- Activity report for weeks of 12/26 and 1/2
- Hirata-san:
- Modified parts list and screw list for payload.
- Sent lists to i-ject and asked for preliminary quotes.
- Made drawings for some jigs (PR hold-down jig) and some parts for payload (PR/SR wire clamps with disposable jaw pieces - improved version with disposable pieces in both primary and secondary clamps).
- For Type Bp:
- Searched for PR gluing jigs.
- Washed and assembled recoilmass base for mirror hanging jigs, and sent them to Kamioka.
- Washed additional masses for IM and sent them to Kamioka.
- For others:
- Washed IMMT plate and sent them to Kamioka.
- Fabian
- Designed a pull down system to fix the PR IM to the EQ stop (similar to the SR one).
- Worked on design of the SR assembly frame. As hoped, the SR version can be almost identical to the BS version.
- Worked on design of additional trim mass (≈18 kg) for the BS BF.
- Checked assembly PR/SR drawings. There were a few corrections/changes.
- Checked fastener list. There were few corrections/changes.
- Checked component list for the manufacture order. There were few corrections/changes.
- Helped in searching for the PR gluing jigs.
- Mark
- Started design of SR assembly frame (but then passed it to Fabian).
- Worked on task lists and schedule.
- Hirata-san:
- Plan for 1/10-13
- Mark and Fabian at Kamioka:
- Finish rebalance of IM
- Reinstall IRM, adjust OSEMs
- Replace broken Type 3 cable.
- Do TFs from IRM OSEMs to IRM and IM OSEMs.
- Cable up and test BF LVDT and fishing rod (time permitting).
- Disconnect BF and ship back to Mitaka (time permitting).
- Hirata-san:
- More SR procurement.
- Mark and Fabian at Kamioka: