Line 15: Line 15:
 * Put a report here  * Type B Past Week Summary
  * Fabian, Mark and Liu-kun did BS installation at Kamioka:
   * Debugged the issue with the BF keystone being tilted enough to cause rubbing on the yoke for the magnets. It was solved by moving the yoke ≈1 mm taking advantage of the oversized holes.
   * Measured the height of the payload as a function of trim mass. The BF spring seems to have a slightly lower load capacity and a rather higher spring constant than when it was remeasured by Hirata-san.
   * Removed IM trim mass to set the average height of the keystone to the CAD value.
   * Moved IM trim mass around to set the pitch of the dummy BS.
  * Hirata-san
   * TBD.

Agenda/Minutes of the VIS Meeting on 2016/10/28

2016/10/28 13:30 - @Mitaka F2F.

Participants:

Progress report

Schedule Chart (PDF,MPP)

Type-A (Takahashi)

  • Put a report here

Type B (Mark)

  • Type B Past Week Summary
    • Fabian, Mark and Liu-kun did BS installation at Kamioka:
      • Debugged the issue with the BF keystone being tilted enough to cause rubbing on the yoke for the magnets. It was solved by moving the yoke ≈1 mm taking advantage of the oversized holes.
      • Measured the height of the payload as a function of trim mass. The BF spring seems to have a slightly lower load capacity and a rather higher spring constant than when it was remeasured by Hirata-san.
      • Removed IM trim mass to set the average height of the keystone to the CAD value.
      • Moved IM trim mass around to set the pitch of the dummy BS.
    • Hirata-san
      • TBD.

Type-Bp (Shoda)

  • Put a report here

IMMT (Ohishi)

  • Put a report here

Watchdog system (Tanaka)

  • Put a report here

Safety

  • Any issue ?

Discussion

  • Suspension naming convention (Okutomi)
  • Type-Bp installation tool: Lever block or Chain block (Shoda)

Site work plan for the next week

  • Mon: BS test hanging
  • Tue: BS test hanging
  • Wed: BS test hanging
  • Thu: BS test hanging
  • Fri: BS test hanging

Travel Plans

  • Travel (Week of 10/31):
    • Takahashi:
    • Shoda:
    • Mark: 31-11/4 (BS)
    • Fabian:
    • Okutomi: 31-11/4 (PI realtime model development)
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Sato: 31-11/4 (Accelerometer test)
    • Ohishi:
  • Travel (Week of 11/7):
    • Takahashi: 7-8 (Extended chief meeting/Fire drill)
    • Shoda: 7-8 (Extended chief meeting/Fire drill)
    • Mark: 8? (Fire drill)
    • Fabian:
    • Okutomi: 8? (Fire drill)
    • Fujii: 8? (Fire drill)
    • Ishizaki: 8? (Fire drill)
    • Hirata: 8? (Fire drill)
    • Sato: 8? (Fire drill)
    • Ohishi:

Next meeting

On 2016/11/4(Fri) VIS F2F: Nov. 18, Dec. 2