2015/12/4 13:30 - | 2015/12/4 13:30 - |
Line 6: | Line 6: |
Participants: | Participants: |
Line 8: | Line 8: |
== Schedule == |
== Schedule == |
Line 11: | Line 10: |
* Latest schedule chart | * [[attachment:05_VIS-20151203.pdf|Latest schedule chart]] |
Line 24: | Line 23: |
* BF load check at the ATC | * BF load check at the ATC |
Line 33: | Line 32: |
* Clean work procedure | * Clean work procedure |
Line 49: | Line 48: |
* Transportation schedule | * Transportation schedule |
Line 58: | Line 57: |
Line 83: | Line 82: |
* Next week (from 12/7) plan | * Next week (from 12/7) plan |
Line 85: | Line 84: |
* Mon: * Tue: |
* Mon: * Tue: |
Line 88: | Line 87: |
* Thu: * Fri: |
* Thu: * Fri: |
Line 91: | Line 90: |
* PR2 * Mon: * Tue: * Wed: * Thu: * Fri: |
* PR2 * Mon: * Tue: * Wed: * Thu: * Fri: |
Line 99: | Line 98: |
* Takahashi: * Shoda: * Mark: * Fabian: |
* Takahashi: * Shoda: * Mark: * Fabian: |
Line 104: | Line 103: |
* Fujii: | * Fujii: |
Line 106: | Line 105: |
* Hirata: | * Hirata: |
Line 111: | Line 110: |
* Shoda: * Mark: * Fabian: * Okutomi: * Fujii: |
* Shoda: * Mark: * Fabian: * Okutomi: * Fujii: |
Line 118: | Line 117: |
* Ohishi: |
* Ohishi: |
Line 121: | Line 120: |
Line 124: | Line 122: |
Line 140: | Line 138: |
Line 146: | Line 143: |
Line 150: | Line 146: |
* Waiting for shipping information: | * Waiting for shipping information: |
Line 158: | Line 154: |
2015/12/11 (Fri) 13:30 - | 2015/12/11 (Fri) 13:30 - |
VIS Meeting on 2015/12/4
2015/12/4 13:30 -
Room 210 + SeeVogh(?)
Participants:
Schedule
- Schedule status (Aso)
PR
- Test Hanging Status (Takahashi)
- LVDT driver
- Picomotor connection
- Fishing rod motor
- PR2 preparation (Mark, Fabian)
A cable clamp to be attached to the suspension rod has a wrong size collet. Fabian will bring the proper collets from Mitaka. -> status ?
- Payload weight issue
- BF load check at the ATC
- Digital system (Okutomi, Fujii)
- Traverser actuation check (Shoda)
- Traverser stop mechanism (Shoda)
- Procurement status (Takahashi)
- Clean work procedure
- Particle count record (Shoda)
- Where to put the floor coach filters for PR2 and PR3 work
- PR CAD model and assembly drawings (Hirata)
- Need to give the rotation angle of the traverser top plate (Aso)
- Cable status (Takahashi)
Made a cable list -> Put a link to the excel file on Wiki. Takahashi will improve the table. -> Status
- Call for shift for cable checking (Takahashi)
- Call for shift for assembly help (Takahashi)
- PR2 gluing schedule (Tatsumi)
- Discussion with Hirose-san (Aso)
- Transportation schedule
- Bring PR3 also ?
- Bring the original containers of PR3 and the spare mirror ?
- Production of additional PR winches (Akutsu)
- RM compensation mass
- Design status (Fabian): Will finish it after the ELITES meeting by the end of the next week.
- Order status (Takahashi): Placed an order. Will check the delivery date.
- RM EQ stop screw position (Takahashi)
Out sourcing: Need to send the plates to the company -> Status
- PR Optical Bench (Akutsu)
- When to install
PR2/3 OpLev (Akutsu)
- OSEM assembly status (Akutsu)
- Rails for the hanging frame (Hirata)
Hirata will finish exchanging the balls and send them to Kamioka by the end of the next week -> status
- Screws for fixing the rails ?
- Test hanging vacuum installation
- Do we have everything necessary ?
- Cleaness check by Hirose-san
- What needs to be done when the suspension is inside the chamber ?
- Transfer function measurement
Do we need OpLev ?
- Check the orientation of the mirror ?
- Peel off the first contact
- Suspension cleaning practice ?
- Transfer function measurement
- Next week (from 12/7) plan
- Test hanging
- Mon:
- Tue:
- Wed:
- Thu:
- Fri:
- PR2
- Mon:
- Tue:
- Wed:
- Thu:
- Fri:
- Test hanging
- Travel (Week of 12/7)
- Takahashi:
- Shoda:
- Mark:
- Fabian:
- Okutomi:
- Fujii:
- Ishizaki:
- Hirata:
- Ohishi:
- Travel (Week of 12/14)
- Takahashi:
- Shoda:
- Mark:
- Fabian:
- Okutomi:
- Fujii:
- Ishizaki:
- Hirata:
- Ohishi:
BS
- What to do with BS after iKAGRA (Aso)
- We need to decide on the plan by the end of Dec.
- BS Assembly Frame Design (Aso, Hirata)
- BS flag design (Mark, Fabian)
- BS gluing jigs (Tatsumi)
- Not enough crane height problem (Hirata, Saito)
- IP base clamp (Fabian)
- Bread board spring (Takahashi)
- BS clean bag (Aso)
ETM
- ETM installation procedure (Aso)
- Sent the final version drawings to Mirapro
- Waiting for quotation
Other
- Watch dog system (Tanaka)
- GAS blade inspection by Virgo (Takahashi)
- Waiting for shipping information:
- Request to the ATC for the next year
Production of the blades of the Type-A BF: We should check the consistency of the optimal load at the TAMA prototype experiment and G&M measurements (SF and TF) (Takahashi) -> Status
- Safety at the site (Takahashi, Ishizaki)
Next meeting
2015/12/11 (Fri) 13:30 -