VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
Coming Weeks
2018-06-18
Main Sequence
- Tweak BF total trim masses.
- SF/... TFs.
- Add budgeted ballast mass to SF (or remove stuff!).
- Cable, test SF FR.
- Grab and configure a picomotor driver as SR2_BF 10.68.150.25.
- Check JGWDoc electronic item lists are up to date.
F0/LBB Stuff
- Finish tuning F0 in PI #3.
- Replace ceramic thrust bearing in PI #3 with metal one (do PI #1 as well if time).
- Characterize more blades?
- Park PI #1 in SR3 AF.
- Crane PI #3 behind SR3.
- Crane PI #1 to factory area.
Software
- Review/improve macro file fixes for split models; write klog; submit changes to SVN.
Install AC bandpass filters in SR3 WD filters.
- Check coil filter gains for compensation of magnet polarities (confirm SR3 IM, set and confirm SR2 and SR3 TM).
- Create software stepper drivers for SR3 and SRM and link to from STEP_MASTER.adl screen.
- Fix link to SUS_CUS_BSFM_BIO.adl in VIS_CUST_TYPEB_OVERALL.adl.
- Rename VIS_CUST_BS_BIO.adl screen to VIS_CUST_TYPEB_BIO.adl and adjust links.
- Fix hardwiring to BS in VIS_CUST_TYPEB_IP_WD_AC_BANDLIM.adl (ACC H2 and ACC H3 sections).
2018-06-25
Main Sequence
F0/LBB Stuff
- Build/tune F0 in PI #1.
- Finish tuning PI #3.
- Wrap PI #1.
- Crane PI #1 to SR2 AF.
- Crane PI #3 into SR3 AF.
Software/Remote
2018-07-02
Main Sequence
F0/LBB Stuff
2018-07-09
Main Sequence
F0/LBB Stuff
2018-07-16
Main Sequence
F0/LBB Stuff
2018-07-23
Main Sequence
F0/LBB Stuff
SR Prep Tasks - To Be Scheduled
Tunnel
- Get independent power supply for SR3 so SR2 can be powered back up.
- Remove SR3 tank lid, crane LBB rings to top of lower half of the tank, clamp in position.
- Check SR2, SR3 TM coil gains for magnet polarity compensation.
- Calibrate last six IM OSEMs.
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- Rebuild filter in PI #1.
- Install clamps on PI #1.
- Install geophone plates on PI #3.
- Install geophone plates on PI #1.
- Install correct IP in PI #2.
- Rebuild filter in PI #2.
- Install clamps on PI #2.
- Install LBB blade units on PI #2.
- Install geophone plates on PI #2.
Mitaka or remotely
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Review Shoda-san's Guardian.
- Review DIO stuff.
- Review DAC channel requests.
- Set up SR2 and SR3 Guardian.
- Create Python drivers for SR3_IM and SR3_BF picos and link to them from Mio-kun's PICO_MASTER.adl MEDM screen.
- Install damping filters for SR2.
- Do buoyancy calculation (see LIGO-T1100616).
- Split SRx real-time models?
Ordering
See ../WishList .