Minute of PEM meeting
- Date: 2019/6/25 17:00-18:00(JST)
- Attendance: Yokozawa, Kozakai, Mori, TTanaka, Kaihotsu, Somiya, Okawa, Fujikawa, Washimi, Oshino
=== Agenda ===
- General issue
- Installation of the 1st PEM toward the O3 was (almost) completed!!
- Center area, X end, Y end, weather station
- Remaining : Magnetometer!!!
- 2nd PEM installation will be started after the characterization of the chambers. (After O3??)
Washimi PEM webpage URL
- PEM map provided by the medm was updated.
- The power supply status measurements will be (re-)start soon
- With the discussion with the Facility
- Task list toward the O3
- Please send e-mail to me if you have comments.
- Engineering run
- 1st engineering run : Jun. 8th 12:00-18:00(JST) : Xarm cavity
- What should we do toward the next engineering run
- KIW6
- Washimi-san and Kaihotsu-san presented
- Currently, I heard that PEM activity is great! This is good news.
- English meeting
- We will have a monthly English meeting(Mainly share the information with Virgo people)
- The third Tuesday of every month 17:00-(JST) 10:00-(CEST)
2nd meeting will be held at 16th Jul.(Tue) 17:00-18:00 URL
- Seismon issue
- We already installed to KAGRA system
- Need the tuning for the KAGRA
- Large earthquake happened this month, we "should" be a safe mode before coming large earthquake (PEM issue???)
- Yuzu summary page was upgraded!
- There will be a report in the each member progress
- One student (Yikang) will come to KAGRA and work with PEM group
- Last his visiting was cryo issue
- Magnetometer and shaker injection (?)
- Installation of the 1st PEM toward the O3 was (almost) completed!!
- each member progress
- Yokozawa
- Coherent analysis during the engineering run
- Bruco analysis
- Origin of the vibration
- Washimi
- KIW6 report
- Status talk
- Importance of the PEM injection
Suspect of the magnetic field requirement -> 勾配のほうだった
- LIGOで静電場が問題になってきている。ポンプからの鉄カスなどが影響するかもしれない、caltechのabbottさんなど
- New accelerometer
- USB output accelerometer will be arrived at KAGRA (6/26)
- Check the signal soon
- plan for cryochamber characterization
- Summary to the paper at August
- Scheduling
- Thunderbolt issue
- Thunderbolt generated the magnetic field and observed by the magnetometer
- No monitor tool in the weather station
- KIW6 report
- Kozakai
- Trigger rate analysis during engineering run
- 6 segments with long lock
- Trigger time
IMC PC was replaced before the engineering run -> IMC trigger 1min
- Accelerometer trigger rate was not so changed between fan on and off.
- No large SNR glitch for the important channel
- Time different between previous trigger
- random case : clean explanation plot
- Collaboration with Yuzu summary page
- Generate the help slide
- Trigger rate analysis during engineering run
- Miyo
- Effect the protect shied to the seismometer
Long term study of the KAGRA ground motion, Link
- select 300 1h data from February
- categorize good or bad
- Bad is earthquake, daq troble , ...
- 5% - 95%の範囲を示した。
- 2-6月の静かな時、世界基準のLow modelと近い感じ
- 関口さん@clio site : Lowとhighの間に位置している。
- 月ごと、時間ごと
- BLRMSの時間変化
- 気象との相関、波や低気圧やいろいろ
- Oshino
- Weather station issue
- TTanaka(may not attend this meeting)
Preparing for the PEM injection pdf
- Microphone calibration
- Okutomi
- Shaker injection
- Kaihotsu
- Report about the KIW6
- Yuzurihara
- Yuzu summary page
- etc
- Yokozawa
- github progress