Line 181: Line 181:
   * '''Will give them to MIyakawa-san when Shoda-san come to Kamioka for the shifts -> Done ?'''    * Will give them to MIyakawa-san when Shoda-san come to Kamioka for the shifts
    
-> Done (3/28)
    * Shoda is also asking Uraguchi-san to provide one more Traverser motor driver for the test.

VIS Meeting on 2016/4/1

2016/4/1 13:30 -

Room 210 & eZuce

Participants:

Schedule

  • Schedule status (Aso)

PR3

  • PR3 Operation Status (Aso)
    • The fuse of the k1pr0 machine has been tripped.
    • Guardian script is updated (Shoda)
      • saving safe snapshot automatically.
      • The pre-tripped state is added in order to protect from the sudden shut down of the outputs. If PR3 enters the pre-tripped state, it turn off the outputs gradually.
  • Traverser and Stepper motor remote control (Shoda): Not applied yet.
  • April commissioning break plan (Shoda)
    • Offload LVDT using the stepping motor
    • Add BIO in order to reset analog WD in the LVDT coil driver
      • Add the BIO board
      • Modify the realtime model
    • Put the tilt meter (which is borrowed from Araya-san) in order to check the tilt of the inner frame during the evacuation.
      • (information for the Type-Bp modification)
    • If possible: LVDT sensitivity optimization
    • If possible: remote control system for motors

Plan for the next week

  • Mon:
  • Tue:
  • Wed:
  • Thu:
  • Fri:

iKAGRA ETM suspension

  • Current status (Ohishi)
  • PZT activation at EY (Ohishi)

Travel Plans

  • Travel (Week of 4/4)
    • Takahashi:
    • Shoda:
    • Mark:
    • Fabian:
    • Okutomi:
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Ohishi:
  • Travel (Week of 4/11)
    • Takahashi:
    • Shoda:
    • Mark:
    • Fabian:
    • Okutomi:
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Ohishi:

Electronics

bKAGRA preparation

  • Three big categories of the tasks
    • Type-A: Leader = Takahashi, Okutomi, Ishizaki, a new engineer
    • Type-B (BS and SRC): Leader = Mark, Fabian, Hirata
    • Type-Bp modification: Leader = Shoda, Fujii, A new technician (?)

Common Issues

  • Policy of the screw types to be used (Mark)
  • OSEM assembly (Akutsu)
    • Schedule for each suspension is necessary
    • Each leader must tell Akutsu-kun when and how many OSEMs they need by the next meeting.

Type-B

  • KAGRA/Subgroups/VIS/TypeB

  • Task list/schedule

  • Past Week Summary
    • Mark worked on schedule and task list(see above) - aiming to start suspending around 5/22.
    • Takahashi-san met with Shinkosha and worked out a plan for prisms. .
    • Hirata-san released assembly drawings for checking:
    • Hirata-san also did drawings for two types of BS optic flags (regular and stub) and IM flags (rigid and magnetic) (D1503487, D1605087, D1605088, ?? - not yet posted)
    • Mark checked the above for completeness and screw info - a handful of errors will be corrected.
    • Hirata-san worked to finalize drawings for BS clamp modifications. Now that the prism size is back to 5 mm we want to reinstate lowering the clamp surfaces by 1.28 mm. Some pins will need to be removed to allow this - IJECT is checking feasibility.
    • Fabian did analysis of RM wire thickness versus pitch mode frequency
  • BS prism preparation (Mark)
    • 6 prisms were ordered, to arrive just after Golden Week. Prisms will be polished and cut parallel to the correct axis for strength. Size will be 5 mm for compatibility with SR. Plan is to use for test hanging but have metal dummy prisms as a backup.
  • Can we make SR wire breakers bigger ?
    • Fukushima-san preparing test: 3/4/2016 + 1 month = ≈4/1/2016-> Any news on thi

  • Flag design
    • BS Flag Redesign on OneDrive

    • Optic flag design
      • Drawings done - two types.
    • IM Flag design
      • Drawings done - two types.
    • Widen the OSEM opening (Akutsu)
    • A new local length sensing
      • Need to decide the strategy for BS: three choices
        • Use OSEMs as originally planned
        • Use OpLev, No OSEM flag

        • Use reflection type sensors, No OSEM flag
      • Decide later!
  • BS dummy optics design (Fabian)
  • BS dummy and secondary prisms
    • Dummy prisms will be 5 mm to match SR - need to adjust BS clamp blocks.
    • Mark trying to find out from Tatsumi-san what height of prism is assumed by current jig.
  • EQ stop screws, extensions and lock nuts - designed, drawn; will order in new financial year (April)
  • Ballast masses for payload
    • Hirata-san created drawings DropBox link

    • Drawing check by Mark, not yet ordered.
  • Lower breadboard stuff
    • Breadboard spring bases and associated cable clamps: in manufacture
    • Breadboard springs: in manufacture
    • Damper ring mods: in manufacture, expects 4/28
    • Nail-head parts: quote from Mirapro received, not yet ordered
  • BS Assembly Frame Design (Mark, Hirata)
    • Mark wrote requirements doc for Mirapro: E1605037

    • Meeting with Mirapro 4/1, 11 am at Mitaka.
    • Need to add some mechanism to hook a load gauge
    • Need to request some attachment points (e.g., ferromagnetic plates) for placing wind-shield panels.
    • Need to request work platforms for standing on.
    • Need to request rack for holding vacuum feedthroughs during testing.
    • Need to request frame to hold clean bag.
    • Need to check the structural strength.
    • Clean bag needs to be ordered soon. Mark will make a design. Aso will contact the company.
  • 2D and 3D CAD
    • Assembly drawings
      • Individual mass assemblies for payload all done.
    • BS 3D Assembly
      • Needs updates for BF and SF blade spring configuration.
  • Procedure documents
    • Fabian worked on payload assembly.
  • BS gluing jigs (Tatsumi)
  • Not enough crane height problem (Hirata, Saito)

Type A

  • Task list (Takahashi)

  • Thinking about a possibility of testing the long filter chain using the prototype EQ stop in Kashiwa.
    • The prototype EQ stop will be transported from Kashiwa to Kamioka on 31th March.
    • Pre-assembly of the EQ stop prototypr on 6-7 April.
    • Demonstration of installation procedure using prototype filters (SFx1 + BFx2) from May.
  • The kick-off meeting will be held on 31th March.
  • The test of prototype long maraging rod was started. Detail is here: http://klog.icrr.u-tokyo.ac.jp/osl/index.php?r=1185

    • Load dependence was measured using a laser position sensor. Extension of 2.84mm was observed for the load of 272.8kg. The extension is consistent with the calculation (2.75mm).
  • Please notice humidity keeping maraging steel to avoid cracking noise.
  • Simultion: Okutomi will work with Fujii
    • Will have a draft simulation results by the Type-A kick-off meeting.
      • Got simulation information from Fujii-kun and Cryo group.
      • Now able to run simulation code
      • Need to confirm parameters with the actually delivered ones (like the weight): Some parameters are not consistent between some data.
  • #Type-A Filters Optimal Load Measurements
    • #Takahashi will make a plan for the optimal load check and ask ATC.-> Check two filters per month from April 2016. -> Will be presented to the ATC steering committee.

Type-Bp modification

  • Traverser motor driver (Shoda)
    • Need a box for stepping motor driver. Miyakawa-san is thinking about ordering chassis and boxes for motors. We discussed and agreed that the design of the boxes will be unified. The boxes will be designed and ordered together with those. (16/03/10)
    • Miyakawa-san wants to have a driver and a motor to test
      • Will give them to MIyakawa-san when Shoda-san come to Kamioka for the shifts
        • -> Done (3/28)

        • Shoda is also asking Uraguchi-san to provide one more Traverser motor driver for the test.
  • #PR2 Wire breaker problem
    • Prism removal from PR2 (Hirose, Mark)
      • Spare mirror is now back to Kashiwa
  • #CLIO suspension
    • Ishizaki-san will come to pick it up
  • Modification for bKAGRA
    • wiki

      • Uraguchi-san proposed us the new IP plan
      • Shoda updated the proposal(concerns?) for the BF active damping plan
    • Will have a brainstorming after the JSPS meeting -> Done (3/23)

      • We also discussed with Uraguchi-san, and tell him our concerns raised in our brainstorming discussion. (3/25)

    • Action items for Type-Bp modification
      • Calculate the upper limit of the resonant fequency for IP (Fujii)
      • Check if we need the magnetic damper for the bottom filter (Fujii)
      • Check the mass of the bottom plate and the cap of the standard filter -> Send Uraguchi-san (Shoda)

        • -> Done (3/31)

      • Check structure analysis of the EQ stop for active damping on BF (Shoda)
      • Check the minimam weight we need for the BFRM in order to damp the resonance enough (Shoda)
      • Check the capability to modify the BF cap (Shoda)
        • -> optimal load on the SF GAS filter checked. We have about 30kg margine. We have chance to modify the BF.

    • Review in April

Other

  • Safety
  • #GAS blade inspection by Virgo (Takahashi)
    • Shipped the blades. Will get results in 1-2 months.

Next meeting

2016/4/8 (Fri) 13:30 - F2F@Mitaka

KAGRA/Subgroups/VIS/VISMinutes20160401 (last edited 2016-04-08 17:28:49 by NobuyukiTanaka)