Agenda/Minutes of the VIS Meeting on 2016/9/2
2016/9/2 13:30 - @ Room 210
Participants:
Progress report
Type-A (Takahashi)
- Top chamber: Installation and leak test will be postponed to January due to delay of cooling test of the cryostat.
- EQ stop, release sensor, dummy payload: Procurement is in the bidding process. Open bidding is on 13th September.
- BF damper: Assembling the LVDT prototype.
- Maraging wire: Stress concentration around the head was pointed out by CRY. Now investigationg.
Type-B (Mark)
- Put a report her
Type-Bp (Shoda)
* Type-Bp modification
- Saito-san made some updates around the LVDT coils. Shoda is implimenting them into the 3D CAD model.
- Obuchi-san provided the result of the structure analysis. Shoda will gather the information and write the design document.
- Saito-san is asking the cost estimate to Techno-port and still waiting for the reply.
- We asked him to ask the cost estimate to another company.
- Shoda is preparing the specification sheets for the ordering.
- We are planing to have the final design reciew from 12 - 14th September.
* Additional ordering for PRs.
- additional masses for IM: Hirata-san made the drawing.
- additional masses for BF: Shoda is making the model.
- IM flags: Hirata-san will make the drawing for the additional machinig.
- TM flags: Discussion is ongoing with Aso-san, Mark, and Hirata-san. (Old design parts will be ordered together with BF modification parts just in case.)
- 1st wire breakers: will be ordered with BF modification parts
- 2nd wire breakers: will be ordered with BF modification parts
- the correts for the hexagon cable clamps: the CAD model of the maraging rod is wrong. Re-design will be done by Hirata-san.
- maraging rods for BFRM: will be ordered with Type-A maraging rods.
- signal cables: will be ordered with Type-A.
- BF EQ stop ring: will be ordered together with the assembly frame.
* Assembly frame
- Design is almost fixed: shown via Seevogh
* Optical bench
- Installation jigs: shown via Seevogh
- Adapters: shown via Seevogh
- wires: shown via Seevogh (the hook analysis is necessary?)
- missing hooks: shown via Seevogh
- Shoda is preparing the specification sheets for the ordering (together with the assembly frame).
* Washing
- EQ stop: 3sets are in Akeno, un-washed. Takahashi-san will order the washing.
- OB-IM, OB-MD: 3sets are not ordered yet. Takahashi-san will order them.
* Bottom filter weight
The thickness of the top plate of the cup is different from the design. (12mm -> 11mm)
* Mirror preparation
- Hirose-san and Shoda are preparing jigs for the flag detaching. [[|Catoon]]
* A/I
- Prepare for the final design review. (Shoda)
- Make the design document (Shoda, Fujii)
- Ordering preparation (Shoda)
- Design work around flags (Hirata, Mark)
IMMT (Ohishi)
- Put a report here
Watchdog system (Tanaka)
Progress report(For Power circuit re-design)PDF
Safety
- Any issue ?
Discussion
- Insufficient strength of the maraging rods ?
- Local sensor to monitor the TM motion during assembly
Site work plan for the next week
- Mon: BS test hanging (Mark, Fabian, Zhao)
- Tue: BS test hanging (Mark, Fabian, Zhao)
- Wed: BS test hanging (Mark, Fabian, Zhao)
- Thu: BS test hanging (Mark, Fabian, Zhao)
- Fri: BS test hanging (Mark, Fabian, Zhao)
Travel Plans
- Travel (Week of 9/5):
- Takahashi:
- Shoda:
- Mark: 5 - 8
- Fabian: 5 - 8
- Okutomi:
- Fujii:
- Ishizaki:
- Hirata:
- Sato:
- Ohishi:
- Travel (Week of 9/12):
- Takahashi:
- Shoda:
- Mark: 12 - 15
- Fabian: 12 - 15
- Okutomi:
- Fujii:
- Ishizaki:
- Hirata:
- Sato:
- Ohishi:
Next meeting
2016/9/9(Fri) 13:30 - in Mitaka