Comment:
|
← Revision 12 as of 2016-02-13 06:23:04 ⇥
Size: 9455
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 2: | Line 2: |
2015/2/12 13:30 -15:00 | 2015/2/12 13:30 -15:30 |
Line 6: | Line 6: |
Participants: | Participants:Takahashi, Mark, Hirata, Fabian, Shoda, Fujii, Aso, Sekiguchi, Akutsu, Okutomi |
Line 13: | Line 13: |
* Wire breaker slit problem | * Wire breaker groove problem * Wrong surface was glued on the mirror side. So no groove is present where the wires touch. * Put alminum foil between the prism and the wires * Current status (http://klog.icrr.u-tokyo.ac.jp/osl/?r=756) * IM and the bottom filter is connected. * Adjusting the weight of the IM |
Line 22: | Line 27: |
* Tell Mirapro to go ahead (Aso) * Mirapro will come on 22nd to make changes. * Crane will be not available on 2/25 for the crane upgrade to remote control. We need to coordinate with Uchiyama-san if we want to do the vacuum installation on 25th. |
|
Line 24: | Line 32: |
* Mon: Hang the mirror * Tue: Hang RM, Cabling * Wed: RM alignment, Signal check of OSEMs * Thu: Set the top plate on the assembly frame * Fri: Hang IM |
* Mon: IM hanging * Tue: IMRM hanging * Wed: IM alignment * Thu: OSEM setup * Fri: |
Line 33: | Line 41: |
* Insulation tubes for picomotor connectors -> ordered | * Insulation tubes for picomotor connectors * Tubes were delivered on Wed. * Cable ties are not yet delivered -> check the delivery date (Takahashi) |
Line 36: | Line 46: |
* PRM transportation (Tatsumi) | * Made 13 coils in total. * Need to send 3 bobins to the coil winding company * TAMA PRM transportation (Tatsumi) -> done today. |
Line 57: | Line 69: |
* Takahashi: * Shoda: |
* Takahashi:Wed - Thu (Fri: Akeno for the acceptance of IP from NIKHEF) * Shoda:Wed - Fri |
Line 61: | Line 73: |
* Okutomi: * Fujii: |
* Okutomi:Wed - Fri * Fujii:Wed - Fri |
Line 71: | Line 83: |
* Currently the mirror is rotated by 0.65deg (measured at the time of the test hanging). * This is well within the actuation range of the traverser. -> Will not make any further adjustment. |
|
Line 108: | Line 122: |
* Mark: started overview schematic [[attachment:Cabling Overview.graffle.pdf|diagram]], | * Mark: started overview schematic [[attachment:Cabling Overview.graffle.pdf|diagram]], * Need to make Guradian script for PR3. Shoda + Fujii and Okutomi will write one after the mechanical installation is finished. |
Line 132: | Line 147: |
== BS and SR == | == Type-B == |
Line 141: | Line 156: |
* Can we make SR wire breakers bigger ?<<BR>> | * Should contact Shinko-sha again (Takahashi) * Can we make SR wire breakers bigger ? |
Line 143: | Line 159: |
* Will talk to Fukushima-san again (Hirata) * Wider cuts will break the horizontal balance. Need to check how much compensation mass is reduced (Hirata). |
* Two concerns * The rework may bend the wing shaped parts. * The P.C.D. of the new screw holes may not coincide exactly with the other existing holes * Consult with Fukushima-san again. Takahashi will contact Fukushima-san * Do we need to widen the slits for PRC RMs ? -> Depends on how difficult it is to rework the RM. * Wider cuts will break the horizontal balance. Need to check how much compensation mass is reduced (Hirata) -> 2mm reduction will be necessary. We can do this. |
Line 146: | Line 166: |
* Shorter flag is desirable ? | |
Line 147: | Line 168: |
* IP base clamp (Fabian): [[attachment:image.png|Picture]] -> Reduce the number of clamps-> Hirata-san is working on 2D drawings. Will finish on Monday. * Bread board spring (Takahashi): Will talk to Mark after the meeting. |
* IP base clamp (Fabian): [[attachment:image.png|Picture]] -> Reduce the number of clamps-> Hirata-san finished 2D drawings. Trying to get quotation now. * Bread board spring (Takahashi): Hirata-san is getting quotations. |
Line 156: | Line 177: |
* '''Prioritize the tasks and make a tentative schedule by the next meeting (Takahashi)''' | |
Line 169: | Line 189: |
* Tell Uraguchi-san about the above plan (Takahashi) | * Tell Uraguchi-san about the above plan (Takahashi) -> done |
Line 176: | Line 196: |
* No incident |
VIS Meeting on 2016/2/12
2015/2/12 13:30 -15:30
Kamioka TV conference room + SeeVogh
Participants:Takahashi, Mark, Hirata, Fabian, Shoda, Fujii, Aso, Sekiguchi, Akutsu, Okutomi
Schedule
Schedule status (Aso) (Chart)
PR3
- PR3 Installation Status (Takahashi)
- Wire breaker groove problem
- Wrong surface was glued on the mirror side. So no groove is present where the wires touch.
- Put alminum foil between the prism and the wires
Current status (http://klog.icrr.u-tokyo.ac.jp/osl/?r=756)
- IM and the bottom filter is connected.
- Adjusting the weight of the IM
#Traverser repair: Repair of the broken ones at Mitaka -> Uraguchi-san is working on it.
#Screws to fix the front and back rings the RM were too long, or the tapping in the holes were too short. Couldn't use M5x40. Ordered M5x35 with vent holes. -> Delivered. Remember to replace them
- Wire breaker groove problem
- The frame for the clean bag is bent.
- Reinformcement design by Mirapro
- Tell Mirapro to go ahead (Aso)
- Mirapro will come on 22nd to make changes.
- Crane will be not available on 2/25 for the crane upgrade to remote control. We need to coordinate with Uchiyama-san if we want to do the vacuum installation on 25th.
Plan for the next week
- Mon: IM hanging
- Tue: IMRM hanging
- Wed: IM alignment
- Thu: OSEM setup
- Fri:
iKAGRA ETM suspension
- Assembly of the suspension (Ohishi)
- Missing parts (Tatsumi, Takahashi)
- Insulation tubes for picomotor connectors
- Tubes were delivered on Wed.
Cable ties are not yet delivered -> check the delivery date (Takahashi)
- Insulation tubes for picomotor connectors
- Suspension Test (Ohishi)
- Coil winding (Takahashi)
- Made 13 coils in total.
- Need to send 3 bobins to the coil winding company
TAMA PRM transportation (Tatsumi) -> done today.
Plan for the next week
Travel Plans
- Travel (Week of 2/15)
Takahashi:Mon-Thu
Shoda:Mon-Thu
- Mark:
- Fabian:
Okutomi:Mon-Thu
Fujii:Mon-Thu
- Ishizaki:
- Hirata:
- Ohishi:
- Sekiguchi: Mon-Thu
VIS F2F 2/19
KAGRA F2F 2/21 - 23
- Travel (Week of 2/22)
Takahashi:Wed - Thu (Fri: Akeno for the acceptance of IP from NIKHEF)
Shoda:Wed - Fri
- Mark:
- Fabian:
Okutomi:Wed - Fri
Fujii:Wed - Fri
- Ishizaki:
- Hirata:
- Ohishi:
Other Mechanical Issues
- Rotation angle of the PR3 mirror
- 0.786deg counter clockwise from the line connecting the centers of the PR3 and BS chambers.
0.619deg counter clockwise with respect to the chamber (schematic)
- Currently the mirror is rotated by 0.65deg (measured at the time of the test hanging).
This is well within the actuation range of the traverser. -> Will not make any further adjustment.
- #Wire winches
- Now in the ATC clean room.
- Asked Ikenue-san to repair it (Takahashi)
- #Clean work procedure
- Will be discussed at F2F.
- #BF Optimal Weight (Takahashi)
- #Balast masses: Delivered to Mitaka. Will send them to Kamioka (Hirata)
- #IM wire clamps
- #Need to send the wire clamps used for the test hanging to I-ject: it was sent to I-ject (Takahashi)
- #Traverser actuation check (Shoda)
- #Wire cleaning (Hirata)
Hirata will order 20m more wires. -> Delivered. Will wipe in the next week. -> Finished. Will send to Kamioka soon.
Will wash Tungsten wire delivery status -> Delivered. Will wipe in the next week -> Finished. Will send to Kamioka soon.
- #Production of additional PR winches (Akutsu)
Shipping status (Takahashi, Hirata) -> Wrapped. Will be shipped with IP in the next week.
- #OSEM assembly status (Akutsu)
- #List of what should be changed for PR3 hanging
- People should share ideas whenever they come up with missing thigns.
- Shoda made a spread sheet for keep tracking the ideas
https://docs.google.com/spreadsheets/d/1zZaLObWjDSEOTrr85Hz0ApXxEUChK3xJ_chk0f7r5nY/edit?usp=sharing
- All the items are now done or being taken care of
- #Missing items(to be purchased soon)
#Traverser motor driver (Shoda) -> Will discuss Uraguchi-san. Need a box for stepping motor driver. -> These are for PR2. Will be ordered sometime.
Electronics
- What are necessary in the next few weeks ?
- Nothing
- Electronics diagram and review
Mark: detailed schematics nearly ready to post - D1503615 (full PR3), D1604795 (iKAGRA PR3)
Mark: started overview schematic diagram,
- Need to make Guradian script for PR3. Shoda + Fujii and Okutomi will write one after the mechanical installation is finished.
- Watch dog system (Tanaka)
- #LVDT distributor connector problem
Miyakawa-san circulated a design of the conversion cable (D9-D15): drawing
- #Digital System (Okutomi, Fujii)
- #Cable status (Takahashi)
Need to send more PTFE cable to finish the remaining two -> Will do it in the next week
Need to send the cables used for the test hanging once it is finished. -> Will send them once the test hanging is disassembled.
- #Cable check
- Liu-kun Zhao-kun finished checking all the cables. They found another broken cable.
- Will send the broken cables together with the other cable related items (Takahashi).
bKAGRA preparation
- Three big categories of the tasks
- Type-A: Leader = Takahashi: Task list, team members
- Type-B (BS and SRC): Leader = Mark: Task list, team members
- Type-Bp modification: Continue discussion (Aso, Raffaele)
Common Issues
Type-B
Task listKAGRA/Subgroups/VIS/TypeB/TaskList
- Kick off meeting within February (Mark)
- BS prism preparation (Mark)
5mm prism drawing
- Confirmed with Hirata-san that BS can use same 5 mm prism as SR (grooves, wire clearance all OK).
- Confirmed with Tatsumi-san that not a big deal to use smaller BS prism as long as secondary position not changed.
- Submitted 5 mm prism drawing to company that did LIGO HSTS prism (except grooves), waiting on response.
- Second company that did LIGO groove cutting not interested in quoting - exploring other US companies.
- Should contact Shinko-sha again (Takahashi)
- Can we make SR wire breakers bigger ?
Check what happens if we widen the slit by 3.75mm and make a new M5 (Hirata) -> Result
- Two concerns
- The rework may bend the wing shaped parts.
- The P.C.D. of the new screw holes may not coincide exactly with the other existing holes
- Consult with Fukushima-san again. Takahashi will contact Fukushima-san
Do we need to widen the slits for PRC RMs ? -> Depends on how difficult it is to rework the RM.
Wider cuts will break the horizontal balance. Need to check how much compensation mass is reduced (Hirata) -> 2mm reduction will be necessary. We can do this.
- Two concerns
- Flag design (Mark)
- Shorter flag is desirable ?
Mark will sort out the ideas and organize a specialized meeting.-> will present an updated version in the next meeting.
IP base clamp (Fabian): Picture -> Reduce the number of clamps-> Hirata-san finished 2D drawings. Trying to get quotation now.
- Bread board spring (Takahashi): Hirata-san is getting quotations.
- #BS Assembly Frame Design (Aso, Hirata)
- #BS gluing jigs (Tatsumi)
- #Not enough crane height problem (Hirata, Saito)
- #BS clean bag (Aso)
Type A
Task list (Takahashi)
- #Type-A Filters Optimal Load Measurements
#Takahashi will make a plan for the optimal load check and ask ATC.-> Check two filters per month from April 2016. -> Will be presented to the ATC steering committee.
- #How to manufacture the long maraging wires ?
- One prototype was machined by Ojima
Aoshima can do the heat treatment for the long rod. Will ask them soon (Takahashi) -> Still waiting for a quotation.
- How to test it ?
- We can use the prototype assembly frame in TAMA.
Type-Bp modification
- PRM traverser
- Postpone the production to the next FY until we know the details of the modification.
Tell Uraguchi-san about the above plan (Takahashi) -> done
- #PR2 Wire breaker problem
- Prism removal from PR2 (Hirose, Mark)
- Not yet ready
- Prism removal from PR2 (Hirose, Mark)
Other
- Safety
- No incident
- #GAS blade inspection by Virgo (Takahashi)
- Shipped the blades. Will get results in 1-2 months.
Next meeting
2015/2/19 (Fri) 13:30 - @ Mitaka