O4 Commissioning Task List
This is a list of things to do for each commissioning stage for O4.
Each stage include ASC.
References
klog review during O3 commissioining JGW-E2112729
MIF Schedule Estimate for bKAGRA Phase 2 JGW-T1707079
Definitions for the X arm commissioning JGW-T1808343
Definitions for the DRMI commissioning JGW-T1909573
Preparations
- Tune f1, f2, f3 frequencies to IMC FSR
Replace all the in-vac steering mirrors and pick-off mirrors to proper ones JGW-T2112592
Replace all the beam splitters in in-air optical tables to non-polarizing beam splitters JGW-D2112956
- This is necessary to estimate the polarization content of the interferometer correctly (without too much confusion)
- Install polarization optics to backward POP or POS, and TRY and TRY.
This is necessary to estimate the arm cavity round-trip loss correctly JGW-T2011633
Xarm
- Measure the finesse at room temperature and at cryogenic temperatures, for both 1064 nm and 532 nm.
- Measure the round-trip loss by taking into account the effect of birefringence correctly.
- Measure the beam spot position dependence
- Measure the mode-matching for both 1064 nm and 532 nm.
- Tune the Gouy phase separation between two QPDs at TRX.
- Measure the alignment sensing matrix at REFL/AS/TRX, for ITMX and ETMX.
- Try closing ASC loops.
- Measure modulation depths for f1, f2 and f3.
Yarm
- Same as Xarm
Michelson
Power recycling cavity
FPMI