Minute of PEM meeting
- Date: 2020/10/02 17:10-18:00(JST)
- Attendance: Yokozawa, Fujikawa, Washimi, Yokoyama, Kozakai, Ohkawa, Kume, Uchiyama, Miyoki, Oshino
- Regular meeting
Minutes
Interferometer schedule JGW12041
- - 12th Oct. RSE lock trial
- 5th Oct. - 19th Oct. Start the cleaning
- 15th Oct. - 21st Oct. Warming up cryogenic ducts(IX, IY, EY)
- 14th Oct. blackout (13th, 15th working date for blackout)
- 19th Oct. - 23rd Oct. Clean work by company
- 22nd Oct. - 25th Oct. break vacuum
- 26th Oct. - Open chambers
- Call for discussion
- PEM measurement during blackout
- Prepare the DAQ during blackout
- Seismometer + magnetometer + Infrasound microphone + GND
- ポンプと乾燥空気を送る装置は動いている
- 人が近くを通るときの時間把握
- PEM DAQ racks
- Use only IX and IY racks
- Move the position of IX and IY racks
- New PEMs toward O4
- Many microphone
- Not only tables but also booth
- Position of magnetometer
- Position of seismometer
- Additional PEMs to PSL room
- 120Hz noise
- glitch study
- Many microphone
- Lock loss study
- control loop of the ETMX MNR?
- If you have new idea or discussion item, please write here
- PEM measurement during blackout
- Fujikawa will visit Kamioka from 4th Oct. to 17th Oct.
- ICA analysis
- コードを直している
- Next PEM meeting 17:00- 2nd Oct.