VIS Meeting on 2016/2/26

2015/2/26 13:30 -

Kamioka NAOJ Room & SeeVogh

Participants:

Schedule

  • Schedule status (Aso) (Chart)

PR3

Plan for the next week

  • Mon: Suspenion control tuning
  • Tue: Suspenion control tuning
  • Wed: Suspenion control tuning
  • Thu:Suspenion control tuning

  • Fri: Suspenion control tuning

iKAGRA ETM suspension

  • Current status (Ohishi)

Travel Plans

  • Travel (Week of 2/29)
    • Takahashi:
    • Shoda:
    • Mark:
    • Fabian:
    • Okutomi:
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Ohishi:
  • Travel (Week of 3/7)
    • Takahashi:
    • Shoda:
    • Mark:
    • Fabian:
    • Okutomi:
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Ohishi:

Other Mechanical Issues

  • #OSEM assembly status (Akutsu)
  • #Missing items(to be purchased soon)
    • #Traverser motor driver (Shoda) -> Will discuss Uraguchi-san. Need a box for stepping motor driver. -> These are for PR2. Will be ordered sometime.

Electronics

  • What are necessary in the next few weeks ?
    • Nothing
  • Watch dog system (Tanaka)
  • Need to make Guradian script for PR3. Shoda + Fujii and Okutomi will write one after the mechanical installation is finished.
  • #Electronics diagram and review

bKAGRA preparation

  • Three big categories of the tasks
    • Type-A: Leader = Takahashi
    • Type-B (BS and SRC): Leader = Mark
    • Type-Bp modification: Leader = Shoda

Common Issues

Type-B

  • Task listKAGRA/Subgroups/VIS/TypeB/TaskList

    • Kick off meeting within February (Mark)
  • BS prism preparation (Mark)
    • First LIGO company quoted on prism less grooves, and recommended other company for those. US$750 each for 12, 6-8 weeks delivery. Insaco_prism_quote.pdf

    • Should contact Shinko-sha again (Takahashi)
      • 260KJPY for two. Lead time = 1.5month
  • Can we make SR wire breakers bigger ?
    • Check what happens if we widen the slit by 3.75mm and make a new M5 (Hirata) -> Result

      • Two concerns
        • The rework may bend the wing shaped parts.
        • The P.C.D. of the new screw holes may not coincide exactly with the other existing holes
      • Consult with Fukushima-san again. Takahashi will contact Fukushima-san
        • 型振り放電加工機 may be better
        • Will test machine the dirty recoil mass. Will have another meeting with Fukushima-san (Takahashi)
      • Do we need to widen the slits for PRC RMs ? -> Depends on how difficult it is to rework the RM.

  • Flag design (Mark)
    • Mark's drawings

    • Make shorter by small changes
    • Widen the OSEM opening (Akutsu)
  • BS dummy optics design (Fabian)
  • IP base clamp (Fabian): Reduce the number of clamps-> Hirata-san finished 2D drawings. Trying to get quotation now.-> Still waiting for the quotation.

  • Bread board spring (Takahashi): Hirata-san is getting quotations.Asked quotation with the above one all at once.
  • Issue with adjustment screws on lower optical bench (bench can only be adjusted down from nominal due to lack of holes in bench below new position of screws holding wires)
  • #BS Assembly Frame Design (Aso, Hirata)
  • #BS gluing jigs (Tatsumi)
  • #Not enough crane height problem (Hirata, Saito)
  • #BS clean bag (Aso)

Type A

  • Task list (Takahashi)

  • #Type-A Filters Optimal Load Measurements
    • #Takahashi will make a plan for the optimal load check and ask ATC.-> Check two filters per month from April 2016. -> Will be presented to the ATC steering committee.

    • #How to manufacture the long maraging wires ?
      • One prototype was machined by Ojima
      • Aoshima can do the heat treatment for the long rod. Will ask them soon (Takahashi) -> Still waiting for a quotation.

      • How to test it ?
        • We can use the prototype assembly frame in TAMA.

Type-Bp modification

  • PR2 Wire breaker problem
    • Prism removal from PR2 (Hirose, Mark)
      • We need to send the spare mirror and the containers back to Kashiwa soon.
        • Bring back to Mitaka on 2/26.
      • Bring back CLIO suspension too (Takahashi) -> Not this time

Other

  • Safety
  • #GAS blade inspection by Virgo (Takahashi)
    • Shipped the blades. Will get results in 1-2 months.

Next meeting

2015/3/4 (Fri) 13:30 -

Next F2F 2016/4/1