iKAGRA ETM suspension preparation log

Schedule

Disassembling at ATC Mitaka [Ohishi] (12th-19th Jan.)

Washing and transportation to Kamioka [Hirata-san]

New parts

Pico-motors and PZTs

Coil driver

Cables

Assembling [Tomaru-san, Ohishi, Yamamoto-san]

Hanging

Transfer Function Measurement

==== Transportation to the End [Prof. Kimura, Sawada-san, Tomaru-san(KEK),]====

Mirrors

Stages

Installation