Agenda/Minutes of the VIS Meeting on 2016/9/2
2016/9/2 13:30 - @ Room 210
Participants:
Progress report
Type-A (Takahashi)
- Top chamber: Installation and leak test will be postponed to January due to delay of cooling test of the cryostat.
- EQ stop, release sensor, dummy payload: Procurement is in the bidding process. Open bidding is on 13th September.
- BF damper: Assembling the LVDT prototype.
- Maraging wire: Stress concentration around the head was pointed out by CRY. Now investigationg.
Type-B (Mark)
- Put a report her
Type-Bp (Shoda)
- Put a report here
IMMT (Ohishi)
- Put a report here
Watchdog system (Tanaka)
- Put a report here
Safety
- Any issue ?
Discussion
- Insufficient strength of the maraging rods ?
- Local sensor to monitor the TM motion during assembly
Site work plan for the next week
- Mon: BS test hanging (Mark, Fabian, Zhao)
- Tue: BS test hanging (Mark, Fabian, Zhao)
- Wed: BS test hanging (Mark, Fabian, Zhao)
- Thu: BS test hanging (Mark, Fabian, Zhao)
- Fri: BS test hanging (Mark, Fabian, Zhao)
Travel Plans
- Travel (Week of 9/5):
- Takahashi:
- Shoda:
- Mark: 5 - 8
- Fabian: 5 - 8
- Okutomi:
- Fujii:
- Ishizaki:
- Hirata:
- Sato:
- Ohishi:
- Travel (Week of 9/12):
- Takahashi:
- Shoda:
- Mark: 12 - 15
- Fabian: 12 - 15
- Okutomi:
- Fujii:
- Ishizaki:
- Hirata:
- Sato:
- Ohishi:
Next meeting
2016/9/9(Fri) 13:30 - in Mitaka