enomoto, Akutsu, Aso, Furuhata, Kambara
put PRM-PR3 bellows (MIRAPRO 8:00-11:00)
DONE put BS-IXC bellows (MIRAPRO PM?)
DONE - IMC stabilization (Kawamura,Enomoto)
IXC+IXA vent (Kimura)
DONE finish IXA clean booth clean up, bring clean goods (Kimura,Tomaru)
DONE - peel ETMX first contact and set coils (Ohishi,Shoda,Aso) REMAINING ISSUE
install BS viewports for the oplev and the camera(Akutsu,Michimura,Kambara,Furuhata) half done (45deg issue, IPC issue)
install PR3 viewport for the camera, and the camera (Akutsu,Shoda,Okutomi,Fujii) half done (no camera yet)
k1cam0 and k1cam1 setup (Kokeyama)
DONE DAQ networks for EX and EY (Miyakawa,Kokeyama)
DONE calibrate PR3 oplev (Shoda,Okutomi,Fujii)
DONE
- Mar 03 (Thu): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Akutsu, Aso, Furuhata, Kambara
high power IMC (Enomoto)
DONE (~850 mW) PR2 alignment, beam profiling at PR3 half done (beam profiling not yet)
check IMMT2 picomotor (Miyo,Doi)
DONE ETMX,ETMY,BS picomotor (Miyo)
mostly DONE (ETMX to be confirmed) setup PDs at EXA (Akutsu,Fujii)
DONE peel ETMY first contact and set coils (Ohishi,Takahashi)
DONE - PR2, PR3, BS, IMMT1T cameras (Kokeyama) PR2 DONE, BS and PR3 to be done
- ETMX first contact issue: WE DECIDED TO GO WITH REMAINING FIRST CONTACT
- Mar 04 (Fri): Miyakawa, Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Furuhata, Kambara
PR3 rough alignment into IXA (Michimura,Ushiba,Kuwahara,Okutomi,Kambara,Furuhata)
DONE (beam profiling at IXA not yet) DQ channels for EXA EYA PDs (Kokeyama)
Done fix IPC errors (Miyakawa, Kokeyama)
Done open BS-IXC GV (Saito,Uchiyama,Kimura)
DONE place ND filters to MC_REFL and PMC_TRANS cameras, and check ghost beams (Enomoto)
DONE (decreased power to ~250 mW)
- Mar 05 (Sat): Kokeyama, Kataoka
- Mar 06 (Sun): Kataoka
- block PSL beam for VAC work (Uchiyama)
second week
- Mar 07 (Mon)
- beam clipping at BS check, BS rough alignment into Y, IXA beam check with respect to PR3 alignment, beam profiling at IXA?, sweep PR3 at night (Michimura,Ushiba,Kataoka,Kambara,Furuhata,Okutomi)
check ETMX actuation (Ohishi,Takahashi)
DONE calibrate ETMX oplev (Kuwahara)
DONE ETMX picomotor check (Miyo)
DONE install EXA end flange (Tomaru)
DONE calibrate ETMY oplev (Kokeyama,Kuwahara)
DONE PR3 oplev calibration result, check PR3 oplev channels (Kokeyama,Okutomi)
DONE - RFM test between center area and both ends (Kokeyama)
- Mar 08 (Tue)
install BS oplev and calibrate (Akutsu,Hasegawa,Kuwahara)
DONE fine adjustment of PR3 alignment to BS and IXA, Xarm viewport, PR3 sweep to EXA (Michimura,Shoda,Okutomi,Ushiba,Furuhata,Kagawa,Fujisawa)
DONE install EXA end viewport (Akutsu,Hasegawa,Kuwahara)
DONE check ETMY actuation (Ohishi,Takahashi,Kuwahara)
DONE install EYA end flange (Kimura,Tomaru)
DONE VIS guardian (Shoda,Okutomi,Kokeyama)
DONE
- Mar 09 (Wed)
BS actuation check (Ushiba,Kuwahara,Furuhata)
DONE setup PD at EYA (Akutsu,Hasegawa,Kambara)
DONE install EYA end viewport (Akutsu,Hasegawa,Kambara)
DONE take PD from EXA, EXA beam check, ETMX rough alignment (Michimura,Fujii)
DONE, DONE setup PD at BS (Akutsu,Hasegawa,Kambara)
DONE EXA end, EYA end cameras (Kokeyama)
DONE RFM network between center and Yend (Kokeyama)
DONE
- Mar 10 (Thu)
connect BS-IYC (MIRAPRO)
DONE start EXA evacuation (Kimura)
DONE block Y arm beam (Akutsu,Kambara,Hasegawa) investigated
LED from EYA to BS (Miyoki) failed -> try brighter LED
- Mar 11 (Fri)
connect PR2-PR3 duct (MIRAPRO)
DONE - sweep ETMX and wait for AS PD to get any signal (Miyo,Hasegawa)
- sweep BS and wait for ETMY PD to get any signal (Fujii,Furuhata)
- Mar 12 (Sat)
- partially connect PR2-BS duct (MIRAPRO)
- LED from EYA to BS (Tomaru,Uchiyama,Hasegawa,Miyo) failed
- Mar 13 (Sun)
BS PD to face X (Uchiyama)
DONE
third week
EXA vent (Saito,Tomaru)
DONE ETMX alignment re-adjustment (Uchiyama)
DONE viewport for IXA (Michimura)
DONE BS alignment re-adjustment (Uchiyama?)
DONE ETMY oplev re-calibration
DONE IYA vent (Kimura?)
DONE get the beam back to IFI and then to REFL
DONE set up REFL optics and cabling
DONE beam to and from X and Y arms
DONE
TO DO before Mar 26
insert PR2-BS duct
Done - evacuate IXA and IYA (we do not evacuate anything in March)
- IOO cabling check (?)
- get PMC back to remote control mode (To be done by Apr 11)
coil balancing for BS, ETMX, ETMY
Done except BS coil offload with picomotors for BS, ETMX, ETMY (and PR3 yaw)
Done oplev damping for BS, ETMX, ETMY, PR3
Done more alignment to maximize contrast, clipping investigation
Done, 75%MAX measure power at REFL port from X and Y arms
Done install REFL camera (steal IMMT1T camera)
Done check LSC model
Done lock Michelson and measure openloop transfer function
Done MICH guardian
Done calibration model
Done get strain spectrum
Done
What we do
- confirm mirror actuators (picomotors, coils, OSEMs) work from digital system
- prepare oplevs and cameras
- prepare RT models and MEDM screens for mirrors and LSC
- prepare feet for large beam profiler
- prepare pedestals for DC PDs
- REFL optics
- stable operation of IMC
initial alignment: JGW-T1604823
- lock 3km Michelson
LCGT Commissioning plan (As of Aug 2012)
Schedule
- List up issues to be addressed for installation procedure (September)
- Detailed installation plan (October)
- General Commissioning Strategy (how to deploy man power etc) (by the end of November)
List of items necessary for commissioning
The List is Here.