VIS Meeting on 2016/2/5

2015/2/5 13:00 -

Kamioka TV conference room + SeeVogh

Participants:

Schedule

  • Schedule status (Aso)

PR3

  • PR3 Installation Status (Takahashi)
    • #Traverser repair: Repair of the broken ones at Mitaka -> Uraguchi-san is working on it.

    • #Screws to fix the front and back rings the RM were too long, or the tapping in the holes were too short. Couldn't use M5x40. Ordered M5x35 with vent holes. -> Delivered. Remember to replace them

  • PR3 flag and 2nd wire breaker repair status (Tatsumi)
  • #The frame for the clean bag is bent. Aso will contact Mirapro for a stronger frame.

Plan for the next week

  • Mon:
  • Tue:
  • Wed:
  • Thu:
  • Fri:

iKAGRA ETM suspension

  • Assembly of the suspension (Ohishi)
    • Missing parts (Tatsumi, Takahashi)
      • Plates to fix the connectors on the suspension frame were ordered. -> Expected delivery date Feb. 4th.

      • Coil bobin: Delivery date-> Feb. 4th.

      • Insulation tubes for picomotor connectors
  • PRM transportation (Tatsumi)
  • Coil winding (Takahashi)
    • Will be done by Ando-lab students from 2/8
    • Winding machine test status ? (Takahashi)

Plan for the next week

  • 2/8-2/12: TF measurements
  • 2/12: Packing

Travel Plans

  • Travel (Week of 2/8)
    • Takahashi: Mon-Wed
    • Shoda:Mon-Fri

    • Mark:
    • Fabian:
    • Okutomi:Mon-Fri

    • Fujii:Mon-Fri

    • Ishizaki:
    • Hirata:
    • Ohishi:
  • Travel (Week of 2/15)
    • Takahashi:
    • Shoda:
    • Mark:
    • Fabian:
    • Okutomi:
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Ohishi:

Other Mechanical Issues

  • Wire winches
    • Shipped to Mitaka. We need a coordination with Ikenoue-san for this work (Takahashi)

  • Clean work procedure
    • Will be discussed in F2F.
  • #BF Optimal Weight (Takahashi)
    • #Balast masses: Delivered to Mitaka. Will send them to Kamioka (Hirata)
  • #IM wire clamps
    • #Need to send the wire clamps used for the test hanging to I-ject: it was sent to I-ject (Takahashi)
  • #Traverser actuation check (Shoda)
  • #PR CAD model and assembly drawings (Hirata)
    • Aso calculated the rotation angle
      • PR3: 0.786deg counter clockwise from the line connecting the centers of the PR3 and BS chambers.
      • Will make a report soon.
  • #Wire cleaning (Hirata)
    • Hirata will order 20m more wires. -> Delivered. Will wipe in the next week. -> Finished. Will send to Kamioka soon.

    • Will wash Tungsten wire delivery status -> Delivered. Will wipe in the next week -> Finished. Will send to Kamioka soon.

  • #Production of additional PR winches (Akutsu)
    • Shipping status (Takahashi, Hirata) -> Wrapped. Will be shipped with IP in the next week.

  • #OSEM assembly status (Akutsu)
  • #List of what should be changed for PR3 hanging
  • #Missing items(to be purchased soon)
    • #Traverser motor driver (Shoda) -> Will discuss Uraguchi-san. Need a box for stepping motor driver. -> These are for PR2. Will be ordered sometime.

Electronics

  • What are necessary in the next few weeks ?
    • Nothing
  • Electronics diagram and review
    • Had a review on PR3 on Thursday
    • We still need an overview diagram
  • Watch dog system (Tanaka)
    • Status ?
  • #LVDT distributor connector problem
    • Miyakawa-san circulated a design of the conversion cable (D9-D15): drawing

  • #Digital System (Okutomi, Fujii)
  • #Cable status (Takahashi)
    • Need to send more PTFE cable to finish the remaining two -> Will do it in the next week

    • Need to send the cables used for the test hanging once it is finished. -> Will send them once the test hanging is disassembled.

  • #Cable check
    • Liu-kun Zhao-kun finished checking all the cables. They found another broken cable.
    • Will send the broken cables together with the other cable related items (Takahashi).

bKAGRA preparation

  • Three big categories of the tasks
    • Type-A: Leader = Takahashi: Task list, team members
    • Type-B (BS and SRC): Leader = Mark: Task list, team members
    • Type-Bp modification: Continue discussion (Aso, Raffaele)

Common Issues

BS and SR

  • Task listKAGRA/Subgroups/VIS/TypeB/TaskList

    • Kick off meeting within February (Mark)
  • BS prism preparation
    • Contacted the company LIGO used for the possibility of buying sapphire prisms (Mark)
    • They are happy to take an order. No Japanese agent. But international order can be taken.
    • Will ask for the lead time to the company (Mark) Drawing to be sent (LIGO drawing) -> Send the drawing to the companies immediately

  • Can we make SR wire breakers bigger ?
    • Asked Fuskushima-san about the possibility of widening the slits (Takahashi) -> It is possible but there is a risk of slight deformation.

    • We will try to widen the slit using the dirty RM used for the test hanging.
    • We need to decide on how much to widen. Check what happens if we use 5mm tall prism on CAD (Hirata) -> Result

      • Make the slit wider by 3mm will interfere with a M5 threaded hole
        • The hole is needed to keep the mechanical rigidity
        • Can make a new M5 hole somewhere near by ?
      • Check what happens if we widen the slit by 3.75mm and make a new M5 (Hirata) -> Result

        • Then we will talk to Fukushima-san again
      • If the design of the SR prisms can be the same as BS, it will be a good idea to order them at once.
        • Check if the BS prism can be used(Mark)
  • Flag design (Mark)

    • Mark will sort out the ideas and organize a specialized meeting.
  • IP base clamp (Fabian): Picture -> Reduce the number of clamps

  • Bread board spring (Takahashi): Slides

  • New accelerometer for IP (Joris)
    • Will give a talk at an NAOJ seminar in March
  • #BS Assembly Frame Design (Aso, Hirata)
  • #BS gluing jigs (Tatsumi)
  • #Not enough crane height problem (Hirata, Saito)
  • #BS clean bag (Aso)

Type A

  • Task list (Takahashi): Present at the next VIS meeting.
  • Fishing rod production status (Takahashi)
    • Ordered the material for the blades.
    • Stepping motors were ordered.
    • Mechanical parts remaining to be ordered (have drawings already)
  • #Type-A Filters Optimal Load Measurements
    • #Takahashi will make a plan for the optimal load check and ask ATC.-> Check two filters per month from April 2016. -> Will be presented to the ATC steering committee.

    • #How to manufacture the long maraging wires ?
      • One prototype was machined by Ojima
      • Aoshima can do the heat treatment for the long rod. Will ask them soon (Takahashi) -> Still waiting for a quotation.

      • How to test it ?
        • We can use the prototype assembly frame in TAMA.

#Type-Bp modification

  • #PR2 Wire breaker problem
    • Prism removal from PR2 (Hirose, Mark)
      • Not yet ready

Other

  • Safety
    • No incident
  • #Installation procedure document
    • Many people need to contribute to the document. However, we need one person responsible for the consistency of the document.
    • BS installation document: Mark will be the editor.
  • #GAS blade inspection by Virgo (Takahashi)
    • Shipped the blades. Will get results in 1-2 months.

Next meeting

2015/2/12 (Fri) 13:30 -

The next F2F at Mitaka: 2/19