Agenda/Minutes of the VIS Meeting on 2016/9/2
2016/9/2 13:30 - @ Room 210
Participants:
Progress report
Type-A (Takahashi)
- Put a report here
Type-B (Mark)
- Put a report her
Type-Bp (Shoda)
- Put a report here
IMMT (Ohishi)
- Put a report here
Watchdog system (Tanaka)
- Put a report here
Safety
- Any issue ?
Discussion
- Installation order for Type-B and Type-Bp
BS(1-3) -> SR3(3-7) -> SR2(7-11) -> SRM (11-)
PR3 (12-3) -> PRM(3-5) -> PR2(5-7)
- We need to coordinate the BS area usage with PI assembly work and the transportation of the assembly frame.
- Aso, Mark, Takahashi will discuss it F2F.
Site work plan for the next week
- Mon: BS test hanging (Mark, Fabian, Zhao)
- Tue: BS test hanging (Mark, Fabian, Zhao)
- Wed: BS test hanging (Mark, Fabian, Zhao)
- Thu: F2F
- Fri: F2F
Travel Plans
- Travel (Week of 8/22):
Takahashi:25 - 27
Shoda:22 - 27
- Mark: 22 - 27
- Fabian: 22 or 23 - 27
- Okutomi: 25 - 27
- Fujii:
- Ishizaki:
- Hirata:
- Sato:
- Ohishi:
- Travel (Week of 8/29):
- Takahashi:
- Shoda:
- Mark: 29 - 9/2
- Fabian: 29 - 9/2
- Okutomi:
- Fujii:
- Ishizaki:
- Hirata:
- Sato:
- Ohishi:
Next meeting
2016/9/2(Fri) 13:30 -
Next F2F 2016/9/9