Size: 9972
Comment:
|
Size: 9455
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 1: | Line 1: |
= VIS Meeting on 2016/2/5 = 2015/2/5 13:00 -15:00 |
= VIS Meeting on 2016/2/12 = 2015/2/12 13:30 -15:00 |
Line 6: | Line 6: |
Participants:Shoda, Tanaka, Faian, Hirata, Mark, Takahashi, Okutomi, Aso, Sekiguchi, Tatsumi, Akutsu | Participants:Takahashi, Mark, Hirata, Fabian, Shoda, Fujii, Aso, Sekiguchi, Akutsu, Okutomi |
Line 9: | Line 9: |
* Schedule status (Aso) ([[attachment:05_VIS-20160205.pdf|Chart]]) | * Schedule status (Aso) ([[https://www.dropbox.com/s/y586flgsr0usmvx/05_VIS-20160212.pdf?dl=0|Chart]]) |
Line 13: | Line 13: |
* Wire breaker groove problem * Wrong surface was glued on the mirror side. So no groove is present where the wires touch. * Put alminum foil between the prism and the wires * Current status (http://klog.icrr.u-tokyo.ac.jp/osl/?r=756) * IM and the bottom filter is connected. * Adjusting the weight of the IM |
|
Line 15: | Line 21: |
* PR3 flag and 2nd wire breaker repair status (Tatsumi) * PR3 arrived at Kamioka. Sitting in the front room of the PR3 clean booth. |
|
Line 18: | Line 22: |
* Mirapro is available to reinforce the frame by gluing diagnal beams on Feb. 22. * Once reinformced the frame cannot be disassembled. The frame will stay on the 2F. * Will ask Mirapro to go ahead (Aso)-> done |
* Reinformcement design by Mirapro * [[https://www.dropbox.com/s/l8er09c3d7lmsgr/VP5904-A_Bag%20Frame%20Assy.pdf?dl=0|2D Drawing]] * [[https://www.dropbox.com/s/j8rcpvytin0qft6/Bag%20Frame.stp?dl=0|STEP]] * [[https://www.dropbox.com/s/llu99rjj0gnesz2/Bag%20Assy.png?dl=0|Assembly image]] * [[https://www.dropbox.com/s/zsrizfnzx9xuovp/Bag%20Assy.stp?dl=0|Assembly STEP]] * Tell Mirapro to go ahead (Aso) * Mirapro will come on 22nd to make changes. * Crane will be not available on 2/25 for the crane upgrade to remote control. We need to coordinate with Uchiyama-san if we want to do the vacuum installation on 25th. |
Line 23: | Line 32: |
* Mon: Hang the mirror * Tue: Hang RM, Cabling * Wed: RM alignment, Signal check of OSEMs * Thu: Set the top plate on the assembly frame * Fri: Hang IM |
* Mon: IM hanging * Tue: IMRM hanging * Wed: IM alignment * Thu: OSEM setup * Fri: |
Line 31: | Line 40: |
* Mostly completed. * Need to buy some screws-> ordered |
|
Line 34: | Line 41: |
* Plates to fix the connectors on the suspension frame were ordered. -> Delivered to Mitaka * Coil bobin: Delivery date-> Delivered to Kamioka * Insulation tubes for picomotor connectors -> ordered * PRM transportation (Tatsumi) * Wire breakers do not fit the plastic container. * Asking for quotation for a larger size, but will take some time * Cutting slits on the side wall of the container is another possibility. In this case, wrap the thing with a plastic bag willl be necessary for preventing dusts from coming in. * '''Will consult with Hirose-san about this (Tatsumi).''' |
* Insulation tubes for picomotor connectors * Tubes were delivered on Wed. * Cable ties are not yet delivered -> check the delivery date (Takahashi) * Suspension Test (Ohishi) |
Line 43: | Line 46: |
* Will be done by Ando-lab students from 2/8 * Winding machine test status ? (Takahashi) -> Setup the machine in the clean booth. Test winding OK. |
* Made 13 coils in total. * Need to send 3 bobins to the coil winding company * TAMA PRM transportation (Tatsumi) -> done today. |
Line 47: | Line 51: |
* 2/8-2/12: Completion of the assembly. TF measurements * 2/12: Packing |
|
Line 51: | Line 52: |
* Travel (Week of 2/8) * Takahashi: Mon-Wed * Shoda:Mon-Fri * Mark: * Fabian: * Okutomi:Mon-Thu * Fujii:Mon-Fri * Ishizaki: * Hirata: * Ohishi: |
|
Line 74: | Line 64: |
VIS F2F 2/19 KAGRA F2F 2/21 - 23 * Travel (Week of 2/22) * Takahashi:Wed - Thu (Fri: Akeno for the acceptance of IP from NIKHEF) * Shoda:Wed - Fri * Mark: * Fabian: * Okutomi:Wed - Fri * Fujii:Wed - Fri * Ishizaki: * Hirata: * Ohishi: |
|
Line 75: | Line 80: |
* Wire winches | * Rotation angle of the PR3 mirror * 0.786deg counter clockwise from the line connecting the centers of the PR3 and BS chambers. * 0.619deg counter clockwise with respect to the chamber ([[https://www.dropbox.com/s/073wcbz652i016a/VM5920_KAGRA真空容器PR3_Type-Bp.pdf?dl=0|schematic]]) * Currently the mirror is rotated by 0.65deg (measured at the time of the test hanging). * This is well within the actuation range of the traverser. -> Will not make any further adjustment. * #Wire winches |
Line 79: | Line 89: |
* Clean work procedure | * #Clean work procedure |
Line 88: | Line 98: |
* #PR CAD model and assembly drawings (Hirata) * Aso calculated the rotation angle * PR3: 0.786deg counter clockwise from the line connecting the centers of the PR3 and BS chambers. * Will make a report soon. |
|
Line 116: | Line 121: |
* Had a review on PR3 on Thursday - [[KAGRA/Subgroups/VIS/VISMinutes20160204|minutes]], [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=719|Mark's klog]] * We still need an overview diagram-> Mark will show us a draft version in the next meeting. |
* Mark: detailed schematics nearly ready to post - [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3615|D1503615 (full PR3)]], [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4795|D1604795 (iKAGRA PR3)]] * Mark: started overview schematic [[attachment:Cabling Overview.graffle.pdf|diagram]], * Need to make Guradian script for PR3. Shoda + Fujii and Okutomi will write one after the mechanical installation is finished. |
Line 120: | Line 125: |
* Made a prototype circuit board for checking the PCB design before ordering * Getting quotations for electric components * Will get a quotation for PCB production soon (target date is Feb 15) |
|
Line 145: | Line 147: |
== BS and SR == | == Type-B == |
Line 148: | Line 150: |
* BS prism preparation * Contacted the company LIGO used for the possibility of buying sapphire prisms (Mark) * They are happy to take an order. No Japanese agent. But international order can be taken. * Will ask for the lead time to the company (Mark) [[attachment:JGW-D1504344_rev2.pdf|Drawing to be sent]] ([[attachment:D0810033_ADLIGO SUS IMC_PRISM_BREAKOFF_WIRE LOOP_TEST MASS.pdf|LIGO drawing]]) -> '''Send the drawing to the companies immediately assuming SR uses 5mm''' * Can we make the BS and SR prisms the same: [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=718|Mark/Hirata klog]] -> Seems possible to use the same size 5mm |
* BS prism preparation (Mark) * 5mm prism [[attachment:JGW-D1604796.pdf|drawing]] * Confirmed with Hirata-san that BS can use same 5 mm prism as SR (grooves, wire clearance all OK). * Confirmed with Tatsumi-san that not a big deal to use smaller BS prism as long as secondary position not changed. * Submitted 5 mm prism drawing to company that did LIGO HSTS prism (except grooves), waiting on response. * Second company that did LIGO groove cutting not interested in quoting - exploring other US companies. * Should contact Shinko-sha again (Takahashi) |
Line 154: | Line 158: |
* We need to decide on how much to widen. Check what happens if we use 5mm tall prism on CAD (Hirata) -> [[attachment:wire and groove position.pdf|Result]] * Make the slit wider by 3mm will interfere with a M5 threaded hole * The hole is needed to keep the mechanical rigidity * Can make a new M5 hole somewhere near by ? * Check what happens if we widen the slit by 3.75mm and make a new M5 (Hirata) -> [[https://www.dropbox.com/sh/f5lnexvb6k9bovo/AABEYf4_C19GXYEuJZZiy7cqa?dl=0|Result]] * Will talk to Fukushima-san again (Hirata) * Wider cuts will break the horizontal balance. '''Need to check how much compensation mass is reduced. ''' |
* Check what happens if we widen the slit by 3.75mm and make a new M5 (Hirata) -> [[https://www.dropbox.com/sh/f5lnexvb6k9bovo/AABEYf4_C19GXYEuJZZiy7cqa?dl=0|Result]] * Two concerns * The rework may bend the wing shaped parts. * The P.C.D. of the new screw holes may not coincide exactly with the other existing holes * Consult with Fukushima-san again. Takahashi will contact Fukushima-san * Do we need to widen the slits for PRC RMs ? -> Depends on how difficult it is to rework the RM. * Wider cuts will break the horizontal balance. Need to check how much compensation mass is reduced (Hirata) -> 2mm reduction will be necessary. We can do this. |
Line 162: | Line 166: |
* Mark will sort out the ideas and organize a specialized meeting.-> '''will present an updated version in the next meeting.''' * IP base clamp (Fabian): [[attachment:image.png|Picture]] -> Reduce the number of clamps-> Hirata-san is working on 2D drawings. '''Will finish on Monday. ''' * Bread board spring (Takahashi): '''Will talk to Mark after the meeting. ''' * New accelerometer for IP (Joris) * Will give a talk at an NAOJ seminar in March-> Will tell him to contact Akutsu-kun-> done |
* Shorter flag is desirable ? * Mark will sort out the ideas and organize a specialized meeting.-> will present an updated version in the next meeting. * IP base clamp (Fabian): [[attachment:image.png|Picture]] -> Reduce the number of clamps-> Hirata-san finished 2D drawings. Trying to get quotation now. * Bread board spring (Takahashi): Hirata-san is getting quotations. |
Line 174: | Line 177: |
* Need more frequent interaction with cryogenic people * Simulation task is needed. It should be the first priority * Blade design task is missing * '''Prioritize the tasks and make a tentative schedule by the next meeting (Takahashi)''' * Fishing rod production status (Takahashi) * Ordered the material for the blades. * Stepping motors were ordered. * Mechanical parts remaining to be ordered -> ordered |
|
Line 194: | Line 189: |
* '''Tell Uraguchi-san about the above plan (Takahashi)''' | * Tell Uraguchi-san about the above plan (Takahashi) -> done |
Line 203: | Line 198: |
* Installation procedure document * Many people need to contribute to the document. However, we need one person responsible for the consistency of the document. * BS installation document: Mark will be the editor. * iKAGRA PR3 installation document: Shoda will be the editor |
|
Line 212: | Line 202: |
2015/2/12 (Fri) 13:30 - The next F2F at Mitaka: 2/19 |
2015/2/19 (Fri) 13:30 - @ Mitaka |
VIS Meeting on 2016/2/12
2015/2/12 13:30 -15:00
Kamioka TV conference room + SeeVogh
Participants:Takahashi, Mark, Hirata, Fabian, Shoda, Fujii, Aso, Sekiguchi, Akutsu, Okutomi
Schedule
Schedule status (Aso) (Chart)
PR3
- PR3 Installation Status (Takahashi)
- Wire breaker groove problem
- Wrong surface was glued on the mirror side. So no groove is present where the wires touch.
- Put alminum foil between the prism and the wires
Current status (http://klog.icrr.u-tokyo.ac.jp/osl/?r=756)
- IM and the bottom filter is connected.
- Adjusting the weight of the IM
#Traverser repair: Repair of the broken ones at Mitaka -> Uraguchi-san is working on it.
#Screws to fix the front and back rings the RM were too long, or the tapping in the holes were too short. Couldn't use M5x40. Ordered M5x35 with vent holes. -> Delivered. Remember to replace them
- Wire breaker groove problem
- The frame for the clean bag is bent.
- Reinformcement design by Mirapro
- Tell Mirapro to go ahead (Aso)
- Mirapro will come on 22nd to make changes.
- Crane will be not available on 2/25 for the crane upgrade to remote control. We need to coordinate with Uchiyama-san if we want to do the vacuum installation on 25th.
Plan for the next week
- Mon: IM hanging
- Tue: IMRM hanging
- Wed: IM alignment
- Thu: OSEM setup
- Fri:
iKAGRA ETM suspension
- Assembly of the suspension (Ohishi)
- Missing parts (Tatsumi, Takahashi)
- Insulation tubes for picomotor connectors
- Tubes were delivered on Wed.
Cable ties are not yet delivered -> check the delivery date (Takahashi)
- Insulation tubes for picomotor connectors
- Suspension Test (Ohishi)
- Coil winding (Takahashi)
- Made 13 coils in total.
- Need to send 3 bobins to the coil winding company
TAMA PRM transportation (Tatsumi) -> done today.
Plan for the next week
Travel Plans
- Travel (Week of 2/15)
Takahashi:Mon-Thu
Shoda:Mon-Thu
- Mark:
- Fabian:
Okutomi:Mon-Thu
Fujii:Mon-Thu
- Ishizaki:
- Hirata:
- Ohishi:
- Sekiguchi: Mon-Thu
VIS F2F 2/19
KAGRA F2F 2/21 - 23
- Travel (Week of 2/22)
Takahashi:Wed - Thu (Fri: Akeno for the acceptance of IP from NIKHEF)
Shoda:Wed - Fri
- Mark:
- Fabian:
Okutomi:Wed - Fri
Fujii:Wed - Fri
- Ishizaki:
- Hirata:
- Ohishi:
Other Mechanical Issues
- Rotation angle of the PR3 mirror
- 0.786deg counter clockwise from the line connecting the centers of the PR3 and BS chambers.
0.619deg counter clockwise with respect to the chamber (schematic)
- Currently the mirror is rotated by 0.65deg (measured at the time of the test hanging).
This is well within the actuation range of the traverser. -> Will not make any further adjustment.
- #Wire winches
- Now in the ATC clean room.
- Asked Ikenue-san to repair it (Takahashi)
- #Clean work procedure
- Will be discussed at F2F.
- #BF Optimal Weight (Takahashi)
- #Balast masses: Delivered to Mitaka. Will send them to Kamioka (Hirata)
- #IM wire clamps
- #Need to send the wire clamps used for the test hanging to I-ject: it was sent to I-ject (Takahashi)
- #Traverser actuation check (Shoda)
- #Wire cleaning (Hirata)
Hirata will order 20m more wires. -> Delivered. Will wipe in the next week. -> Finished. Will send to Kamioka soon.
Will wash Tungsten wire delivery status -> Delivered. Will wipe in the next week -> Finished. Will send to Kamioka soon.
- #Production of additional PR winches (Akutsu)
Shipping status (Takahashi, Hirata) -> Wrapped. Will be shipped with IP in the next week.
- #OSEM assembly status (Akutsu)
- #List of what should be changed for PR3 hanging
- People should share ideas whenever they come up with missing thigns.
- Shoda made a spread sheet for keep tracking the ideas
https://docs.google.com/spreadsheets/d/1zZaLObWjDSEOTrr85Hz0ApXxEUChK3xJ_chk0f7r5nY/edit?usp=sharing
- All the items are now done or being taken care of
- #Missing items(to be purchased soon)
#Traverser motor driver (Shoda) -> Will discuss Uraguchi-san. Need a box for stepping motor driver. -> These are for PR2. Will be ordered sometime.
Electronics
- What are necessary in the next few weeks ?
- Nothing
- Electronics diagram and review
Mark: detailed schematics nearly ready to post - D1503615 (full PR3), D1604795 (iKAGRA PR3)
Mark: started overview schematic diagram,
- Need to make Guradian script for PR3. Shoda + Fujii and Okutomi will write one after the mechanical installation is finished.
- Watch dog system (Tanaka)
- #LVDT distributor connector problem
Miyakawa-san circulated a design of the conversion cable (D9-D15): drawing
- #Digital System (Okutomi, Fujii)
- #Cable status (Takahashi)
Need to send more PTFE cable to finish the remaining two -> Will do it in the next week
Need to send the cables used for the test hanging once it is finished. -> Will send them once the test hanging is disassembled.
- #Cable check
- Liu-kun Zhao-kun finished checking all the cables. They found another broken cable.
- Will send the broken cables together with the other cable related items (Takahashi).
bKAGRA preparation
- Three big categories of the tasks
- Type-A: Leader = Takahashi: Task list, team members
- Type-B (BS and SRC): Leader = Mark: Task list, team members
- Type-Bp modification: Continue discussion (Aso, Raffaele)
Common Issues
Type-B
Task listKAGRA/Subgroups/VIS/TypeB/TaskList
- Kick off meeting within February (Mark)
- BS prism preparation (Mark)
5mm prism drawing
- Confirmed with Hirata-san that BS can use same 5 mm prism as SR (grooves, wire clearance all OK).
- Confirmed with Tatsumi-san that not a big deal to use smaller BS prism as long as secondary position not changed.
- Submitted 5 mm prism drawing to company that did LIGO HSTS prism (except grooves), waiting on response.
- Second company that did LIGO groove cutting not interested in quoting - exploring other US companies.
- Should contact Shinko-sha again (Takahashi)
- Can we make SR wire breakers bigger ?
Check what happens if we widen the slit by 3.75mm and make a new M5 (Hirata) -> Result
- Two concerns
- The rework may bend the wing shaped parts.
- The P.C.D. of the new screw holes may not coincide exactly with the other existing holes
- Consult with Fukushima-san again. Takahashi will contact Fukushima-san
Do we need to widen the slits for PRC RMs ? -> Depends on how difficult it is to rework the RM.
Wider cuts will break the horizontal balance. Need to check how much compensation mass is reduced (Hirata) -> 2mm reduction will be necessary. We can do this.
- Two concerns
- Flag design (Mark)
- Shorter flag is desirable ?
Mark will sort out the ideas and organize a specialized meeting.-> will present an updated version in the next meeting.
IP base clamp (Fabian): Picture -> Reduce the number of clamps-> Hirata-san finished 2D drawings. Trying to get quotation now.
- Bread board spring (Takahashi): Hirata-san is getting quotations.
- #BS Assembly Frame Design (Aso, Hirata)
- #BS gluing jigs (Tatsumi)
- #Not enough crane height problem (Hirata, Saito)
- #BS clean bag (Aso)
Type A
Task list (Takahashi)
- #Type-A Filters Optimal Load Measurements
#Takahashi will make a plan for the optimal load check and ask ATC.-> Check two filters per month from April 2016. -> Will be presented to the ATC steering committee.
- #How to manufacture the long maraging wires ?
- One prototype was machined by Ojima
Aoshima can do the heat treatment for the long rod. Will ask them soon (Takahashi) -> Still waiting for a quotation.
- How to test it ?
- We can use the prototype assembly frame in TAMA.
Type-Bp modification
- PRM traverser
- Postpone the production to the next FY until we know the details of the modification.
Tell Uraguchi-san about the above plan (Takahashi) -> done
- #PR2 Wire breaker problem
- Prism removal from PR2 (Hirose, Mark)
- Not yet ready
- Prism removal from PR2 (Hirose, Mark)
Other
- Safety
- No incident
- #GAS blade inspection by Virgo (Takahashi)
- Shipped the blades. Will get results in 1-2 months.
Next meeting
2015/2/19 (Fri) 13:30 - @ Mitaka