Weekly PEM meeting
- 2020/01/28(Tue) 16:00-(JST)
- Regular meeting meeting (Japanese)
Web meeting with Zoom2 (Zoom2)
Agenda
General issue
- Interferometer status
- Finally, we can lock the PRFPMI
- Transmittance laser power became 100 times higher than FPMI
- Lock duration is about 30min at maximum
- OMC commissioning is also ongoing
~100Hz noise and line noise of the higher frequency -> PEM
- Finally, we can lock the PRFPMI
- New PEMs
- We bought the ACO power supply, microphone and accelerometers(end of Feb.)
- Basically the portable PEMs
- PEM plan
- PEM injection
- Shaker injection (TTanaka, Yokozawa)
- Acoustic injection (TTanaka, Yokozawa)
PSL, REFL and AS table injection (Defence of TT Thesis -> tomorrow)
- magnetic field injection (Niigata TTanaka, Fujikawa, Yokozawa)
- Effect of the air cooler magnetic field
- AS, REFL table injection
- He is writing the thesis
- Hammering test
Hammering test @ Y-end : around 2/15 (JGW-G2011419)
- Long term PEM evaluation
- Turning off the instruments
- Many microphone in the PSL room
- PEM injection
- Conference
Each progress
- Yokozawa
- Planning toward the O3 run
- IX. IY microphone
- Instrument switch off
- Washimi
Noise around 100Hz @ ER3 klog12629
Portable PEM with DataLogger GutHub201
PEM chassis JGW-T2011425
- Kozakai
Coupling with calibration line @ ER3 slides
- TTanaka(ICRR)
- shaker injection with FPMI
Master thesis JGW-G1910387
- Fujikawa
- Lock loss study
- TTanaka(Niigata)
- Magnetic field from air cooler and compressor
- Magnetic field injection to AS and REFL table
- etc