* December 17-24 24h engineering run * [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/EngineeringRun/ER191217_24/ | wiki]] * We also held the post ER. We turned off the FFUs and vacuum pumps * Lock acquisition to PRFPMI * There is still some peaks in the lower frequency * Type-A resonant frequency [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11116|JGWDoc11116]] * Peaks appeared at higher frequency * PEM injection to REFL table * After that, we will move to noise hunting |
* Finally, we can lock the PRFPMI * Transmittance laser power became 100 times higher than FPMI * Lock duration is about 30min at maximum * OMC commissioning is also ongoing |
Line 23: | Line 18: |
* PEM plan January * Identification of the ~100Hz noise source * (Maybe, ) the dominant noise for lower frequency may come from suspension * After the success of the PRFPMI (or chance to operate the FPMI), we would like to do following things * Understanding the coupling function detected at the refl table * At the some point, we detected the larger coupling function * Periscope or some optics? * We would like to inject sound or vibration to AS, POP and TMS table |
* New PEMs * We bought the ACO power supply, microphone and accelerometers(end of Feb.) * Basically the portable PEMs * PEM plan * PEM injection * Shaker injection (TTanaka, Yokozawa) * Acoustic injection (TTanaka, Yokozawa) * PSL, REFL and AS table injection (Defence of TT Thesis -> tomorrow) * magnetic field injection (Niigata TTanaka, Fujikawa, Yokozawa) * Effect of the air cooler magnetic field * AS, REFL table injection * He is writing the thesis * Hammering test |
Line 32: | Line 33: |
* PEM festival * 01/14(Tue) 9:00-15:00 * Evaluate the scattered light for payload (with CRY team) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=12293]] * 01/15(Wed) (Maybe expanded) * Turned off almost all FFUs and vacuum pumps |
* Turning off the instruments * Many microphone in the PSL room |
Line 45: | Line 42: |
* PEM injection * Shaker injection1 (TTanaka, Yokozawa) * acoustic injection (TTanaka, Yokozawa) * PSL, REFL and AS table injection * Analysis is ongoing * magnetic field injection (Niigata Tanaka, Fujikawa, Yokozawa) * Effect of the air cooler magnetic field * AS, REFL table injection * He is writing the thesis |
|
Line 55: | Line 43: |
* Newtonian noise measurement * Thank you for Virgo PEM member! * Francesca mainly measured the newtonian noise * We will discuss in 21st. Jan.(Virgo KAGRA PEM meeting) * PEM measurement * Someday : Effect of the sound to DARM displacement * Someday : Environmental check around BS (including the POP) * Someday : Evaluation of the table cover * Someday : SR2 and SR3 optical lever (Reflection light from SRM?) |
|
Line 70: | Line 48: |
* IX. IY microphone * Instrument switch off |
|
Line 72: | Line 52: |
* Preparation for the hammering test @ Y-end [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=12497|klog]] * Sound reverberation study (KAGRA & Virgo) |
* Preparation for the hammering test @ Y-end [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/PEM/Meeting/200121/Minute|200121/Minute]] * Noise around 100Hz [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=12629|klog12629]] * Portable PEM with DataLogger [[https://github.com/gw-pem/kagra-pem/issues/201|GutHub201]] * PEM chassis [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11425|JGW-T2011425]] |
Line 76: | Line 58: |
* Offline detchar report for the part of the PEM | * Coupling with calibration line |
Line 79: | Line 61: |
* shaker injection with FPMI[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11117|speaker@12/8]],[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11128|shaker@12/15]] * Master thesis[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=10387|thesis]] |
* shaker injection with FPMI |
Line 82: | Line 64: |
* Lock loss study2 * fujimopy |
* Lock loss study |
Line 89: | Line 70: |
Weekly PEM meeting
- 2020/01/28(Tue) 16:00-(JST)
- Regular meeting meeting (Japanese)
Web meeting with Zoom2 (Zoom2)
Agenda
General issue
- Interferometer status
- Finally, we can lock the PRFPMI
- Transmittance laser power became 100 times higher than FPMI
- Lock duration is about 30min at maximum
- OMC commissioning is also ongoing
~100Hz noise and line noise of the higher frequency -> PEM
- Finally, we can lock the PRFPMI
- New PEMs
- We bought the ACO power supply, microphone and accelerometers(end of Feb.)
- Basically the portable PEMs
- PEM plan
- PEM injection
- Shaker injection (TTanaka, Yokozawa)
- Acoustic injection (TTanaka, Yokozawa)
PSL, REFL and AS table injection (Defence of TT Thesis -> tomorrow)
- magnetic field injection (Niigata TTanaka, Fujikawa, Yokozawa)
- Effect of the air cooler magnetic field
- AS, REFL table injection
- He is writing the thesis
- Hammering test
- Long term PEM evaluation
- Turning off the instruments
- Many microphone in the PSL room
- PEM injection
- Conference
地下宇宙若手研究会@茂住 (2/22-24)
- JPS (2020/3/16-19 @ Nagoya)
- Yokozawa, TTanaka
- KIW7
Each progress
- Yokozawa
- Planning toward the O3 run
- IX. IY microphone
- Instrument switch off
- Washimi
Preparation for the hammering test @ Y-end 200121/Minute
Noise around 100Hz klog12629
Portable PEM with DataLogger GutHub201
PEM chassis JGW-T2011425
- Kozakai
- Coupling with calibration line
- TTanaka(ICRR)
- shaker injection with FPMI
- Fujikawa
- Lock loss study
- TTanaka(Niigata)
- Magnetic field from air cooler and compressor
- Magnetic field injection to AS and REFL table
- etc