Progress report

Schedule Chart (PDF,MPP)

Type-A (Takahashi)

Type-B (Mark)

Type-Bp (Shoda)

IMMT (Ohishi)

Watchdog system (Tanaka)

Safety

Issues

Site work plan for the next week

BS crane will not be available: 13th -14th of June

Travel Plans

June 27-29: Fujii, Shoda

July 4 - 8: Takahashi, Ishizaki, Sato (site check for the installation of Type-A)

Mark is away: July 8-20

Next meeting