Line 33: | Line 33: |
* IX LVDT ACC installation * Bp's finalize |
* IX Suspension commissioning * Green laser recovery(PLL) * IMM suspension check |
Line 36: | Line 37: |
* Optics characterization * IMC characterization * ASC * PMC calibration |
* IMC ASC * Initial alignment->beam reached to PR2 * IMC, PMC calibration |
Line 50: | Line 50: |
Line 57: | Line 56: |
* Lightening paper (Washimi) '''<<1st refree comments : finished>>''' [[https://arxiv.org/abs/2103.06516|arXiv:2103.06516 ]] * Fractal paper (Alessandro) '''<<Submitted to Journal>>''' [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=12438|JGW-P2112438]], [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/PEM/Meeting/Seminar/210128|seminor slide]] |
* Fractal paper (Alessandro) '''<<Reply to referee comment>>''' [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=12438|JGW-P2112438]], [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/PEM/Meeting/Seminar/210128|seminor slide]] |
Line 72: | Line 69: |
* Electric box position (Done) * BS-IYC cable rack (Done) * New cable diagram (Done) * Cleaning around IY rack cables(Done) * MCF rack ready (Mostly done) * Cabling around MCF (Done) * Set electric boxes * D-sub cablings |
* Already done * Electric box position * BS-IYC cable rack * New cable diagram * Cleaning around IY rack cables * MCF rack ready * Cabling around MCF * Progress * Set electric boxes(POP, BS, POS done)(OMC not yet) * D-sub cablings IY(POP, BS, POS done)(OMC not yet)(15pin not yet) * Future |
Line 81: | Line 81: |
* Booth MIC setting | * Booth MIC setting(IMC, REFL done) |
Line 91: | Line 91: |
* Before closing the IMC chambers, IMC vacuum tables | * PR2 pylon * Oplev issue |
Line 95: | Line 96: |
* Low frequency sound injector | |
Line 119: | Line 121: |
* Instrumental noise of sensor measure * PMC noise budget [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=12937|slide]] |
* Microphone analysis |
Line 123: | Line 124: |
* Kobayashi-san future plan | |
Line 126: | Line 128: |
* Lightening analysis | * ACO power, microphone test : |
Line 128: | Line 130: |
* Water fluid monitor : No report | * Water fluid monitor : |
Line 131: | Line 133: |
* Cabling plan * Infrasound microphone |
* Seismic motion IMC |
Weekly PEM meeting
- 2021/06/04(Fri) 17:00-
- Regular meeting
Zoom2 : https://zoom.us/j/6676627462
Conference issue
- Future conferences
JPS meeting url
- Remote style
- Deadline 6/3
- Yuzurihara(ICRR), Kobayashi(OCU)
- 8th KIW (online), KASI, Daejeon, Korea, July 7-9, 2021
- Remote style
Poster abstract submission -> Extend to 15th June
- If you have a plan of presentation, please let me know.
- 27th KAGRA Face-to-face meeting
- Remote style
Other meetings url
- GWPAW Hannover, Germany, Dec 14th-17th, 2021
If you have some presentation about PEM related, please contact to me.
General issue
- Interferometer schedule
- VIS upgrade (ongoing)
- EYC dirty check
- IX Suspension commissioning
- Green laser recovery(PLL)
- IMM suspension check
- IO commissioning
- IMC ASC
Initial alignment->beam reached to PR2
- IMC, PMC calibration
- Noise budget by PEMs
- Sound check
- VIS upgrade (ongoing)
- Schedule
- PEM schedule
- Re-installation of PEMs toward O4
Jurnal paper issue
PTEP (2) : noise budget(K.Yamamoto, Kokeyama, Washimi) Check list, slack <<Writing>>
- NB plot has been finalised
- PWT is writing the draft for each part
Fractal paper (Alessandro) <<Reply to referee comment>> JGW-P2112438, seminor slide
Newtonian noise paper (Francesca) <<Submitted>>
Reverberation time paper (Washimi+) <<Start writing>>
ICA for E-run/O3GK (Kume, Yokoyama) <<Analysis ON GOING>>
Portable PEMs (Yokozawa+) <<Start writing>>
Preparation for O4
- PEM cabling plan
- Already done
- Electric box position
- BS-IYC cable rack
- New cable diagram
- Cleaning around IY rack cables
- MCF rack ready
- Cabling around MCF
- Progress
- Set electric boxes(POP, BS, POS done)(OMC not yet)
- D-sub cablings IY(POP, BS, POS done)(OMC not yet)(15pin not yet)
- Future
- BNC cabling
- Booth MIC setting(IMC, REFL done)
- Set calibration factor
- Already done
- PEM sensors
- Re-install the ACCs, MICs, MAGs before commissioning start
- water fluid monitor
Magnetometers for Schumann resonance MFS-06e
- Develop the satellite box
- Vibration projection
- PR2 pylon
- Oplev issue
- Discussion with CAL team about A chamber
- PEM injection
- Low frequency sound injector
- Acoustic injection at X/Y-end
- Magnetic injection
- After O4
- RF monitor
- Tiltmeter
- RI detector
- Newtonian noise
- Discussion with DET members
- Daily summary page PEM
- Line identification
- Yokozawa
VIS -> IOO -> MIF
Progress report
- Pil-Jong
- Discussion of O3GK DET
- Suzuki
- Water simulation
- Yuzurihara
- Microphone analysis
- Investigation of ICA analysis
- Kobayashi-san future plan
- Progress
- Washimi
- ACO power, microphone test :
- Infrasound sensor test :
- Water fluid monitor :
- Yokozawa
- Seismic motion IMC
- Seismic motion analysis
- O3GK
- Microseismic
- Long term