Line 9: Line 9:
 * Commissioning (IOO): Evaluation meeting [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=12491|JGW-G2112491]]
Line 20: Line 21:
 * Check actuation efficiencies of IMC mirrors, frequency actuation efficiencies of PSL.
 * Install picomotor+PZT steering mirrors for POP green and POS green.
 * Install coil driver switch for ETMs (and ITMs?).
  * High power for lock acquisition, low power for low noise mode.
 * Install picomotors to center the beam on oplev QPDs and ASC QPDs.
Line 24: Line 30:
   * Measure the beam spot position dependence    * Measure the beam spot position dependence.
* Measure the amount of POP/POS p-pol when the arm is locked and unlocked.
Line 26: Line 33:
 * Tune the Gouy phase separation between two QPDs at TRX.
 * Measure the alignment sensing matrix at REFL/AS/TRX, for ITMX and ETMX.
 * Tune the Gouy phase separation between two QPDs at REFL/AS/TRX.
   * Make sure all the signals are in in-phase
.
 * Measure the alignment sensing matrix at REFL/AS/TRX, for ITM and ETM.
Line 30: Line 38:
 * Check ITM and ETM actuation efficiencies.
 * Make a power budget of each ISC detection port.
 * Refining the automation -- mainly for the successive full ifo initial alignment.
 * Leave a record on the demod phases -- for repeating the Schnup asymmetry measurement.
Line 32: Line 45:
 * Same as Xarm  * Same as Xarm.
Line 35: Line 48:
 * Check BS actuation efficiency.
 * Check out the LSC optical gain. Should be easy enough to doublecheck.
 * Measure, again, the contrast defect.
 * Record typical Mich length noise.
 * Close the ASC loops -- mainly for the purpose of the initial alignment automation.
 * Refine the automation.
Line 37: Line 56:
 * Measure PRY length and PRX length.
  * Previous methods give inconsistent results and also not compatible with Schnupp asymmetry measurements.
 * Tune IMC length to PRC length (and re-tune sideband frequencies).
 * Check actuation efficiency of PR mirrors.
 * Measure PRC Gouy phase.
 * Close the ASC loops.
 * Refine the automation.
 * Check out the power build up in the carrier-locked and side-band locked conditions
 * Correlation measurement of p/s-pol sloshing (https://klog.icrr.u-tokyo.ac.jp/osl/?r=9333) against angular fluctuations or whatever.
 * Identification of any drifty suspensions as the carrier is locked -- to support the coming full lock operation.
Line 38: Line 67:
== FPMI == == Signal recycling cavity ==
 * Check actuation efficiency of SR mirrors.
 * Measure SRC Gouy phase.
 * Automation?
Line 40: Line 72:
== PRFPMI == == Dual Recycled Michelson ==
 * Measure power recycling gains for carrier and sidebands, with and without SRC.
 * Measure length sensing matrix.
 * Measure power at each ISC detection port when DRMI is locked.
 * Tune the Gouy phase separation between two QPDs at POP.
 * Measure the alignment sensing matrix at REFL/POP/AS.
  * Try closing ASC loops.

== Fabry-Perot Michelson ==
 * Measure length sensing matrix.
 * Measure power at each ISC detection port when FPMI is locked.
 * Measure the alignment sensing matrix at REFL/POP/AS/TRX/TRY.
  * Try closing ASC loops.
 * Do some noise hunting at low frequencies and VIS commissioning with FPMI
 *

== Power Recycled Fabry-Perot Michelson ==
 * Measure length sensing matrix.
 * Measure power recycling gains for carrier and sidebands
 * Measure power at each ISC detection port when PRFPMI is locked.
 * Measure the alignment sensing matrix at REFL/POP/AS/TRX/TRY.
  * Try closing ASC loops.

== Resonant Sideband Extraction ==
 * Measure length sensing matrix.
 * Measure power recycling gains for carrier and sidebands
 * Measure the cavity pole
 * Measure power at each ISC detection port when PRFPMI is locked.
 * Measure the alignment sensing matrix at REFL/POP/AS/TRX/TRY.
  * Try closing ASC loops.

O4 Commissioning Task List

This is a list of things to do for each commissioning stage for O4.

Each stage include ASC.

References

Preparations

  • Tune f1, f2, f3 frequencies to IMC FSR
  • Replace all the in-vac steering mirrors and pick-off mirrors to proper ones JGW-T2112592

  • Replace all the beam splitters in in-air optical tables to non-polarizing beam splitters JGW-D2112956

    • This is necessary to estimate the polarization content of the interferometer correctly (without too much confusion)
  • Install polarization optics to backward POP or POS, and TRY and TRY.
    • This is necessary to estimate the arm cavity round-trip loss correctly JGW-T2011633

  • Check actuation efficiencies of IMC mirrors, frequency actuation efficiencies of PSL.
  • Install picomotor+PZT steering mirrors for POP green and POS green.
  • Install coil driver switch for ETMs (and ITMs?).
    • High power for lock acquisition, low power for low noise mode.
  • Install picomotors to center the beam on oplev QPDs and ASC QPDs.

Xarm

  • Measure the finesse at room temperature and at cryogenic temperatures, for both 1064 nm and 532 nm.
  • Measure the round-trip loss by taking into account the effect of birefringence correctly.
    • Measure the beam spot position dependence.
  • Measure the amount of POP/POS p-pol when the arm is locked and unlocked.
  • Measure the mode-matching for both 1064 nm and 532 nm.
  • Tune the Gouy phase separation between two QPDs at REFL/AS/TRX.
    • Make sure all the signals are in in-phase.
  • Measure the alignment sensing matrix at REFL/AS/TRX, for ITM and ETM.
    • Try closing ASC loops.
  • Measure modulation depths for f1, f2 and f3.
  • Check ITM and ETM actuation efficiencies.
  • Make a power budget of each ISC detection port.
  • Refining the automation -- mainly for the successive full ifo initial alignment.
  • Leave a record on the demod phases -- for repeating the Schnup asymmetry measurement.

Yarm

  • Same as Xarm.

Michelson

  • Check BS actuation efficiency.
  • Check out the LSC optical gain. Should be easy enough to doublecheck.
  • Measure, again, the contrast defect.
  • Record typical Mich length noise.
  • Close the ASC loops -- mainly for the purpose of the initial alignment automation.
  • Refine the automation.

Power recycling cavity

  • Measure PRY length and PRX length.
    • Previous methods give inconsistent results and also not compatible with Schnupp asymmetry measurements.
  • Tune IMC length to PRC length (and re-tune sideband frequencies).
  • Check actuation efficiency of PR mirrors.
  • Measure PRC Gouy phase.
  • Close the ASC loops.
  • Refine the automation.
  • Check out the power build up in the carrier-locked and side-band locked conditions
  • Correlation measurement of p/s-pol sloshing (https://klog.icrr.u-tokyo.ac.jp/osl/?r=9333) against angular fluctuations or whatever.

  • Identification of any drifty suspensions as the carrier is locked -- to support the coming full lock operation.

Signal recycling cavity

  • Check actuation efficiency of SR mirrors.
  • Measure SRC Gouy phase.
  • Automation?

Dual Recycled Michelson

  • Measure power recycling gains for carrier and sidebands, with and without SRC.
  • Measure length sensing matrix.
  • Measure power at each ISC detection port when DRMI is locked.
  • Tune the Gouy phase separation between two QPDs at POP.
  • Measure the alignment sensing matrix at REFL/POP/AS.
    • Try closing ASC loops.

Fabry-Perot Michelson

  • Measure length sensing matrix.
  • Measure power at each ISC detection port when FPMI is locked.
  • Measure the alignment sensing matrix at REFL/POP/AS/TRX/TRY.
    • Try closing ASC loops.
  • Do some noise hunting at low frequencies and VIS commissioning with FPMI

Power Recycled Fabry-Perot Michelson

  • Measure length sensing matrix.
  • Measure power recycling gains for carrier and sidebands
  • Measure power at each ISC detection port when PRFPMI is locked.
  • Measure the alignment sensing matrix at REFL/POP/AS/TRX/TRY.
    • Try closing ASC loops.

Resonant Sideband Extraction

  • Measure length sensing matrix.
  • Measure power recycling gains for carrier and sidebands
  • Measure the cavity pole
  • Measure power at each ISC detection port when PRFPMI is locked.
  • Measure the alignment sensing matrix at REFL/POP/AS/TRX/TRY.
    • Try closing ASC loops.