⇤ ← Revision 1 as of 2023-06-23 06:51:39
Size: 4211
Comment:
|
Size: 4853
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 2: | Line 2: |
* 2023/06/16(Fri) 17:00- | * 2023/06/23(Fri) 17:00- |
Line 8: | Line 8: |
* O4a run started from 24th May | * O4a run finished successfully |
Line 10: | Line 10: |
* CAL/DET week now | |
Line 52: | Line 53: |
* Situation didn't change from last week * Depending on the PR3 alignment |
* Summary [[https://gwdet.icrr.u-tokyo.ac.jp/~controls/misc/html/|url]] * CAL/DET week * Calibration measurement done : No significant change from previous measurement * Some additional measurement toward O4b Saturday * Noise budget measurement * Interferometer (MICH, PRCL, ISS, CARM, ...) * Suspensions * PEMs * etc. |
Line 56: | Line 66: |
* The rate became smaller after change the process of the detchar script * Currently, appeared again |
* The rate didn't change * Need to investigate the reason |
Line 61: | Line 71: |
* Summary page update for O4a * [[https://gwdet.icrr.u-tokyo.ac.jp/~controls/summary/|url]] |
|
Line 75: | Line 82: |
* Set the geophone inside the chamber and evaluate the vibration | |
Line 93: | Line 101: |
* Accepted | * Published * TCam paper * Writing ongoing |
Line 99: | Line 110: |
* It may appeared in DARM sensitivity (SR3?) | |
Line 101: | Line 113: |
* Ongoing | |
Line 102: | Line 115: |
* Start the O4a observation * Fixed the PRMs * PEM working check [[https://klog.icrr.u-tokyo.ac.jp/osl/?r=25527|klog25527]] |
* Acoustic injection post O4a * OMC * Portable PEM reinstallation [[https://klog.icrr.u-tokyo.ac.jp/osl/?r=25673|klog25673]] * PSL room * Next week? * TMSX/TMSY * Prepared today * SR3 * If we have a time * other area? * Any idea? |
Line 140: | Line 161: |
* Applying the deepclean | |
Line 143: | Line 165: |
* PR3 line injection [[https://klog.icrr.u-tokyo.ac.jp/osl/?r=25670|klog25670]] | |
Line 150: | Line 173: |
* Noise O4a | * Overlap reduction function for Schumann resonance |
Line 153: | Line 176: |
* PEM check during O4a | |
Line 155: | Line 177: |
* Preparing for the acoustic injection in both end |
Weekly PEM meeting
- 2023/06/23(Fri) 17:00-
- Regular meeting
Zoom2 : https://zoom.us/j/6676627462
General announcement
- O4a run finished successfully
- 4 weeks run it will finish 21st June 8:00(JST)
- CAL/DET week now
- KAGRA visiting plan
- If you want to visit Kamioka, please contact to Yokozawa
- Kiban S application
- 高精度レーザーひずみ計観測網の広域展開による地殻活動の時空間マルチスケール観測
- Yokozawa and Washimi would be co-investigator, about KAGRA environment and strain-mater
Meeting and Conference issue
ICRC 2023 url
- Nagoya
- Yokozawa will present about KAGRA PEM (oral)
- Washimi will present about Schumann resonance and SGWB
- LVK meeting at Toyama
- 11-14 September 2023
- F2F meeting during this meeting(?)
- JPS meeting (Tohoku U)
- 16-19 September 2023
- Presentation about PEM
- Yokozawa (Status)
- Washimi (Noise hunting)
- Hoshino (Seismic forecast)
Other meetings url
If you have some presentation about PEM related, please contact to me.
Business travel
- Depending on the situation of COVID-19
- To Kamioka
- Hoshino(planned)
- From Kamioka
- No
General issue
- Status
Sensitivity 1.1~1.4 Mpc latest
Summary url
- CAL/DET week
- Calibration measurement done : No significant change from previous measurement
- Some additional measurement toward O4b Saturday
- Noise budget measurement
- Interferometer (MICH, PRCL, ISS, CARM, ...)
- Suspensions
- PEMs
- etc.
- IPC glitch
- The rate didn't change
- Need to investigate the reason
- Lock loss investigation
- Ongoing
- Schedule after O4a
- CAL/DET week (1 week)
- Calibration measurement
- Remaining measurement for O4a
- Switch to high power laser (1-2 week)
- Check the sensitivity
- Turned off and on the cryocooler (1 week)
- Same timing with switch high power laser
- IX, IY, EY. Not perform EX
- Open the OMC chamber (1 week)
- Set the geophone inside the chamber and evaluate the vibration
- Treatment the ghost beam
- Commissioning toward 10 Mpc
- CAL/DET week (1 week)
出張PEM injection (planning form)
Jurnal paper issue
- Micro seismic analysis (Hoshino)
- Submit to CQG soon
- Acoustic reverberation time paper (Washimi+)
- Suspend
- Re-measurement before O4?
- Tonga GIF paper
- Published
- TCam paper
- Writing ongoing
Preparation for O4
- Check the seismic motion around mozumi area
- Daytime ground motion
- It may appeared in DARM sensitivity (SR3?)
- Schumann resonance measurement
- Ongoing
- Acoustic injection post O4a
- OMC
Portable PEM reinstallation klog25673
- PSL room
- Next week?
- TMSX/TMSY
- Prepared today
- SR3
- If we have a time
- other area?
- Any idea?
- OMC
- Investigation of the PEM injection
- Magnetic injection
- After O4a?
- Magnetic injection
- Voltmeter preparation
- AC power monitor installation
- DC power monitor installation
- After O4
- RF monitor with mokugo
- Tiltmeter
- RI detector
- Newtonian noise
- Discussion with DET members
- Daily summary page PEM
Progress report
- Yuzurihara
- Pastavi
Data Quality Report slide
- Data quality evaluation
- Hoshino
- Seismic motion analysis
- Sato
- Sound source analysid
- Miyamoto
- Weather analysis
- Takatani
- Applying the deepclean
- Calculation of Schumann resonance
- Kume
PR3 line injection klog25670
- Noise subtraction
- Nishizawa
- Water newtonian noise
- Magnetic field analysis
- Washimi
- Overlap reduction function for Schumann resonance
- Yokozawa
- Lock loss study O4a
- Preparing for the acoustic injection in both end