VIS Meeting on 2016/2/5
2015/2/5 13:00 -15:00
Kamioka TV conference room + SeeVogh
Participants:Shoda, Tanaka, Faian, Hirata, Mark, Takahashi, Okutomi, Aso, Sekiguchi, Tatsumi, Akutsu
Schedule
Schedule status (Aso) (Chart)
PR3
- PR3 Installation Status (Takahashi)
#Traverser repair: Repair of the broken ones at Mitaka -> Uraguchi-san is working on it.
#Screws to fix the front and back rings the RM were too long, or the tapping in the holes were too short. Couldn't use M5x40. Ordered M5x35 with vent holes. -> Delivered. Remember to replace them
- PR3 flag and 2nd wire breaker repair status (Tatsumi)
- PR3 arrived at Kamioka. Sitting in the front room of the PR3 clean booth.
- The frame for the clean bag is bent.
- Mirapro is available to reinforce the frame by gluing diagnal beams on Feb. 22.
- Once reinformced the frame cannot be disassembled. The frame will stay on the 2F.
Will ask Mirapro to go ahead (Aso)-> done
Plan for the next week
- Mon: Hang the mirror
- Tue: Hang RM, Cabling
- Wed: RM alignment, Signal check of OSEMs
- Thu: Set the top plate on the assembly frame
- Fri: Hang IM
iKAGRA ETM suspension
- Assembly of the suspension (Ohishi)
- Mostly completed.
Need to buy some screws-> ordered
- Missing parts (Tatsumi, Takahashi)
Plates to fix the connectors on the suspension frame were ordered. -> Delivered to Mitaka
Coil bobin: Delivery date-> Delivered to Kamioka
Insulation tubes for picomotor connectors -> ordered
- PRM transportation (Tatsumi)
- Wire breakers do not fit the plastic container.
- Asking for quotation for a larger size, but will take some time
- Cutting slits on the side wall of the container is another possibility. In this case, wrap the thing with a plastic bag willl be necessary for preventing dusts from coming in.
Will consult with Hirose-san about this (Tatsumi).
- Coil winding (Takahashi)
- Will be done by Ando-lab students from 2/8
Winding machine test status ? (Takahashi) -> Setup the machine in the clean booth. Test winding OK.
Plan for the next week
- 2/8-2/12: Completion of the assembly. TF measurements
- 2/12: Packing
Travel Plans
- Travel (Week of 2/8)
- Takahashi: Mon-Wed
Shoda:Mon-Fri
- Mark:
- Fabian:
Okutomi:Mon-Thu
Fujii:Mon-Fri
- Ishizaki:
- Hirata:
- Ohishi:
- Travel (Week of 2/15)
Takahashi:Mon-Thu
Shoda:Mon-Thu
- Mark:
- Fabian:
Okutomi:Mon-Thu
Fujii:Mon-Thu
- Ishizaki:
- Hirata:
- Ohishi:
- Sekiguchi: Mon-Thu
Other Mechanical Issues
- Wire winches
- Now in the ATC clean room.
- Asked Ikenue-san to repair it (Takahashi)
- Clean work procedure
- Will be discussed at F2F.
- #BF Optimal Weight (Takahashi)
- #Balast masses: Delivered to Mitaka. Will send them to Kamioka (Hirata)
- #IM wire clamps
- #Need to send the wire clamps used for the test hanging to I-ject: it was sent to I-ject (Takahashi)
- #Traverser actuation check (Shoda)
- #PR CAD model and assembly drawings (Hirata)
- Aso calculated the rotation angle
- PR3: 0.786deg counter clockwise from the line connecting the centers of the PR3 and BS chambers.
- Will make a report soon.
- Aso calculated the rotation angle
- #Wire cleaning (Hirata)
Hirata will order 20m more wires. -> Delivered. Will wipe in the next week. -> Finished. Will send to Kamioka soon.
Will wash Tungsten wire delivery status -> Delivered. Will wipe in the next week -> Finished. Will send to Kamioka soon.
- #Production of additional PR winches (Akutsu)
Shipping status (Takahashi, Hirata) -> Wrapped. Will be shipped with IP in the next week.
- #OSEM assembly status (Akutsu)
- #List of what should be changed for PR3 hanging
- People should share ideas whenever they come up with missing thigns.
- Shoda made a spread sheet for keep tracking the ideas
https://docs.google.com/spreadsheets/d/1zZaLObWjDSEOTrr85Hz0ApXxEUChK3xJ_chk0f7r5nY/edit?usp=sharing
- All the items are now done or being taken care of
- #Missing items(to be purchased soon)
#Traverser motor driver (Shoda) -> Will discuss Uraguchi-san. Need a box for stepping motor driver. -> These are for PR2. Will be ordered sometime.
Electronics
- What are necessary in the next few weeks ?
- Nothing
- Electronics diagram and review
Had a review on PR3 on Thursday - minutes, Mark's klog
We still need an overview diagram-> Mark will show us a draft version in the next meeting.
- Watch dog system (Tanaka)
- Made a prototype circuit board for checking the PCB design before ordering
- Getting quotations for electric components
- Will get a quotation for PCB production soon (target date is Feb 15)
- #LVDT distributor connector problem
Miyakawa-san circulated a design of the conversion cable (D9-D15): drawing
- #Digital System (Okutomi, Fujii)
- #Cable status (Takahashi)
Need to send more PTFE cable to finish the remaining two -> Will do it in the next week
Need to send the cables used for the test hanging once it is finished. -> Will send them once the test hanging is disassembled.
- #Cable check
- Liu-kun Zhao-kun finished checking all the cables. They found another broken cable.
- Will send the broken cables together with the other cable related items (Takahashi).
bKAGRA preparation
- Three big categories of the tasks
- Type-A: Leader = Takahashi: Task list, team members
- Type-B (BS and SRC): Leader = Mark: Task list, team members
- Type-Bp modification: Continue discussion (Aso, Raffaele)
Common Issues
BS and SR
Task listKAGRA/Subgroups/VIS/TypeB/TaskList
- Kick off meeting within February (Mark)
- BS prism preparation
- Contacted the company LIGO used for the possibility of buying sapphire prisms (Mark)
- They are happy to take an order. No Japanese agent. But international order can be taken.
Will ask for the lead time to the company (Mark) Drawing to be sent (LIGO drawing) -> Send the drawing to the companies immediately assuming SR uses 5mm
Can we make the BS and SR prisms the same: Mark/Hirata klog -> Seems possible to use the same size 5mm
- Can we make SR wire breakers bigger ?
We need to decide on how much to widen. Check what happens if we use 5mm tall prism on CAD (Hirata) -> Result
- Make the slit wider by 3mm will interfere with a M5 threaded hole
- The hole is needed to keep the mechanical rigidity
- Can make a new M5 hole somewhere near by ?
Check what happens if we widen the slit by 3.75mm and make a new M5 (Hirata) -> Result
- Will talk to Fukushima-san again (Hirata)
Wider cuts will break the horizontal balance. Need to check how much compensation mass is reduced.
- Make the slit wider by 3mm will interfere with a M5 threaded hole
- Flag design (Mark)
Mark will sort out the ideas and organize a specialized meeting.-> will present an updated version in the next meeting.
IP base clamp (Fabian): Picture -> Reduce the number of clamps-> Hirata-san is working on 2D drawings. Will finish on Monday.
Bread board spring (Takahashi): Will talk to Mark after the meeting.
- New accelerometer for IP (Joris)
Will give a talk at an NAOJ seminar in March-> Will tell him to contact Akutsu-kun-> done
- #BS Assembly Frame Design (Aso, Hirata)
- #BS gluing jigs (Tatsumi)
- #Not enough crane height problem (Hirata, Saito)
- #BS clean bag (Aso)
Type A
Task list (Takahashi)
- Need more frequent interaction with cryogenic people
- Simulation task is needed. It should be the first priority
- Blade design task is missing
Prioritize the tasks and make a tentative schedule by the next meeting (Takahashi)
- Fishing rod production status (Takahashi)
- Ordered the material for the blades.
- Stepping motors were ordered.
Mechanical parts remaining to be ordered -> ordered
- #Type-A Filters Optimal Load Measurements
#Takahashi will make a plan for the optimal load check and ask ATC.-> Check two filters per month from April 2016. -> Will be presented to the ATC steering committee.
- #How to manufacture the long maraging wires ?
- One prototype was machined by Ojima
Aoshima can do the heat treatment for the long rod. Will ask them soon (Takahashi) -> Still waiting for a quotation.
- How to test it ?
- We can use the prototype assembly frame in TAMA.
Type-Bp modification
- PRM traverser
- Postpone the production to the next FY until we know the details of the modification.
Tell Uraguchi-san about the above plan (Takahashi)
- #PR2 Wire breaker problem
- Prism removal from PR2 (Hirose, Mark)
- Not yet ready
- Prism removal from PR2 (Hirose, Mark)
Other
- Safety
- No incident
- Installation procedure document
- Many people need to contribute to the document. However, we need one person responsible for the consistency of the document.
- BS installation document: Mark will be the editor.
- iKAGRA PR3 installation document: Shoda will be the editor
- #GAS blade inspection by Virgo (Takahashi)
- Shipped the blades. Will get results in 1-2 months.
Next meeting
2015/2/12 (Fri) 13:30 -
The next F2F at Mitaka: 2/19