Line 21: | Line 21: |
* Install picomotor+PZT steering mirrors for POP green and POS green. | |
Line 25: | Line 26: |
* Measure the beam spot position dependence | * Measure the beam spot position dependence. |
Line 33: | Line 34: |
* Make a power budget of each ISC detection port. | |
Line 35: | Line 37: |
* Same as Xarm | * Same as Xarm. |
Line 38: | Line 40: |
* Check BS actuation efficiency | * Check BS actuation efficiency. |
Line 41: | Line 43: |
* Measure PRY length and PRX length * Previous methods give inconsistent results and also not compatible with Schnupp asymmetry measurements * Tune IMC length to PRC length (and re-tune sideband frequencies) * Check actuation efficiency of PR mirrors * Measure PRC Gouy phase |
* Measure PRY length and PRX length. * Previous methods give inconsistent results and also not compatible with Schnupp asymmetry measurements. * Tune IMC length to PRC length (and re-tune sideband frequencies). * Check actuation efficiency of PR mirrors. * Measure PRC Gouy phase. |
Line 48: | Line 50: |
* Check actuation efficiency of SR mirrors * Measure SRC Gouy phase |
* Check actuation efficiency of SR mirrors. * Measure SRC Gouy phase. |
Line 54: | Line 56: |
* Measure power at each ISC detection ports when DRMI is locked | * Measure power at each ISC detection port when DRMI is locked. |
Line 60: | Line 62: |
* Measure power at each ISC detection ports when FPMI is locked | * Measure power at each ISC detection port when FPMI is locked. |
Line 67: | Line 69: |
* Measure power at each ISC detection ports when PRFPMI is locked | * Measure power at each ISC detection port when PRFPMI is locked. |
Line 75: | Line 77: |
* Measure power at each ISC detection ports when PRFPMI is locked | * Measure power at each ISC detection port when PRFPMI is locked. |
O4 Commissioning Task List
This is a list of things to do for each commissioning stage for O4.
Each stage include ASC.
References
klog review during O3 commissioining JGW-E2112729
MIF Schedule Estimate for bKAGRA Phase 2 JGW-T1707079
Definitions for the X arm commissioning JGW-T1808343
Definitions for the DRMI commissioning JGW-T1909573
Preparations
- Tune f1, f2, f3 frequencies to IMC FSR
Replace all the in-vac steering mirrors and pick-off mirrors to proper ones JGW-T2112592
Replace all the beam splitters in in-air optical tables to non-polarizing beam splitters JGW-D2112956
- This is necessary to estimate the polarization content of the interferometer correctly (without too much confusion)
- Install polarization optics to backward POP or POS, and TRY and TRY.
This is necessary to estimate the arm cavity round-trip loss correctly JGW-T2011633
- Check actuation efficiencies of IMC mirrors, frequency actuation efficiencies of PSL.
- Install picomotor+PZT steering mirrors for POP green and POS green.
Xarm
- Measure the finesse at room temperature and at cryogenic temperatures, for both 1064 nm and 532 nm.
- Measure the round-trip loss by taking into account the effect of birefringence correctly.
- Measure the beam spot position dependence.
- Measure the amount of POP/POS p-pol when the arm is locked and unlocked.
- Measure the mode-matching for both 1064 nm and 532 nm.
- Tune the Gouy phase separation between two QPDs at TRX.
- Measure the alignment sensing matrix at REFL/AS/TRX, for ITM and ETM.
- Try closing ASC loops.
- Measure modulation depths for f1, f2 and f3.
- Check ITM and ETM actuation efficiencies.
- Make a power budget of each ISC detection port.
Yarm
- Same as Xarm.
Michelson
- Check BS actuation efficiency.
Power recycling cavity
- Measure PRY length and PRX length.
- Previous methods give inconsistent results and also not compatible with Schnupp asymmetry measurements.
- Tune IMC length to PRC length (and re-tune sideband frequencies).
- Check actuation efficiency of PR mirrors.
- Measure PRC Gouy phase.
Signal recycling cavity
- Check actuation efficiency of SR mirrors.
- Measure SRC Gouy phase.
Dual Recycled Michelson
- Measure power recycling gains for carrier and sidebands, with and without SRC.
- Measure length sensing matrix.
- Measure power at each ISC detection port when DRMI is locked.
- Measure the alignment sensing matrix at REFL/POP/AS.
- Try closing ASC loops.
Fabry-Perot Michelson
- Measure length sensing matrix.
- Measure power at each ISC detection port when FPMI is locked.
- Measure the alignment sensing matrix at REFL/POP/AS/TRX/TRY.
- Try closing ASC loops.
Power Recycled Fabry-Perot Michelson
- Measure length sensing matrix.
- Measure power recycling gains for carrier and sidebands
- Measure power at each ISC detection port when PRFPMI is locked.
- Measure the alignment sensing matrix at REFL/POP/AS/TRX/TRY.
- Try closing ASC loops.
Resonant Sideband Extraction
- Measure length sensing matrix.
- Measure power recycling gains for carrier and sidebands
- Measure the cavity pole
- Measure power at each ISC detection port when PRFPMI is locked.
- Measure the alignment sensing matrix at REFL/POP/AS/TRX/TRY.
- Try closing ASC loops.