Weekly PEM meeting
- 2020/12/11(Fri) 17:30-
- Regular meeting
Zoom2 : https://zoom.us/j/6676627462
After this meeting
- 12/11 Regular meeting
- After this meeting, we will have a practice of KIW7 by Fujikawa-san
- 12/18 18:00 - 19:00 VK PEM meeting (After KIW7)
- 12/22 10:00 - 12:00 Newtonian noise meeting (Prelininary)
Agenda
Conference issue
- The 7th KAGRA International Workshop (National Central U., Taiwan), Dec. 18-20, 2020 (F2F meeting on Dec. 17-18)
- For students, oral presentation at KIW7 and poster presentation at F2F meeting
- Presentation
Yokozawa (KIW:Plenary session PEM)
Washimi (KIW:Acoustic inj+sound reverberation time+NN)
Kume (KIW:ICA analysis)
- Fujikawa (KIW+F2F:Lock loss study for thesis)
- If you have some presentation about PEM related, please contact to me.
General issue
Interferometer schedule JGW12041
- VIS upgrade
- IMM upgrade
- IYC experience
- Temperature control
- AC noise at Xend
- Please contact us if you will work inside the chamber(take pictures)
- Author list for O3b was opened
- Contribution to PEM for joining the author list
- KAGRA Environmental study (Including (future) newtonian noise measurement)
- Noise evaluation using PEMs (Including lock loss study)
- Setting monitors (Cabling, making monitor, ondotory maintenance)
- Others
Discussion item
- Start the investigation for measurement of the newtonian noise
- Seismic NN
- Requested to publish (at least 1 year) seismometer data summary from many directions
- Fractal analysis
- Timeline for Francesca analysis
- Many seismometers
- Accelerometers for wall
- Water fluid NN
- Fluid meter
- Simulation
- Atomospheric NN
- Relative temperature monitor
- Infrasound
- Gravity monitor
- TOBA
- Superconducting Gravimeter
- Seismic NN
- We will have a NN meeting in the final week of this December.
Jurnal paper issue
PTEP (2) : noise budget(K.Yamamoto) Check list, slack <<Analysis is ongoing>>
Results of the environmental noise in the PTEP02 JGWDoc12129
PTEP (3) : CAL, DET, PEM, GIF (Yokozawa) <<Submitted>>
Acoustic injection paper (Washimi) <<2nd DRAFT CIRCULATION>> JGW-P2012122-v1
- posted to CPC (12/7), circulated on 12/9 [kagra 03888]
- No comments yet
Seismic NN paper (with Virgo) <<DRAFT CIRCULATION>>
- Playground data application is necessary
Fractal paper (with Virgo) <<DRAFT CIRCULATION>>
- Playground data application is necessary (Yokozawa)
ICA for E-run/O3GK (Kume, Yokoyama) <<Analysis ON GOING>>
Portable PEMs (Yokozawa+) <<Start writing>>
Virgo O3 break paper <<PUBLISHED>>
Preparation for O4
- PEM table
- k1ctr plan
- DELL PC
- Cabling issue
- Cleaning the center area
- PEM cabling plan
- New cable rack
- Noise mitigation / Environment stability
- GND issue
- Temperature control
- PEM sensors
- Re-install the ACCs, MICs, MAGs until commissioning start
- water fluid monitor
- read out of the lightning sensor
- Infrasound monitor @ Atotsu, Mozumi, tunnel (+ Toyama?)
- PEM injection
- Acoustic injection at X/Y-end
- Magnetic injection
- After O4
- RF monitor
- Tiltmeter
- RI detector
- Newtonian noise
Progress report
- Yokozawa
- Rack ground GND
- Washimi
Water fluid JGW-G2012311
- Kume
- ICA analysis related with PEM