Things to remember/fix | Things to remember/fix after BS Test Hang, before final hanging of BS. * Remove cling wrap in BF and install vacuum-compatible heat shrink. * Remove cling wrap in PI and install vacuum-compatible heat shrink (needs wider diameter). * Swap out temporary ballast mass in BF. * If possible, fix galled pole in BF level of EQ stop. * Swap in new F0-SF maraging rod (with 8-mm heads) and new receptacles to match. |
KAGRA VIS - Type B - BS Test Hang Issues
Things to remember/fix after BS Test Hang, before final hanging of BS.
- Remove cling wrap in BF and install vacuum-compatible heat shrink.
- Remove cling wrap in PI and install vacuum-compatible heat shrink (needs wider diameter).
- Swap out temporary ballast mass in BF.
- If possible, fix galled pole in BF level of EQ stop.
- Swap in new F0-SF maraging rod (with 8-mm heads) and new receptacles to match.