Agenda/Minutes of the VIS Meeting on 2016/10/14
2016/10/14 13:30 -
Participants:
Progress report
Type-A (Takahashi)
- Put a report here
Type B (Mark)
- Put a report here
Type-Bp (Shoda)
- Put a report here
IMMT (Ohishi)
- 2D/3D drawings
- Uploaded slightly simplified step and dwg files to Dropbox (Subsystems/VIS/TypeC/).
- Please notice that these still remain some small mistakes.
Watchdog system (Tanaka)
- Put a report here
Safety
- Any issue ?
Discussion
- Maraging and SUS rod issue follow up.
- Order status: Type-B Maraging rods, SUS rods
- Type-A Maraging rod re-optimization status (Takahashi)
- Nail head diameter 9mm (possible ?)
Site work plan for the next week
- Mon: BS test hanging
- Tue: BS test hanging
- Wed: BS test hanging
- Thu: BS test hanging
- Fri: BS test hanging
Travel Plans
- Travel (Week of 10/17):
- Takahashi:
- Shoda:
- Mark: 17-21
- Fabian: 17-21
- Okutomi:
- Fujii:
- Ishizaki:
- Hirata:
- Sato:
- Ohishi:
- Travel (Week of 10/24):
- Takahashi:
- Shoda:
- Mark: 24-27 (BS)
- Fabian: 24-27 (BS)
- Okutomi: 24-27 (PI realtime model development)
- Fujii:
- Ishizaki:
- Hirata:
- Sato:
- Ohishi:
Next meeting
2016/10/21(Fri) 13:30 - VIS F2F: Oct. 28, Nov. 18, Dec. 2