Line 9: | Line 9: |
* Schedule status (Aso) [[attachment:bKAGRA15summer-VIS-20151211.pdf|bKAGRA VIS]] | * Schedule status (Aso) |
Line 12: | Line 12: |
* PR3 Operation Status (Fujii) * Watchdog tripped. Will disable the watchdog (not yet done ?) * Traverser and Stepper motor remote control (Shoda) -> Not yet succeeded (TAMA prototype method cannot be used in KAGRA). Tested in Mitaka, and updated later. * Still trying to fix communication problem of the TCP/IP-Serial converter. * PR3 OpLev now use a collimator for a large beam to increase the range at the expense of noise. We may need to change it back to the original one if we want to reduce the noise. Probably not necessary for iKAGRA. |
* PR3 Operation Status (Aso) * DAC problem * Yaw picomotor does not work ? * Traverser and Stepper motor remote control (Shoda) |
Line 27: | Line 26: |
* Watchdog disabled * Changed the collimator of the OpLev to increase the range: now roughly +/-250urad |
|
Line 31: | Line 28: |
* Travel (Week of 3/14) | * Travel (Week of 3/21) |
Line 35: | Line 32: |
* Fabian: | * Fabian:22-24 (Shift) |
Line 37: | Line 34: |
* Fujii: | * Fujii:24-27 (Shift) |
Line 42: | Line 39: |
* Travel (Week of 3/21) | * Travel (Week of 3/28) |
Line 62: | Line 59: |
* Guardian script for PR3 (Shoda, Okutomi, Fujii) -> DONE(16/03/08) * Watching the digital watchdog status. Recover the damping control if the watchdog is tripped. * http://klog.icrr.u-tokyo.ac.jp/osl/?r=950 |
* Guardian script for PR3 (Shoda, Okutomi, Fujii) * Burt restore implemented ? |
Line 70: | Line 65: |
* Need to think about who will be rensposible for the electronics of each suspension | * #Who will manage the electronics of each suspension |
Line 73: | Line 68: |
* We need to count electronics and cables needed for the tests, such as temporary sensors and so on. * Operation manual for digital system is necessary |
* #We need to count electronics and cables needed for the tests, such as temporary sensors and so on. |
Line 83: | Line 77: |
* #OSEM assembly status (Akutsu) | * OSEM assembly (Akutsu) * Schedule for each suspension is necessary |
Line 88: | Line 83: |
* Quick summary, week to 3/18 * Hirata-san made assembly drawings of IM and IMR. IM is almost finished. IMR is still on going. * Fabian designed the ballast masses for the payload. * Mark confirmed flag concept #4 was easy to make and made concept #5 with no flag tip. * Mark/Fabian worked on procedure docs * Mark surveyed BS clean booth area while at Kamioka (still need longer trip to discuss with site people). * Assorted quotes received. |
|
Line 90: | Line 92: |
* '''Takahashi will call the company to have a meeting ''' | * Meeting with company set for 3/24 in Yokohama. |
Line 99: | Line 101: |
* Mark made a medium footprint flag design "BS Optic Flag Concept 4 (Small Magnet, Small Hole).pdf". | * Hirata-san confirmed with ATC that "BS Optic Flag Concept 4 (Small Magnet, Small Hole).pdf" would be easy to make. |
Line 113: | Line 115: |
* Mark made stub flag (no vane for sensor): "BS Optic Flag Concept 5 (Small Magnet, Stub).pdf" * Tatsumi-san is OK with both designs - just need to choose. |
|
Line 115: | Line 119: |
* Hirata-san is waiting for quotes from three companies | * Hirata-san received one quote, is waiting on a second. |
Line 118: | Line 122: |
* Ballast masses for payload (new item) - Fabian designed [[https://onedrive.live.com/redir?resid=1447B05D5B571A84!294&authkey=!AJuhVfGeF5Nay9A&ithint=file%2cpdf|Dropbox link]] | |
Line 122: | Line 127: |
* Mirapro contacted - will remove rings from clean booth ≈3/12, inspect and quote. | * Received quote from Mirapro. Rings were removed from KAGRA. |
Line 124: | Line 129: |
* Hirata-san has adjusted design and made new drawings. | * No progress since last week but Hirata-san will ask for quote from Mirapro. |
Line 129: | Line 134: |
* Mark did initial mass budget ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4966|E1604966]]) and wrote up some specs for load gauge adapter. | * Mass budget ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4966|E1604966]]). |
Line 132: | Line 137: |
* Hirata-san contacted Mirapro: they will suggest a date after the iKAGRA vacuum work is done this week. | * Mirapro postponed setting a meeting date till after 3/25. |
Line 134: | Line 139: |
* Hirata-san worked on IM assembly drawing for BS | * Assembly drawings * Hirata-san worked on IM assembly drawing for BS - nearly finished. * IRM on-going. |
Line 136: | Line 143: |
* Hirata-san made much more up-to-date version of BS in chamber. * Has cable clamps, lower breadboard stuff. |
|
Line 139: | Line 144: |
* '''BS team need to trip to the site in the first week of April for checking the installation procedure'''. Having a draft procedure document ready before this is important. | * Procedure documents * '''BS team need to visit the site in the first week of April for checking the installation procedure'''. * Mark worked on main assembly. * Fabian worked on payload assembly. |
Line 184: | Line 192: |
* A student hit his head on the edge of an OpLev table at the end station. Always wear a helmet. |
VIS Meeting on 2016/3/18
2016/3/18 13:30 -
Kamioka NAOJ Room & SeeVogh
Participants:
Schedule
- Schedule status (Aso)
PR3
- PR3 Operation Status (Aso)
- DAC problem
- Yaw picomotor does not work ?
- Traverser and Stepper motor remote control (Shoda)
Plan for the next week
Mon:Operation of PR3 (Aso)
- Tue: Operation of PR3 (Aso)
- Wed: Operation of PR3 (Aso)
- Thu: Operation of PR3 (Aso)
- Fri: Operation of PR3 (Aso)
iKAGRA ETM suspension
- Current status (Ohishi)
Travel Plans
- Travel (Week of 3/21)
- Takahashi:
- Shoda:
- Mark:
Fabian:22-24 (Shift)
- Okutomi:
Fujii:24-27 (Shift)
- Ishizaki:
- Hirata:
- Ohishi:
- Travel (Week of 3/28)
- Takahashi:
- Shoda:
- Mark:
- Fabian:
- Okutomi:
- Fujii:
- Ishizaki:
- Hirata:
- Ohishi:
Electronics
- What are necessary in the next few weeks ?
- Nothing
- Watch dog system (Tanaka)
Tested the prototype board with test input -> Worked fine
Put a document on the JGW-Doc
- Guardian script for PR3 (Shoda, Okutomi, Fujii)
- Burt restore implemented ?
- Electronics diagram and review
Electronics document tree for VIS by Mark (http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4937)
Updated PR3 schematic with OpLev wiring (http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4795)
- #Who will manage the electronics of each suspension
- Type-Bp will be controlled by Shoda but the diagram update will be done by Mark
- Type-A may be maintained by a new engineer. Will be discussed with the person later.
- #We need to count electronics and cables needed for the tests, such as temporary sensors and so on.
bKAGRA preparation
- Three big categories of the tasks
- Type-A: Leader = Takahashi, Okutomi, Ishizaki, a new engineer
- Type-B (BS and SRC): Leader = Mark, Fabian, Hirata
- Type-Bp modification: Leader = Shoda, Fujii, A new technician (?)
Common Issues
- OSEM assembly (Akutsu)
- Schedule for each suspension is necessary
Type-B
- Quick summary, week to 3/18
- Hirata-san made assembly drawings of IM and IMR. IM is almost finished. IMR is still on going.
- Fabian designed the ballast masses for the payload.
- Mark confirmed flag concept #4 was easy to make and made concept #5 with no flag tip.
- Mark/Fabian worked on procedure docs
- Mark surveyed BS clean booth area while at Kamioka (still need longer trip to discuss with site people).
- Assorted quotes received.
- BS prism preparation (Mark)
- We decided to order 6 to Shinko-sha
- Meeting with company set for 3/24 in Yokohama.
Aso will check with Ohashi-san about the budget -> we can place an order now.
- We will use the sapphire prisms for the test hanging too
- Since we need to go forward on the BS and we can't make a decision on SR, we decided to go with tall 6.28 mm prisms, which saves adjusting other parts.
- We decided to order 6 to Shinko-sha
- Can we make SR wire breakers bigger ?
- Fukushima-san preparing test: 3/4/2016 + 1 month = ≈4/1/2016
- Flag design
- Optic flag design
- Hirata-san confirmed with ATC that "BS Optic Flag Concept 4 (Small Magnet, Small Hole).pdf" would be easy to make.
- IM Flag design
- Fabian improved rigid IM flag design ("BS_IM_flag_Concept_Screwed2.pdf")
- Mark would (still) like to make a test flag with magnetic attachment.
- Mark designed a tool for aligning the magnetically self-assembling IM flag design (drawing to be posted, hopefully before meeting).
- Widen the OSEM opening (Akutsu)
- Discussed a possibility to remove the sensing function from the mirror OSEM.
- Chop off the flag part from the magnet holder
- Safer (less possibility of flag damage)
- Wider range
OpLev with two QPD sensors may be used instead to sense the longitudinal motion (Virgo is doing this)
- Question is whether the sensing noise is good enough or not
- Raffaele will look for documents/data in Virgo
Akutsu will consider if this option is possible in KAGRA OpLev
- Mark made stub flag (no vane for sensor): "BS Optic Flag Concept 5 (Small Magnet, Stub).pdf"
- Tatsumi-san is OK with both designs - just need to choose.
- Chop off the flag part from the magnet holder
- BS dummy optics design (Fabian)
- Hirata-san received one quote, is waiting on a second.
- BS secondary prisms (no action)
- EQ stop screws, extensions and lock nuts - designed, drawn; will order in new financial year (April)
Ballast masses for payload (new item) - Fabian designed Dropbox link
- Lower breadboard stuff
- Breadboard spring bases and associated cable clamps: in manufacture
- Breadboard springs: in manufacture
- Damper ring needs to have central hole enlarged to allow passage of suspension during installation.
- Received quote from Mirapro. Rings were removed from KAGRA.
- Nail-head parts too short
- No progress since last week but Hirata-san will ask for quote from Mirapro.
- Extension springs for IM pico motors: need to do new drawing from Promec, have made
- BS Assembly Frame Design (Mark, Hirata)
- Design is almost complete
- Need to add some mechanism to hook a load gauge
Mass budget (E1604966).
- Need to add some attachment points (e.g., ferromagnetic plates) for placing wind-shield panels.
- Need to check the structural strength, did mass budget (see above)
- Mirapro postponed setting a meeting date till after 3/25.
- 2D and 3D CAD
- Assembly drawings
- Hirata-san worked on IM assembly drawing for BS - nearly finished.
- IRM on-going.
- BS 3D Assembly
- Needs updates for BF and SF blade spring configuration.
- Assembly drawings
- Procedure documents
BS team need to visit the site in the first week of April for checking the installation procedure.
- Mark worked on main assembly.
- Fabian worked on payload assembly.
- #BS gluing jigs (Tatsumi)
- #Not enough crane height problem (Hirata, Saito)
- #BS clean bag (Aso)
Type A
Task list (Takahashi)
- Thinking about a possibility of testing the long filter chain using the prototype EQ stop in Kashiwa.
Organize a kick-off meeting in the later half of March, concentrating on the room temperature part. (Takahashi) -> Plese reply to the Doodle request.
- Prototype long maraging rods (heat treated) were delivered from Aoyama
- Will start the test in the TAMA west end room using the dummy loads we have.
- Check the drift of the length
- Simultion: Okutomi will work with Fujii
- Will have a draft simulation results by the Type-A kick-off meeting.
- #Type-A Filters Optimal Load Measurements
#Takahashi will make a plan for the optimal load check and ask ATC.-> Check two filters per month from April 2016. -> Will be presented to the ATC steering committee.
- #How to manufacture the long maraging wires ?
- One prototype was machined by Ojima
Aoyama can do the heat treatment for the long rod. Will ask them soon (Takahashi) -> Still waiting for a quotation.
- How to test it ?
- We can use the prototype assembly frame in TAMA.
Type-Bp modification
- Traverser motor driver (Shoda)
- Need a box for stepping motor driver. Miyakawa-san is thinking about ordering chassis and boxes for motors. We discussed and agreed that the design of the boxes will be unified. The boxes will be designed and ordered together with those. (16/03/10)
- Miyakawa-san wants to have a driver and a motor to test
- PR2 Wire breaker problem
- Prism removal from PR2 (Hirose, Mark)
- Spare mirror is now back to Kashiwa
- Prism removal from PR2 (Hirose, Mark)
- CLIO suspension
- Ishizaki-san will come to pick it up
- Modification for bKAGRA
- Uraguchi-san proposed us the new IP plan
- Shoda updated the proposal(concerns?) for the BF active damping plan
- Will have a brainstorming after the JSPS meeting
- Review in April
Other
- Safety
- #GAS blade inspection by Virgo (Takahashi)
- Shipped the blades. Will get results in 1-2 months.
Next meeting
2016/3/25 (Fri) 13:30 -
Next F2F 2016/4/1