Weekly PEM meeting
- 2024/04/26(Fri) 18:00-
 - Regular meeting
 Zoom2 : https://zoom.us/j/6676627462
General announcement
- 2024年度もよろしくお願いします。
 - もうしばらくはKAGRA recovery meetingが伸びる可能性がありますので18:00-開催に変更していただく可能性があります。
 - 祝日ですが、5/6にVirgo memberとVK PEM meeting開催予定です。またご連絡いたします。
 - SEO PEM budget 2024 
- 285 man yen
 
 - Several Virgo ENV member have some plan to visit KAGRA about 1 month 
- One month Aug. - Dec.
 - They are also thinking about visiting LIGO
 - KAGRA would still be commissioning phase
 - Plan  
- Noise hunting (PEM injection)
 - Magnetic injection
 - Additional NN measurement
 - Other
 
 
 - Authorlist 2024 
- If you have an opinion, please let us know.
 
 - O4b 
- ER16 20th Mar.
 - O4b 10th Apr.
 
 - O4a noise budget paper 
- If you have a plan to write the paper using O4a data and PEM, please let me know.
 
 
Meeting and Conference issue
- Please reserve the hotel in Hokkaido if you plan to join the Autumn JPS meeting next time
 - KIW11 
- Taiwan (2024/04/16-20)
 - Yokozawa : Exploring the Mesoscale Meteorology on the KAGRA Gravitational Wave Detector
 - Washimi : Earthquake Effects on KAGRA
 - 4/19 afternoon meeting with deepclean member
 
 - GWADW  
- Australia (2024/05/12-18)
 
 - GWPAW 
- England (2024/05/27-31)
 
 Other meetings url
If you have some presentation about PEM related, please contact to me.
Business travel
- To Kamioka 
- None
 
 - From Kamioka 
- None
 
 
General issue
- Interferometer recovery 
- IMC Recovery : Done (Similar situation around O4a)
 - Plan to have a hammering test toward future blasting
 - Type-Bp 
- First contac trial
 
 - Type-A 
- IX : One leak found and re-pumping down ongoing
 - EX : Pumping down ongoing
 - IY : Started the pumping down
 - EY : Need more investigation aboud liquid at EYA and photo sensor at EYC
 
 - OMC vibration 
- Need to treat something for stacks of OMC chamber
 - Discussed in the recovery meeting
 
 - IR/GR alignment recovery : Ongoing
 
 
出張PEM injection (planning form)
Jurnal paper issue
- Micro seismic analysis (Hoshino) 
- Submit to PTEP
 
 - Acoustic reverberation time paper (Washimi+, Sato?)  
- Suspend
 - Re-measurement before O4?
 
 
Preparation for O4b
- [Important] Strategy for reducing the effect of the acoustic noise 
- Discuss in Yokozawa part
 
 - PEM installation 
- Waiting the timing of TMSX and TMSY
 
 - Evaluation of newtonian noise 
- Anoop and Washimi
 
 - Investigation of the PEM injection 
- Magnetic injection
 
 - Voltmeter preparation 
- AC power monitor installation
 - DC power monitor installation
 
 
Progress report
- Yuzurihara 
- Pastavi
 Data Quality Report slide
- Data quality evaluation
 
 - Sato 
- Sound source analysis
 
 - Kume 
PR3 line injection klog25670
- Noise subtraction
 
 - Nishizawa 
- Water newtonian noise
 - Magnetic field analysis
 
 - Washimi  
- OMC vibration test
 
 - Yokozawa  
- Strategy for reducing the acoustic noise
 
 
