Size: 1613
Comment:
|
Size: 2989
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 12: | Line 12: |
* Put a report here | * [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/TypeA/Meeting|Minutes of Type-A Meeting]] * Pre-isolator: The top filter was mounted onto the IP. The shaft screw of motor was not matching to the slider for fishing rod. New shafts were ordered. * EQ stop, release sensor, dummy payload: Production is on going. * BF damper: Open bidding is on 9th November. * Maraging wire: Hirata-san made 2D drawings. The wires will be ordered soon. * Installation: Making assembly drawings for the installation procedure document. The review is held on 4th November. |
Line 15: | Line 20: |
* Put a report here | * Type B Past Week Summary * Fabian, Mark and Liu-kun did BS installation at Kamioka: * Debugged the issue with the BF keystone being tilted enough to cause rubbing on the yoke for the magnets. It was solved by moving the yoke ≈1 mm taking advantage of the oversized holes. * Measured the height of the payload as a function of trim mass. The BF spring seems to have a slightly lower load capacity and a rather higher spring constant than when it was remeasured by Hirata-san. * Removed IM trim mass to set the average height of the keystone to the CAD value. * Moved IM trim mass around to set the pitch of the dummy BS. * Hirata-san * TBD. |
Line 32: | Line 44: |
* Type-Bp installation tool: Lever block or Chain block (Shoda) | |
Line 43: | Line 56: |
* Shoda: * Mark: 31-11/4 (BS) |
* Shoda: 10/31 - 11/4? (PR3 disassemble) * Mark: |
Line 46: | Line 59: |
* Okutomi: 31-11/4 (PI realtime model development) | * Okutomi: |
Line 50: | Line 63: |
* Sato: 31-11/4 (Accelerometer test) | * Sato: |
Line 54: | Line 67: |
* Takahashi: 7-8 (Extended chief meeting/Fire drill) * Shoda: 7-8 (Extended chief meeting/Fire drill) * Mark: 8? (Fire drill) |
* Takahashi: 7-9 (Extended chief meeting/Fire drill/Accelerometer test) * Shoda: 7-11 (Extended chief meeting/Fire drill/PR3 disassemble) * Mark: 8 - 11 (Fire drill/BS) |
Line 58: | Line 71: |
* Okutomi: 8? (Fire drill) | * Okutomi: 7 - 11 (Extended chief meeting/Fire drill/Accelerometer test/Realtime code) |
Line 60: | Line 73: |
* Ishizaki: 8? (Fire drill) | * Ishizaki: 7-8? (Extended chief meeting/Fire drill) |
Line 62: | Line 75: |
* Sato: 8? (Fire drill) | * Sato: 7-9 (Fire drill/Accelerometer test) |
Agenda/Minutes of the VIS Meeting on 2016/10/28
2016/10/28 13:30 - @Mitaka F2F.
Participants:
Progress report
Type-A (Takahashi)
- Pre-isolator: The top filter was mounted onto the IP. The shaft screw of motor was not matching to the slider for fishing rod. New shafts were ordered.
- EQ stop, release sensor, dummy payload: Production is on going.
- BF damper: Open bidding is on 9th November.
- Maraging wire: Hirata-san made 2D drawings. The wires will be ordered soon.
- Installation: Making assembly drawings for the installation procedure document. The review is held on 4th November.
Type B (Mark)
- Type B Past Week Summary
- Fabian, Mark and Liu-kun did BS installation at Kamioka:
- Debugged the issue with the BF keystone being tilted enough to cause rubbing on the yoke for the magnets. It was solved by moving the yoke ≈1 mm taking advantage of the oversized holes.
- Measured the height of the payload as a function of trim mass. The BF spring seems to have a slightly lower load capacity and a rather higher spring constant than when it was remeasured by Hirata-san.
- Removed IM trim mass to set the average height of the keystone to the CAD value.
- Moved IM trim mass around to set the pitch of the dummy BS.
- Hirata-san
- TBD.
- Fabian, Mark and Liu-kun did BS installation at Kamioka:
Type-Bp (Shoda)
- Put a report here
IMMT (Ohishi)
- Put a report here
Watchdog system (Tanaka)
- Put a report here
Safety
- Any issue ?
Discussion
- Suspension naming convention (Okutomi)
- Type-Bp installation tool: Lever block or Chain block (Shoda)
Site work plan for the next week
- Mon: BS test hanging
- Tue: BS test hanging
- Wed: BS test hanging
- Thu: BS test hanging
- Fri: BS test hanging
Travel Plans
- Travel (Week of 10/31):
- Takahashi:
- Shoda: 10/31 - 11/4? (PR3 disassemble)
- Mark:
- Fabian:
- Okutomi:
- Fujii:
- Ishizaki:
- Hirata:
- Sato:
- Ohishi:
- Travel (Week of 11/7):
- Takahashi: 7-9 (Extended chief meeting/Fire drill/Accelerometer test)
- Shoda: 7-11 (Extended chief meeting/Fire drill/PR3 disassemble)
- Mark: 8 - 11 (Fire drill/BS)
- Fabian:
- Okutomi: 7 - 11 (Extended chief meeting/Fire drill/Accelerometer test/Realtime code)
- Fujii: 8? (Fire drill)
- Ishizaki: 7-8? (Extended chief meeting/Fire drill)
- Hirata: 8? (Fire drill)
- Sato: 7-9 (Fire drill/Accelerometer test)
- Ohishi:
Next meeting
On 2016/11/4(Fri) VIS F2F: Nov. 18, Dec. 2