Differences between revisions 1 and 13 (spanning 12 versions)
Revision 1 as of 2021-06-15 09:20:45
Size: 225
Comment:
Revision 13 as of 2021-06-15 16:05:28
Size: 4613
Comment:
Deletions are marked like this. Additions are marked like this.
Line 3: Line 3:
Line 5: Line 6:
=== References ===
 * klog review during O3 commissioining [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=12729|JGW-E2112729]]
 * [[KAGRA/Subgroups/MIF/OpticalCharacterization|Summary of Optical Characterization]]
 * Commissioning (IOO): Evaluation meeting [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=12491|JGW-G2112491]]
 * MIF Schedule Estimate for bKAGRA Phase 2 [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7079|JGW-T1707079]]
 * Definitions for the X arm commissioning [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=8343|JGW-T1808343]]
 * Definitions for the DRMI commissioning [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9573|JGW-T1909573]]
Line 6: Line 15:
 * Tune f1, f2, f3 frequencies to IMC FSR
 * Replace all the in-vac steering mirrors and pick-off mirrors to proper ones [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=12592|JGW-T2112592]]
 * Replace all the beam splitters in in-air optical tables to non-polarizing beam splitters [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=12956|JGW-D2112956]]
  * This is necessary to estimate the polarization content of the interferometer correctly (without too much confusion)
 * Install polarization optics to backward POP or POS, and TRY and TRY.
  * This is necessary to estimate the arm cavity round-trip loss correctly [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11633|JGW-T2011633]]
 * Check actuation efficiencies of IMC mirrors, frequency actuation efficiencies of PSL.
 * Install picomotor+PZT steering mirrors for POP green and POS green.
 * Install coil driver switch for ETMs (and ITMs?).
  * High power for lock acquisition, low power for low noise mode.
 * Install picomotors to center the beam on oplev QPDs and ASC QPDs.
Line 8: Line 28:
 * Measure the finesse at room temperature and at cryogenic temperatures, for both 1064 nm and 532 nm.
 * Measure the round-trip loss by taking into account the effect of birefringence correctly.
   * Measure the beam spot position dependence.
 * Measure the amount of POP/POS p-pol when the arm is locked and unlocked.
 * Measure the mode-matching for both 1064 nm and 532 nm.
 * Tune the Gouy phase separation between two QPDs at REFL/AS/TRX.
 * Measure the alignment sensing matrix at REFL/AS/TRX, for ITM and ETM.
   * Try closing ASC loops.
 * Measure modulation depths for f1, f2 and f3.
 * Check ITM and ETM actuation efficiencies.
 * Make a power budget of each ISC detection port.
Line 10: Line 41:
 * Same as Xarm.
Line 12: Line 44:
 * Check BS actuation efficiency.
Line 13: Line 46:
== FPMI == == Power recycling cavity ==
 * Measure PRY length and PRX length.
  * Previous methods give inconsistent results and also not compatible with Schnupp asymmetry measurements.
 * Tune IMC length to PRC length (and re-tune sideband frequencies).
 * Check actuation efficiency of PR mirrors.
 * Measure PRC Gouy phase.
Line 15: Line 53:
== PRFPMI == == Signal recycling cavity ==
 * Check actuation efficiency of SR mirrors.
 * Measure SRC Gouy phase.

== Dual Recycled Michelson ==
 * Measure power recycling gains for carrier and sidebands, with and without SRC.
 * Measure length sensing matrix.
 * Measure power at each ISC detection port when DRMI is locked.
 * Tune the Gouy phase separation between two QPDs at POP.
 * Measure the alignment sensing matrix at REFL/POP/AS.
  * Try closing ASC loops.

== Fabry-Perot Michelson ==
 * Measure length sensing matrix.
 * Measure power at each ISC detection port when FPMI is locked.
 * Measure the alignment sensing matrix at REFL/POP/AS/TRX/TRY.
  * Try closing ASC loops.
 * Do some noise hunting at low frequencies and VIS commissioning with FPMI

== Power Recycled Fabry-Perot Michelson ==
 * Measure length sensing matrix.
 * Measure power recycling gains for carrier and sidebands
 * Measure power at each ISC detection port when PRFPMI is locked.
 * Measure the alignment sensing matrix at REFL/POP/AS/TRX/TRY.
  * Try closing ASC loops.

== Resonant Sideband Extraction ==
 * Measure length sensing matrix.
 * Measure power recycling gains for carrier and sidebands
 * Measure the cavity pole
 * Measure power at each ISC detection port when PRFPMI is locked.
 * Measure the alignment sensing matrix at REFL/POP/AS/TRX/TRY.
  * Try closing ASC loops.

O4 Commissioning Task List

This is a list of things to do for each commissioning stage for O4.

Each stage include ASC.

References

Preparations

  • Tune f1, f2, f3 frequencies to IMC FSR
  • Replace all the in-vac steering mirrors and pick-off mirrors to proper ones JGW-T2112592

  • Replace all the beam splitters in in-air optical tables to non-polarizing beam splitters JGW-D2112956

    • This is necessary to estimate the polarization content of the interferometer correctly (without too much confusion)
  • Install polarization optics to backward POP or POS, and TRY and TRY.
    • This is necessary to estimate the arm cavity round-trip loss correctly JGW-T2011633

  • Check actuation efficiencies of IMC mirrors, frequency actuation efficiencies of PSL.
  • Install picomotor+PZT steering mirrors for POP green and POS green.
  • Install coil driver switch for ETMs (and ITMs?).
    • High power for lock acquisition, low power for low noise mode.
  • Install picomotors to center the beam on oplev QPDs and ASC QPDs.

Xarm

  • Measure the finesse at room temperature and at cryogenic temperatures, for both 1064 nm and 532 nm.
  • Measure the round-trip loss by taking into account the effect of birefringence correctly.
    • Measure the beam spot position dependence.
  • Measure the amount of POP/POS p-pol when the arm is locked and unlocked.
  • Measure the mode-matching for both 1064 nm and 532 nm.
  • Tune the Gouy phase separation between two QPDs at REFL/AS/TRX.
  • Measure the alignment sensing matrix at REFL/AS/TRX, for ITM and ETM.
    • Try closing ASC loops.
  • Measure modulation depths for f1, f2 and f3.
  • Check ITM and ETM actuation efficiencies.
  • Make a power budget of each ISC detection port.

Yarm

  • Same as Xarm.

Michelson

  • Check BS actuation efficiency.

Power recycling cavity

  • Measure PRY length and PRX length.
    • Previous methods give inconsistent results and also not compatible with Schnupp asymmetry measurements.
  • Tune IMC length to PRC length (and re-tune sideband frequencies).
  • Check actuation efficiency of PR mirrors.
  • Measure PRC Gouy phase.

Signal recycling cavity

  • Check actuation efficiency of SR mirrors.
  • Measure SRC Gouy phase.

Dual Recycled Michelson

  • Measure power recycling gains for carrier and sidebands, with and without SRC.
  • Measure length sensing matrix.
  • Measure power at each ISC detection port when DRMI is locked.
  • Tune the Gouy phase separation between two QPDs at POP.
  • Measure the alignment sensing matrix at REFL/POP/AS.
    • Try closing ASC loops.

Fabry-Perot Michelson

  • Measure length sensing matrix.
  • Measure power at each ISC detection port when FPMI is locked.
  • Measure the alignment sensing matrix at REFL/POP/AS/TRX/TRY.
    • Try closing ASC loops.
  • Do some noise hunting at low frequencies and VIS commissioning with FPMI

Power Recycled Fabry-Perot Michelson

  • Measure length sensing matrix.
  • Measure power recycling gains for carrier and sidebands
  • Measure power at each ISC detection port when PRFPMI is locked.
  • Measure the alignment sensing matrix at REFL/POP/AS/TRX/TRY.
    • Try closing ASC loops.

Resonant Sideband Extraction

  • Measure length sensing matrix.
  • Measure power recycling gains for carrier and sidebands
  • Measure the cavity pole
  • Measure power at each ISC detection port when PRFPMI is locked.
  • Measure the alignment sensing matrix at REFL/POP/AS/TRX/TRY.
    • Try closing ASC loops.