Participants: Participants: Takahashi, Mark, Sato, Tanaka, Okutomi, Ishizaki, Aso
Line 12: Line 12:
 * Put a report here  * [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/TypeA/Meeting|Minutes of Type-A Meeting]]
 * Pre-isolator: The top filter was mounted onto the IP. The shaft screw of motor was not matching to the slider for fishing rod. New shafts were ordered.
 * EQ stop, release sensor, dummy payload: Production is on going.
 * BF damper: Open bidding is on 9th November.
 * Maraging wire: Hirata-san made 2D drawings. The wires will be ordered soon.
 * Installation: Making assembly drawings for the installation procedure document. The review is held on 4th November.
Line 15: Line 20:
 * Put a report here  * Type B Past Week Summary
  * Fabian, Mark and Liu-kun did BS installation at Kamioka:
   * Debugged the issue with the BF keystone being tilted enough to cause rubbing on the yoke for the magnets. It was solved by moving the yoke ≈1 mm taking advantage of the oversized holes.
   * Measured the height of the payload as a function of trim mass. The BF spring seems to have a slightly lower load capacity and a rather higher spring constant than when it was remeasured by Hirata-san.
   * Removed IM trim mass to set the average height of the keystone to the CAD value.
   * Moved IM trim mass around to set the pitch of the dummy BS and the roll of the IM.
   * Constructed the rest of the IRM around the IM.
  * Hirata-san
   * Prepared to get quotes for different types of "flying saucer" cable clamps (D1504530, D1605625, D1605734).
   * Finished BS assembly drawings (in-tank version) and sent to Saito-sensei).
   * Finished maraging rod 3D models and drawings (for Type A)
   * Modified top plate drawings for PRM inner frame.
Line 18: Line 34:
 * Put a report here  * BFRM
  * Still waiting for ordering process.

 * Stab Flags
  * Waiting for the cost estimation.

 * Assembly frame
  * Asking cost estimate. Also asking to upgrade the assembly frame in the end of November.

 * Install procedure
  * pictures how to install whole suspension chain into the chamber is circulated.
   We will ask the company about the accerelation of the crane, the chain block, and the lever block.
   According to their information, we will buy a chain block or a lever block and test them at Mitaka.

 * Flag removing jig.
  * The model is made by Shoda and approved by Hirose-san. Now the 2D drawing is being made.
Line 23: Line 55:
 * Put a report here  *Conference material PCB Design Draft version.(Oct 21th 2016)[[http://gwdoc.icrr.u-tokyo.ac.jp/DocDB/0057/E1605760/001/Project_WDS_PCB_Design_Ver_0th-161021.pdf|PDF]]
 *Design and preparation(investigation of procurement) for production.[[http://gwdoc.icrr.u-tokyo.ac.jp/DocDB/0057/E1605791/002/Project_WDS_H_W_Assignment_Design_Ver0_1-20161028-1.pdf|PDF]]
Line 32: Line 65:
 * Type-Bp installation tool: Lever block or Chain block (Shoda)
Line 43: Line 77:
  * Shoda:
  * Mark: 31-11/4 (BS)
  * Shoda: 10/31 - 11/4? (PR3 disassemble)
  * Mark:
Line 46: Line 80:
  * Okutomi: 31-11/4 (PI realtime model development)   * Okutomi:
Line 50: Line 84:
  * Sato: 31-11/4 (Accelerometer test)   * Sato:
Line 54: Line 88:
  * Takahashi: 7-8 (Extended chief meeting/Fire drill)
  * Shoda: 7-8 (Extended chief meeting/Fire drill)
  * Mark: 8? (Fire drill)
  * Takahashi: 7-9 (Extended chief meeting/Fire drill/Accelerometer test)
  * Shoda: 7-11 (Extended chief meeting/Fire drill/PR3 disassemble)
  * Mark: 8 - 11 (Fire drill/BS)
Line 58: Line 92:
  * Okutomi: 8? (Fire drill)   * Okutomi: 7 - 11 (Extended chief meeting/Fire drill/Accelerometer test/Realtime code)
Line 60: Line 94:
  * Ishizaki: 8? (Fire drill)   * Ishizaki: 7-8? (Extended chief meeting/Fire drill)
Line 62: Line 96:
  * Sato: 8? (Fire drill)   * Sato: 7-9 (Fire drill/Accelerometer test)

Agenda/Minutes of the VIS Meeting on 2016/10/28

2016/10/28 13:30 - @Mitaka F2F.

Participants: Takahashi, Mark, Sato, Tanaka, Okutomi, Ishizaki, Aso

Progress report

Schedule Chart (PDF,MPP)

Type-A (Takahashi)

  • Minutes of Type-A Meeting

  • Pre-isolator: The top filter was mounted onto the IP. The shaft screw of motor was not matching to the slider for fishing rod. New shafts were ordered.
  • EQ stop, release sensor, dummy payload: Production is on going.
  • BF damper: Open bidding is on 9th November.
  • Maraging wire: Hirata-san made 2D drawings. The wires will be ordered soon.
  • Installation: Making assembly drawings for the installation procedure document. The review is held on 4th November.

Type B (Mark)

  • Type B Past Week Summary
    • Fabian, Mark and Liu-kun did BS installation at Kamioka:
      • Debugged the issue with the BF keystone being tilted enough to cause rubbing on the yoke for the magnets. It was solved by moving the yoke ≈1 mm taking advantage of the oversized holes.
      • Measured the height of the payload as a function of trim mass. The BF spring seems to have a slightly lower load capacity and a rather higher spring constant than when it was remeasured by Hirata-san.
      • Removed IM trim mass to set the average height of the keystone to the CAD value.
      • Moved IM trim mass around to set the pitch of the dummy BS and the roll of the IM.
      • Constructed the rest of the IRM around the IM.
    • Hirata-san
      • Prepared to get quotes for different types of "flying saucer" cable clamps (D1504530, D1605625, D1605734).
      • Finished BS assembly drawings (in-tank version) and sent to Saito-sensei).
      • Finished maraging rod 3D models and drawings (for Type A)
      • Modified top plate drawings for PRM inner frame.

Type-Bp (Shoda)

  • BFRM
    • Still waiting for ordering process.
  • Stab Flags
    • Waiting for the cost estimation.
  • Assembly frame
    • Asking cost estimate. Also asking to upgrade the assembly frame in the end of November.
  • Install procedure
    • pictures how to install whole suspension chain into the chamber is circulated.
      • We will ask the company about the accerelation of the crane, the chain block, and the lever block. According to their information, we will buy a chain block or a lever block and test them at Mitaka.
  • Flag removing jig.
    • The model is made by Shoda and approved by Hirose-san. Now the 2D drawing is being made.

IMMT (Ohishi)

  • Put a report here

Watchdog system (Tanaka)

  • Conference material PCB Design Draft version.(Oct 21th 2016)PDF

  • Design and preparation(investigation of procurement) for production.PDF

Safety

  • Any issue ?

Discussion

  • Suspension naming convention (Okutomi)
  • Type-Bp installation tool: Lever block or Chain block (Shoda)

Site work plan for the next week

  • Mon: BS test hanging
  • Tue: BS test hanging
  • Wed: BS test hanging
  • Thu: BS test hanging
  • Fri: BS test hanging

Travel Plans

  • Travel (Week of 10/31):
    • Takahashi:
    • Shoda: 10/31 - 11/4? (PR3 disassemble)
    • Mark:
    • Fabian:
    • Okutomi:
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Sato:
    • Ohishi:
  • Travel (Week of 11/7):
    • Takahashi: 7-9 (Extended chief meeting/Fire drill/Accelerometer test)
    • Shoda: 7-11 (Extended chief meeting/Fire drill/PR3 disassemble)
    • Mark: 8 - 11 (Fire drill/BS)
    • Fabian:
    • Okutomi: 7 - 11 (Extended chief meeting/Fire drill/Accelerometer test/Realtime code)
    • Fujii: 8? (Fire drill)
    • Ishizaki: 7-8? (Extended chief meeting/Fire drill)
    • Hirata: 8? (Fire drill)
    • Sato: 7-9 (Fire drill/Accelerometer test)
    • Ohishi:

Next meeting

On 2016/11/4(Fri) VIS F2F: Nov. 18, Dec. 2