iKAGRA Commissioning
Travel Plan
- Feb 24 (Wed): Kokeyama
- Feb 25 (Thu): Kokeyama
- Feb 26 (Fri): Kokeyama
- Feb 27 (Sat): Kokeyama
- Feb 28 (Sun): Kokeyama
- Feb 29 (Mon): Kokeyama, Michimura, Enomoto, Kataoka
- Mar 01 (Tue): Kokeyama, Michimura, Enomoto, Kataoka
- Mar 02 (Wed): Kokeyama, Michimura, Enomoto
- Mar 03 (Thu): Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara
- Mar 04 (Fri): Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara
- Mar 05 (Sat): Kokeyama, Kataoka
- Mar 06 (Sun): Kokeyama, Kataoka
- Mar 07 (Mon): Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Kataoka
- Mar 08 (Tue): Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara, Kataoka
- Mar 09 (Wed): Kokeyama, Michimura, Enomoto, Ushiba, Kuwahara
- Mar 10 (Thu): Kokeyama, Michimura, Enomoto
- Mar 11 (Fri): Kokeyama, Michimura, Enomoto
- Mar 12 (Sat): Kokeyama
- Mar 13 (Sun):
- Mar 14 (Mon):
- Mar 15 (Tue): Michimura
Initial Alignment
LCGT Commissioning plan (As of Aug 2012)
Schedule
- List up issues to be addressed for installation procedure (September)
- Detailed installation plan (October)
- General Commissioning Strategy (how to deploy man power etc) (by the end of November)
List of items necessary for commissioning
The List is Here.